This is a Task Assignment Notification Form and associated proposal from the Florida Department of Environmental Protection (FDEP), Bureau of Design and Construction (BDC), for work to be performed by Hydra Engineering & Construction, LLC. The task assignment covers design and permitting services for the road repave and repair project at Grayton Beach State Park. The contract is identified as FDEP Contract No. CN306, Task Assignment No. 18, with Project No. 61302C. Key personnel include Leslie Weiss, P.E., C.G.C., as the Consultant Representative from Hydra Engineering & Construction, LLC, and Ralph Perkins as the FDEP Contract Manager. The project location is Grayton Beach State Park, and the project manager is Theresa Carron.
Hydra Engineering & Construction, LLC will provide design and permit documents for the repave and repair of approximately 1,250 linear feet of park roadway. The scope of work includes seven subtasks: Subtask 1A (Topographic Survey - $4,566.58), Subtask 1B (Geotechnical Investigation - $4,052.50), Subtask 2 (30% Plans - $8,456.94), Subtask 3 (90% Plans - $5,658.94), Subtask 4 (100% Plans - $3,329.56), Subtask 5A (Construction Administration - $1,517.90), and Subtask 5B (Substantial Completion Site Visit - $1,741.74). The total contract amount is $29,324.16, structured entirely as fixed-price costs with no reimbursable expenses. The project schedule indicates subtasks 1A and 1B have 30-day durations beginning upon authorization, while subsequent subtasks are scheduled with durations ranging from 20 to 40 calendar days, with final dates to be determined. Payment is contingent upon FDEP approval of deliverables for each subtask. The task assignment was executed on February 14-15, 2023, with funding categorized under FLAIR code 37501016033 080039/23 000286 U3200 131500 AD.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN306 18 FDEP-BDC 61302C
Grayton Beach State Park Road Repave and Repair
Hydra Engineering & Construction, LLC
Leslie Weiss, P.E., C.G.C. (850) 926-2593 lahope@hydraengineering.com
Ralph Perkins (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Consultant to provide design and permit documents for the repave and repair of approximately 1,250 linear feet of park roadway as per proposal dated 2/13/2023.
Theresa Carron
Upon Execution $ 29,324.16 2/14/2024
$ 29,324.16
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.14 14:29:05 -05'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.02.15 09:54:04 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.15 10:28:13 -05'00'
Leslie Weiss, P.E., C.G.C. Leslie Weiss Digitally signed by Leslie Weiss Date: 2023.02.15 14:09:53 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.02.15 16:37:39 -05'00'
61302C 37501016033 080039/23 000286 U3200 131500 AD $ 29,324.16
$ 29,324.16
HYDRA ENGINEERING & CONSTRUCTION, LLC
36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com
Grayton Beach State Park – Entrance Road Repave and Repair
Dear Ms. Carron:
Hydra Engineering & Construction, LLC is pleased to provide the attached proposal summary and man-hour documentation for Phase 2 of the Road Repave and Repair at Grayton Beach State Park. This proposal assumes no environmental permitting will be required since no additional impervious area is being proposed outside of the existing paved footprint.
Please see the attached proposal summary and deliverables.
Sincerely, Leslie Weiss, P.E., C.G.C.
Hydra Engineering & Construction, LLC
February 13, 2023
Theresa Carron Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: CN306 TA18, BDC Project No. 61302C
Road Repair and Repave - Entrance Grayton Beach State Park
Subtask 1A: Survey Description: Conduct a Topographical Survey of Grayton Beach State Park of Main Park Road from FDOT right of way of Hwy 30A to the south side of the guardhouse. (approximately 1,250 feet).
Topographical Survey to include:
• Topographical Survey of paved roadway surface extending 10' outside the edge of pavement.
• Location of visible utilities (no underground utilities will be located).
• Horizontal and vertical control points will be established and set appropriately throughout the length of the project.
• Topographical survey will be performed on 1 foot contours and or spot elevations as needed.
• Topographical survey will be performed on NAVD 88 Vertical DATUM and Horizontal control will be on NAD 83/90.
Deliverable: Consultant will provide digitally signed and sealed electronic copies (Autocad and pdf) of the topographic survey.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1A
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Edwin Brown & Associates Survey Field Crew
(3 Man Crew) $150.00 17 $2,550.00
Edwin Brown & Associates Licensed Surveyor $155.00 4 $620.00
Edwin Brown & Associates Drafting $80.00 8.75 $700.00
Edwin Brown & Associates Office Administrator $20.00 6.5 $130.00 Hydra Engineering & Construction, LLC
Principal Engineer $279.80 1 $279.80
Hydra Engineering & Construction, LLC
Project Engineer $111.92 2 $223.84
Hydra Engineering & Construction, LLC
Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $4,566.58
Total for Subtask 1A: (Fixed Price Cost + Reimbursable) = $4,566.58
CN306 TA18, Project Number 61302C
Subtask 1B: Geotechnical Investigation:
Description: Geotechnical Investigation – Pavement Survey and Pavement Design Recommendations / 2 Core Locations.
