This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a consulting services contract. The change order involves Hydra Engineering & Construction, LLC, a Florida-based engineering firm located in Crawfordville, with coordination from R.E. Walsh Engineering Inc. The contract is for work at Fred Gannon Rocky Bayou State Park under FDEP Contract No. CN306, Task Assignment No. 15.

The change order adds three subtasks related to electrical easement and utility upgrades totaling $6,813.88 in fixed-price costs with no reimbursable expenses. Subtask 8 covers survey and legal description of proposed CHELCO electrical easement locations for $2,823.19; Subtask 8A includes coordination with CHELCO utility provider for $2,406.07; and Subtask 8B provides redesign documents for relocating the bathhouse electrical feeder load from the north service to the west service for $1,584.62. The original task amount was $163,899.19, bringing the total with all change orders to $170,713.07. The task execution date remains December 6, 2022, with an end date of December 1, 2025, with no net change in days. Payment is contingent upon FDEP approval of deliverables for each subtask. The change order was executed on July 15-23, 2025, with signatures from the Budget Representative, Project Manager, Contract Manager, Consultant, and Contract Authority.

View the file

Other files

File Type Posted
CN-370000-CN306-A1.pdf PDF
CN-370000-CN306-T10.pdf PDF
CN-370000-CN306-T12.pdf PDF
CN-370000-CN306-T13CO1.pdf PDF
CN-370000-CN306-T13CO3.pdf PDF
CN-370000-CN306-T14CO1.pdf PDF
CN-370000-CN306-T15.pdf PDF
CN-370000-CN306-T16CO2.pdf PDF
CN-370000-CN306-T17.pdf PDF
CN-370000-CN306-T18.pdf PDF
CN-370000-CN306-T19 CO1.pdf PDF
CN-370000-CN306-T20.pdf PDF
CN-370000-CN306-T22CO1.pdf PDF
CN-370000-CN306-T22CO2.pdf PDF
CN-370000-CN306-T23CO1.pdf PDF
CN-370000-CN306-T24CO1.pdf PDF
CN-370000-CN306-T28CO3.pdf PDF
CN-370000-CN306-T33.pdf PDF
CN-370000-CN306-T5CO2.pdf PDF
CN-370000-CN306-T6.pdf PDF
CN-370000-CN306-CMC1.pdf PDF
CN-370000-CN306-T10CO2.pdf PDF
CN-370000-CN306-T11CO1.pdf PDF
CN-370000-CN306-T19.pdf PDF
CN-370000-CN306-T20CO1.pdf PDF
CN-370000-CN306-T21CO1.pdf PDF
CN-370000-CN306-T22.pdf PDF
CN-370000-CN306-T23CO2.pdf PDF
CN-370000-CN306-T23CO3.pdf PDF
CN-370000-CN306-T23CO4.pdf PDF
CN-370000-CN306-T26CO1.pdf PDF
CN-370000-CN306-T28.pdf PDF
CN-370000-CN306-T31CO1.pdf PDF
CN-370000-CN306-T32CO1.pdf PDF
CN-370000-CN306-T33CO1.pdf PDF
CN-370000-CN306-T33CO2.pdf PDF
CN-370000-CN306-T3CO1.pdf PDF
CN-370000-CN306-T5CO1.pdf PDF
CN-370000-CN306-T8CO1.pdf PDF
CN-370000-CN306-T1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN306-T10 CO1.pdf PDF
CN-370000-CN306-T10 CO1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN306-T11CO2.pdf PDF
CN-370000-CN306-T13CO2.pdf PDF
CN-370000-CN306-T16.pdf PDF
CN-370000-CN306-T16CO1.pdf PDF
CN-370000-CN306-T19CO3.pdf PDF
CN-370000-CN306-T1CO1.pdf PDF
CN-370000-CN306-T2.pdf PDF
CN-370000-CN306-T23.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN306 15 1 61496C

Fred Gannon Rocky Bayou Redesign Campground, Utilities, & Boat Ramp Parking

Hydra Engineering & Construction, LLC

Leslie Weiss (850) 926-2593 leslie@hydraec.com

Vu Nguyen (850) 245-2630 vu.nguyen@floridadep.gov

This adds survey for the proposed CHELCO Easement sites to create legal descriptions of the sites and redesign documents for the bathhouse feeder per attached proposal dated 6/3/25.

