This is a Task Assignment (TA) document under Contract Number HW684 between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc., executed effective December 4, 2025. The task assignment authorizes GHD Services, Inc. to conduct groundwater monitoring at Dryclean USA #11204, located at 2861 Stirling Road, Broward County, Fort Lauderdale, Florida 33312. The project is identified as ERIC_4174 with a completion date of April 13, 2026. Department Project Manager Mackenzie Childs (850-245-8929) and Contractor Project Manager Brian Moore (813-971-3882) oversee the engagement.
The scope of work encompasses three subtasks: (1) Project Management calculated at 13 percent of direct labor; (2) Groundwater Monitoring involving annual sampling and analysis at seven monitoring wells (MW001, MW003, MW006, MW009, IW001, IW002, and IW003) with volatile organic halogenated compounds (VOHs), total organic carbon (TOC), ammonia, and total dissolved solids (TDS) analysis, followed by a summary report; and (3) PFAS Groundwater Sampling at five wells (MW001, MW003, MW006, IW001, and IW002) with results submitted to the FDEP laboratory. The total task assignment value is $7,189.00 on a fixed unit rate basis. Invoice milestones require FDEP review and approval of the Groundwater Monitoring Report plus Project Management ($6,446.83) and PFAS field notes and data ($742.17), both due February 13, 2026. The contract incorporates a Scope of Work attachment and references the underlying indefinite delivery vehicle contract HW684.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW684
DC006D April 13, 2026
This Task Assignment authorizes GHD Services, Inc to conduct groundwater monitoring at Dryclean USA #11204.
Mackenzie Childs 850-245-8929 GHD Services, Inc.
Brian Moore 813-971-3882
ERIC_4174
2861 Stirling Rd, Broward County, Ft Lauderdale, FL 33312
Dryclean USA #11204
$ 7,189.00
$ 7,189.00
Scope of Work
GHD Services, Inc.
Brian Moore Digitally signed by Brian Moore Date: 2025.12.04 13:48:11 -05'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2025.12.03 08:51:34 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
TO:
FROM:
DATE:
SUBJECT:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2:
SITE : Drclean USA#11204 SUBTASK 2: Groundwater Monitoring
DATE: 11/14/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer JH Conclusions/Recommendations 1
Project Manager JM Coordinate site access with property manager/owner 1 Project Manager JM Field Work Preparation 1
Project Manager JM IDW Characterization and coordination 1 Project Manager JM Prepare groundwater report general text 1 Project Manager JM Field quality parameter summary and trends 1 Project Manager JM Summarize groundwater flow/gradients (shallow/int) 2 Project Manager JM Summarize groundwater analytical results (shallow/int) & UIC 3 Project Manager JM Conclusions/recommendations 1
Staff Scientist ED Mob/demob (from West Palm Beach) - 2 days 4 Staff Scientist ED Water Levels (all wells - 13 wells) 2 Staff Scientist ED Groundwater Sampling (7 wells) 10.5
16.5
Drafting Technician KJ Prepare GW Flow maps (shallow, intermediate) 2 Drafting Technician KJ Prepare VOC plume figures with updated concentration data 2
Staff Assistant JJ Data Entry (13 wls, and 7 monitor wells) 1.5 Staff Assistant JJ Update summary tables (wl, parameter, analytical) 1 Staff Assistant JJ Document Preparation/Publishing 1
3.5
TOTAL LABOR 36
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 2 $240.00
TOTAL VEHICLE $240.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Drum Disposal $125 drum 1 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA 8260 $73.00 8 $584.00
TOC 9060 $30.00 1 $30.00
ammonia 350.2 $24.00 2 $48.00
TDS 160.1 $16.00 2 $32.00
sample shipping (Next Day) Large Cooler $150.00 1 $150.00 Ice $6.50 1 $6.50
TOTAL LAB $850.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 2 $80.00
Groundwater Sampling Kit $290.00 day 2 $580.00 Poly Tubing (HDPE) $0.30 ft 127 $38.10 Silicon Tubing $3.00 ft 7 $21.00 drum $100.00 each 1 $100.00
TOTAL EQUIPMENT $819.10
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Drclean USA#11204 SUBTASK 3: PFAS Sampling
DATE: 11/14/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Field Work Preparation (PFAS) 1
Project Manager JM Summarize groundwater analytical results PFAS 1 Project Manager JM Conclusions/recommendations (PFAS) 1
Drafting Technician KJ Prepare PFAS plume figures with updated concentration data 3
Staff Assistant JJ Update summary tables- PFAS 1.5
1.5
TOTAL LABOR 7.5
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Ice $6.50 1 $6.50 MW001, 3, 6, IW001 and IW002
TOTAL LAB $6.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
FINAL --7/24/96
COST PROPOSAL FOR TASK DC006D
Dryclean USA #11204/069502168
Groundwater Monitoring
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD operated a Soil Vapor Extraction System at the Dryclean USA site from March 19, 2009, through February 2011. Historically, soil excavation activities were completed along with enhanced bioremediation injections in accordance with an approved RAP Modification, utilizing a slow release substrate EOS, along with other nutrients. Following the initial injection event, periodic groundwater monitoring was conducted to evaluate concentration data over time. Following the annual sampling event in February 2014, an additional injection event was recommended. The additional injections occurred in October 2014. Currently, periodic groundwater monitoring activities are ongoing on an annual basis. The previous monitoring report was submitted in January 2025 and FDEP provide comments in February 2024.
