Task Assignment DC018A Summary
This Task Assignment (TA) is a state and local contract issued by the State of Florida Department of Environmental Protection (FDEP) to GHD Services, Inc., with contract number HW684. The task assignment, numbered DC018A, was executed on June 1, 2022, for groundwater monitoring services at the Boston Man Cleaners site located at 6081 W Sunrise Boulevard, Plantation, Broward County, Florida. The Department Project Manager is Kevin Kane, and the Contractor's Project Manager is Brian Moore. The task assignment is effective through December 1, 2022, with a final deliverable due date of September 1, 2022.
The scope of work consists of two subtasks: Subtask 1 involves project management calculated at 13% of direct labor costs, and Subtask 2 encompasses annual groundwater monitoring at five monitoring wells (MW001, MW010, MW015, MW016, and MW018), including depth-to-water measurements from all 18 available site monitor wells, groundwater sampling in accordance with FDEP Standard Operating Procedures, laboratory analysis for volatile organic hydrocarbons using EPA Method 8260, and preparation of a comprehensive Groundwater Monitoring Report. The total task assignment value is $5,757.32 on a fixed unit rate basis. Invoicing occurs upon submission and FDEP approval of the Groundwater Monitoring Report and Project Management deliverables. Cost components include total labor of $4,167.74, travel costs of $120.00, subcontractor services (Investigation Derived Waste disposal) of $121.00, laboratory analytical costs of $423.50, field expenses of $508.30, and a completion fee of $416.78.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC018A Completion December 1, 2022
GHD Services, Inc. will conduct groundwater sampling at the Boston Man Cleaners site located in Plantation, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on May 25, 2022.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_4086
6081 W Sunrise Blvd, Plantation, Broward County
Boston Man Cleaners
✔ $ 5,757.32
$ 5,757.32
Scope of Work
Brian Moore
Project Manager
Brian Moore Digitally signed by Brian Moore Date: 2022.06.01 09:57:11 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.06.01 07:35:29 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report + Project Management 09/01/2022
Subtasks 1 and 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 5,757.32
$ 5,757.32
HW684
DC018A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO: HW684 Contract File
FROM: Kevin Kane, Contract Manager
DATE: May 31, 2022
SUBJECT: Task Assignment DC018A Boston Man Cleaners
ERIC_4086
Monitoring
GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Groundwater Monitoring GHD will conduct annual groundwater sampling in accordance with previous recommendations and Department approval. Annual groundwater monitoring will be conducted at monitoring wells MW001, MW010, MW015, MW016, and MW018. Prior to sampling, depth to water measurements will be gathered from all available site monitor wells (18 total). Sampling will be conducted in general accordance with FDEP Standard Operating Procedures. Groundwater samples will be analyzed for the presence of volatile organic hydrocarbons by EPA Method 8260. The results of the sampling will be summarized in a Groundwater Monitoring Report that will be submitted to the Department for approval. The Groundwater Monitoring Report will include a summary of field and laboratory data. The report will also include recommendations for additional sampling.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis. The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed May 17, 2022.
This work will be conducted in line with the scope of work included with GHD’s proposal, received May 25, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is September 1, 2022, and the completion date for the task assignment is December 1, 2022.
The final cost total for Task Assignment DC018A is $5,757.32.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 05/27/22
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.12 Project Manager JM 4.50 4.5 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 13.00 13.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 12.50 12.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 43.00 4.50 38.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,557.45 $179.18 $1,378.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $2,021.57 $232.58 $1,788.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $588.72 $67.73 $520.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,167.74 $479.49 $3,688.25 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 1
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 05/27/22
Task #: SubTask 1 Project Management SubTask 6
Site: SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: SubTask 3 SubTask 8
Project Manager: SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $365.00 $365.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $58.50 $58.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $423.50 $423.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $468.30 $468.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $508.30 $508.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $5,340.54 $479.49 $4,861.05 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $416.78 $47.95 $368.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $5,757.32 $527.44 $5,229.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Boston Man Cleaners SUBTASK 2: Groundwater Monitoring
DATE: 05/27/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer JH Conclusions/Recommendations 1
Project Manager JM Sample kit coordination/contact property owner 1 Project Manager JM Verify COC/field sampling parameters/field notes 0.5 Project Manager JM Arrange for IDW disposal 1 Project Manager JM Historical assessment and remedial summary 1 Project Manager JM Field sampling scope of work and methodology 1 Project Manager JM Field parameter evaluation/discussion 1 Project Manager JM groundwater flow evaluation (shallow, intermediate, deep) 2.5 Project Manager JM groundwater analytical evaluation (shallow, intermediate, deep) 2.5 Project Manager JM QA/QC data verification 1 Project Manager JM Conclusions/Recommendations 1
12.5
Project Engineer/Scientist TC Mob/demob 2.5 Project Engineer/Scientist TC Water Levels all wells (18 total) 3 Project Engineer/Scientist TC Groundwater Sampling (5 wells) 7.5
Drafting Technician PM Groundwater flow maps (shallow, intermediate, deep) 3 Drafting Technician PM Groundwater analytical maps (shallow, intermediate, deep) 3
Staff Assistant DA Data Entry (7 wells and 18 water levels) 1 Staff Assistant DA Generate summary tables 1 Staff Assistant DA Document Preparation/Publishing (generate pdf) 2 Staff Assistant DA ADAPT/GIS Update 2
TOTAL LABOR 38.5
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal 1 drum $110.00 $110.00
TOTAL $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHS EPA 8260 $73.00 5 $365.00 MW001, 10, 15, 16, 18
Sample Shipping small cooler (2 day) $52.00 1 $52.00
Ice $6.50 1 $6.50
TOTAL LAB $423.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 1 $40.00
Equipment (Analytical Related)
Groundwater Sampling Kit $290.00 Day 1 $290.00 Poly Tubing $0.30 ft 211 $63.30 55-gallon drum $100.00 drum 1 $100.00 silicon Tubing $3.00 ft 5 $15.00
Equipment (Other) $0.00
TOTAL EQUIPMENT $508.30
FINAL --7/24/96
COST PROPOSAL FOR TASK DC018A
Boston Man Cleaners, 069500621
Groundwater Monitoring (Annual)
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD completed active remediation at the Boston Man Cleaners site in 2008. Active remediation included the operation of a Soil Vapor Extraction (SVE) system. Groundwater monitoring has been conducted following active remediation. The first year of groundwater monitoring was completed in April 2009. Task DC018A includes annual groundwater monitoring in accordance with GHD recommendations and FDEP correspondence dated September 21, 2021.