• Environmental and Geotechnical Specialists, Inc. (EGS) will have access to the pavement coring locations and has permission to be on site and close one (1) lane of traffic;
• Bid assumes that EGS can perform the work between the normal business hours of Monday through Friday, 7:00am to 5:00pm;
Deliverable: Consultant will provide Geotechnical report with attachments to project manager electronically in PDF format and mail hard copies on 8 ½” x11” sheets.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1B
Firm Name Position Classification Hourly
Rate Hours
Total Fixed Price Cost
EGS, Inc. Senior Engineer $202.31 2 $404.62 EGS, Inc. Engineering Intern $86.23 8 $689.84 EGS, Inc. Senior Engineering Tech. $83.92 12 $1,007.04
EGS, Inc. Asphalt Coring Equipment $357.62 1 $357.62
EGS, Inc. MOT – Cones / Flags $28.84 1 $28.84
EGS, Inc. Flagmen (Each) $43.13 8 $345.04 EGS, Inc. Pavement Coring – Asphalt $126.50 2 $253.00 EGS, Inc. Auger Borings – Hand $8.59 10 $85.90
EGS, Inc. Particle Size Analysis AASHTO T88 (No Hydrometer) $40.48 2 $80.96
EGS, Inc. Liquid Limit AASHTO T89 $63.25 2 $126.50 EGS, Inc. Plastic Limit & Plasticity Index $25.30 2 $50.60 Hydra Engineering & Construction, LLC
Principal Engineer $279.80 1 $279.80
Hydra Engineering & Construction, LLC
Project Engineer $111.92 2.5 $279.80
Hydra Engineering & Construction, LLC
Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $4,052.50
Total for Subtask 1B: (Fixed Price Cost + Reimbursable) = $4,052.50
Subtask 2: 30% documents
Description: 30% Plans consisting of a cover sheet, general notes, existing conditions and plan and profile sheets. It also includes providing an Opinion of Probable Construction Cost.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly
Rate Hours
Total Fixed Price Cost
Hydra Engineering & Construction, LLC
Project Engineer $111.92 50 $5,596.00
Hydra Engineering & Construction, LLC
Principal Engineer $279.80 10 $2,798.00
Hydra Engineering & Construction, LLC
Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $8,456.94
Total for Subtask 2: (Fixed Price Cost + Reimbursable) = $8,456.94
Subtask 3: 90% Plans Description: 90% Plans consisting of updates from the 30% design review comments for the cover sheet, general notes, existing conditions, plan and profile sheets, cross-sections sheets, erosion control sheets, and construction details. It also includes providing an Opinion of Probable Construction Cost.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3
Firm Name Position
Classification Hourly Rate Hours
Total Fixed Price Cost
Hydra Engineering & Construction, LLC
Project Engineer $111.92 30 $3,357.60
Hydra Engineering & Construction, LLC
Principal Engineer $279.80 8 $2,238.40
Hydra Engineering & Construction, LLC
Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $5,658.94
Total for Subtask 3: (Fixed Price Cost + Reimbursable) =$5,658.94
Subtask 4: 100% Plans Description: 100% Plans consisting of updates from the 90% design review comments for the cover sheet, general notes, existing conditions, plan and profile sheets, cross-sections sheets, erosion control sheets, and construction details. It also includes providing an Opinion of Probable Construction Cost.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format and two (2) signed and sealed hard copies to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 4
Firm Name Position Classification Hourly
Rate Hours
Total Fixed Price Cost
Hydra Engineering & Construction, LLC
Project Engineer $111.92 15 $1,678.80
Hydra Engineering & Construction, LLC
Principal Engineer $279.80 5 $1,399.00
Hydra Engineering & Construction, LLC
Office Administrator $62.94 4 $251.76
Fixed Price Cost Total: $3,329.56
Total for Subtask 4: (Fixed Price Cost + Reimbursable) = $3,329.56
Subtask 5A: Construction Administration
Description: Construction administration includes answering Requests for Information, reviewing shop drawings.
Deliverable: Responses to RFI’s, shop drawings transmitted electronically in PDF format to project manager. RFI’s will be responded to within 7 working days and submittals will be responded to within 5 working days.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5A
Firm Name Position Classification Hourly
Rate Hours
Total Fixed Price Cost
Hydra Engineering & Construction, LLC
Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC
Project Engineer $111.92 8 $895.36
Hydra Engineering & Construction, LLC
Office Administrator $62.94 1 $62.94
Fixed Price Cost Total $1,517.90
Total for Subtask 5A: (Fixed Price Cost + Reimbursable) =$1,517.90
Subtask 5B: Substantial Completion Site Visit
Description: Site visit for substantial completion inspection.
Deliverable: Site visit note transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5B
Firm Name Position Classification Hourly
Rate Hours
Total Fixed Price Cost
Hydra Engineering & Construction, LLC
Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC
Project Engineer $111.92 10 $1,119.20
Hydra Engineering & Construction, LLC
Office Administrator $62.94 1 $62.94
Fixed Price Cost Total $1,741.74
Total for Subtask 5B: (Fixed Price Cost + Reimbursable) =$1,741.74
Project Schedule:
Activity Duration (Calendar Days) Dates Subtask 1A- Topographic Survey
30 Upon Receiving Authorization
Subtask 1B- Geotechnical Investigation
30 Upon Receiving Authorization
Subtask 2: 30% plans 40 TBD Subtask 3: 90% Plans 20 TBD Subtask 4: 100% Plans 21 TBD Subtask 5A: Construction Admin
*Contingent on when department advertises the project for bidding
TBD
Subtask 5B: Substantial Completion Site Visit
*Contingent on when construction starts
TBD
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A- Topographic Survey $4,566.58 $0.00 Subtask 1B- Geotechnical
Investigation $4,052.50 $0.00
Subtask 2: 30% plans $8,456.94 $0.00
Subtask 3 90% $5,658.94 $0.00
Subtask 4 100% $3,329.56 $0.00
Subtask 5A Construction Admin $1,517.90 $0.00 Subtask 5B Substantial Completion
Site Visit $1,741.74 $0.00
Total Fixed Price Cost: $29,324.16 Total Reimbursable Cost: $0.00
Overall Total Cost: $29,324.16
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)