$ 4,466.63 $ 159,432.56 $ 163,899.19 $ 4,466.63 $ 159,432.56 $ 163,899.19

$ 0.00 $ 6,813.88 $ 6,813.88 $ 4,466.63 $ 166,246.44 $ 170,713.07

12/06/22

12/01/25

12/01/25

12/01/25

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2025.07.15 11:27:50 -04'00'

Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2025.07.22 10:31:56 -04'00'

Vu Nguyen Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.07.22 13:23:44 -04'00'

Leslie Weiss Leslie Weiss Digitally signed by Leslie Weiss Date: 2025.07.22 16:09:59 -04'00'

Tim Giesecke Tim Giesecke Digitally signed by Tim Giesecke Date: 2025.07.23 16:16:36 -04'00'

61496C 37501005065 080039/23 423001 U3200 131500 QK $ 6,813.88

$ 6,813.88

HYDRA ENGINEERING & CONSTRUCTION, LLC

36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com

June 03, 2025

Mr. Kenny Franklin or Mr. Garland Sandel Construction Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: CN , BDC Project No. 61496C Fred Gannon Rocky Bayou State Park –

Dear Mr. Franklin and Mr. Sandel:

Hydra Engineering & Construction, LLC is pleased to provide the attached proposal summary and man-hour documentation for the at Fred Gannon Rocky Bayou State Park.

Please see the attached change order proposal summary and deliverables.

Sincerely, Leslie Weiss, P.E., C.G.C.

Hydra Engineering & Construction, LLC

CO1

CHELCO Electrical Easement Survey & Coordination Fred Gannon Rocky Bayou State Park

Subtask 8: CHELCO Electrical Easement Survey

Description: Survey and sketch and legal description of proposed CHELCO Easement flagged locations. Tie easement to known point of commencement to create legal description.

Deliverable: Five (5) copies of signed and sealed survey, AutoCAD and PDF copies.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 8 CHELCO Electrical Easement Survey

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Edwin Brown & Associates Survey Field Crew (3 Man Crew) $150.00 12 $1,800.00

Edwin Brown & Associates Licensed Surveyor $155.00 2 $310.00 Edwin Brown & Associates Drafting $80.00 3.25 $260.00 Edwin Brown & Associates Office Administrator $20.00 1.5 $30.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80 Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $2,823.19

Total for Subtask 8: (Fixed Price Cost + Reimbursable) =$2,823.19

Subtask 8A: Coordination with CHELCO

Description: R.E.Walsh Engineering Inc. and Hydra Engineering and Construction, LLC. will coordinate with CHELCO Utility provider to support the Easement process.

Deliverable: Email correspondence between CHELCO and consultants history in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 8A CHELCO Electrical Easement Coordination

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost R.E. Walsh Engineering, Inc. Senior Engineer $149.93 8 $1,199.44

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80 Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $2,406.07

Reimbursable Cost:

Total for Subtask : (Fixed Price Cost + Reimbursable) =$2,406.07

Subtask 8B: Redesign Documents for New Bathhouse Feeder

Description: R.E.Walsh Engineering Inc. will modify existing construction documents and recalculate loads for the north and west electrical services as necessary to move the bathhouse feeder load from the north service to the west service..

Deliverable: Email correspondence between CHELCO and consultants’ history in PDF format.

ANSI D sheet size drawings will be transmitted electronically in Portable Document Format (PDF) with revisions clouded.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 8B - Redesign Documents for New Bathhouse Feeder

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost R.E. Walsh Engineering, Inc. Senior Engineer $149.93 7 $1,049.51

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80 Hydra Engineering & Construction, LLC Project Engineer $111.92 2 $223.84 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,584.62

Reimbursable Cost:

Total for Subtask 8B: (Fixed Price Cost + Reimbursable) =$1,584.62

Project Schedule:

Activity Duration (Calendar Days) Dates Subtask 8 CHELCO Electrical Easement Survey

* Contingent upon contract execution.

TBD

Subtask 8A CHELCO Electrical Easement Coordination

* Contingent upon contract execution.

TBD

Subtask 8B Redesign Documents for New Bathhouse Feeder

* Contingent upon contract execution.

TBD

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 8 CHELCO Electrical Easement Survey $2,823.19 $0.00

Subtask 8A CHELCO Electrical Easement Coordination $2,406.07 $0.00

Subtask 8B - Redesign Documents for New Bathhouse Feeder $1,584.62 $0.00

Total Fixed Price Cost: $6,813.88 Total Reimbursable Cost: $0.00

Overall Total Cost: $6,813.88

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)