Subtask 1: Project Management Subtask 1 includes all activities associated with completion of groundwater sampling and reporting for the Boston Man Cleaners site.
Subtask 2: Groundwater Monitoring
Task DC018A includes annual groundwater monitoring in accordance with GHD recommendations and Department approval. Annual groundwater monitoring will be conducted at monitoring wells MW001, MW010, MW015, MW016, and MW018. Prior to sampling, depth to water measurements will be gathered from all available site monitor wells (18 total). Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures. Groundwater samples will be analyzed for the presence of volatile organic hydrocarbons by EPA Method 8260.
The results of the sampling will be summarized in a groundwater monitoring report that will be submitted to the Department for approval. The groundwater monitoring report will include a summary of field and laboratory data. The report will also include recommendations for additional sampling.
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
Groundwater Monitoring Report 9/1/22
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
May 23, 2022
Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida
Mr. Moore:
The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.
This pricing is valid for all regions in the State of Florida except for the Florida Keys.
Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
This quote is valid for 180 days.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png
$95.00 per drum plus $150.00 stop charge Have a great day
Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.
P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com
From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami
Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks
Brian Moore, PE
GHD
Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect
WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION
mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
This e-mail has been scanned for viruses
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
62 days Wed 6/8/22 Thu 9/1/22
3 Subtask 2:
Groundwater Sampling
49 days Mon 6/27/22
Thu 9/1/22
4 Field Work Preparation2 wks Mon 6/27/22Fri 7/8/22
5 Groundwater Sampling1 day Fri 7/15/22 Fri 7/15/22
6 Groundwater Monitoring Report
6 wks Fri 7/22/22 Thu 9/1/22
5/15 5/22 5/29 6/5 6/12 June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC018A at the Boston Man Cleaners facility located in Sunrise, Broward County
Project: TA_018A Date: Wed 5/25/22
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
62 days Wed 6/8/22 Thu 9/1/22
3 Subtask 2:
Groundwater Sampling
49 days Mon 6/27/22
Thu 9/1/22
4 Field Work Preparation2 wks Mon 6/27/22Fri 7/8/22
5 Groundwater Sampling1 day Fri 7/15/22 Fri 7/15/22
6 Groundwater Monitoring Report
6 wks Fri 7/22/22 Thu 9/1/22
Jenna Martin
Thomas Cozzie
6/19 6/26 7/3 7/10 7/17 July
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC018A at the Boston Man Cleaners facility located in Sunrise, Broward County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
62 days Wed 6/8/22 Thu 9/1/22
3 Subtask 2:
Groundwater Sampling
49 days Mon 6/27/22
Thu 9/1/22
4 Field Work Preparation2 wks Mon 6/27/22Fri 7/8/22
5 Groundwater Sampling1 day Fri 7/15/22 Fri 7/15/22
6 Groundwater Monitoring Report
6 wks Fri 7/22/22 Thu 9/1/22 e
7/24 7/31 8/7 8/14 8/21 August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC018A at the Boston Man Cleaners facility located in Sunrise, Broward County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
62 days Wed 6/8/22 Thu 9/1/22
3 Subtask 2:
Groundwater Sampling
49 days Mon 6/27/22
Thu 9/1/22
4 Field Work Preparation2 wks Mon 6/27/22Fri 7/8/22
5 Groundwater Sampling1 day Fri 7/15/22 Fri 7/15/22
6 Groundwater Monitoring Report
6 wks Fri 7/22/22 Thu 9/1/22 Jeremy Hess,Jenna Martin,Peter McLean,Debra Andrews
8/28 9/4 9/11 9/18 9/25 September Oc
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC018A at the Boston Man Cleaners facility located in Sunrise, Broward County