Subtask 1: Project Management Subtask 1 includes all activities associated with completing annual groundwater sampling, analysis, and reporting for the Dryclean USA #11204 site.
Subtask 2: Groundwater Monitoring Task assignment DC006C (Subtask 2) includes annual groundwater sampling and analysis at seven (7) wells including MW001, MW003, MW006, MW009, IW001, IW002, and IW003.
Groundwater analysis will include volatile organic halocarbons (VOHs) at all wells, as well as TOC at monitor well MW001. In addition, ammonia and total dissolved solids (TDS) will be analyzed at MW001 and MW006. This sampling is in accordance with GHD’s recommendations in the January 2025 monitoring report, and DEP approval. During mobilization for sampling, depth to water measurements will be gathered from all available wells. Groundwater sampling will be conducted in general accordance with FDEP SOPs;
however, interior wells IW001, IW002, and IW003 will be sampled following collection of one set of parameters in order to reduce the amount of odor entering the active Pawn Shop facility.
In addition, the well caps will be sealed with epoxy following sampling to reduce odors.
Following groundwater sampling, a summary report will be prepared. The summary report will include a description of field sampling methodology and analytical results. The report will also include recommendations regarding the next step toward site rehabilitation.
Subtask 3: PFAS Groundwater Sampling Task assignment DC006D (Subtask 3) also includes PFAS sampling at site monitoring wells.
Based on PFAS screening results that identified elevated PFAS at 4 wells, GHD recommends sampling all site monitoring wells with PFAS analysis. Therefore, monitoring wells MW001, MW003, MW006, IW001, and IW002 will also be analyzed for PFAS. PFAS sampling will be conducted in accordance with FDEP and GHD PFAS sampling protocols. Samples from all wells (5 total) will be submitted to the FDEP laboratory for PFAS analysis.
Upon receipt of PFAS data, the results will be summarized within the Groundwater Monitoring Report described under Subtask 2.
Deliverables:
Deliverable Deliverable Due Date
Groundwater Monitoring Report 2/13/26
Field notes and PFAS data 2/13/26
From: Craig Burns To: Brian Moore Subject: GHD_IDW Drum Rates FL Date: Tuesday, June 28, 2022 10:26:46 AM Attachments: image001.png image002.png image003.png image004.png image005.png GHD Drum Rates FL 2022.pdf
Here you go Brian. I do this for a lot of engineering/consulting firms.
Be aware of the low stop less than 6 drums at $50/flat Be aware of the 10% to the total cost for FSC (implemented April 15).
Pass around the GHD Florida offices
From: Brian Moore <Brian.Moore@ghd.com> Sent: Tuesday, June 28, 2022 10:05 AM To: Craig Burns <cburns@clarkenvironmental.com> Subject: IDW Drums
Craig, Is it possible to provide a generic quote for IDW water disposal.
Assumption is non-haz with necessary analytical Maybe provide a range of locations
South florida or central florida, or both?
Thanks in advance
We have many sites that we generate 1 gw drum of IDW and would like to streamline the vendor coordination
BRIAN MOORE PE
GHD
Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA
O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com
The Power of Commitment
Connect
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
File details come from the government source that posted it. Updated .