This Task Assignment Notification Form (T/A 20) is issued by the Florida Department of Environmental Protection (FDEP) to Hydra Engineering & Construction, LLC for design and engineering services related to playground improvements and pavilion repairs at Dr. Julian G. Bruce St. George Island State Park in Franklin County, Florida. The contract is designated as CN306, Project No. 61494C, with Ralph Perkins serving as the FDEP Contract Manager and Leslie Wiess as the Consultant Representative. The task was authorized upon execution on February 23, 2023, with a completion date of December 30, 2025.
The scope of work consists of five subtasks valued at a combined fixed price of $22,437.14 with no cost reimbursement component. Subtask 1 ($4,218.62) involves 30% schematic design for playground improvements at Sugar Hill Campgrounds. Subtask 2 ($2,194.30) covers 100% final design and construction drawings for the playground. Subtask 3 ($4,231.02) includes structural investigation of six existing pavilions. Subtask 4 ($8,378.82) provides 30% schematic plans for pavilion repairs based on structural findings. Subtask 5 ($3,414.38) delivers 100% final plans for pavilion repairs with opinions of probable construction cost. All deliverables are to be provided in PDF format with final plans digitally signed and sealed by licensed professionals. Payment is contingent upon FDEP approval of deliverables for each individual subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN306 T/A 20 FDEP 61494C
Dr.Julian G. Bruce St. George Island State Park Replace Playground Equipment & Pavilion Bolts/Hardware
Hydra Engineering
Leslie Wiess 850-926-2593 lahope@hydraengineering.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Replace hardware/bolts at four (4) Pavilions and Replace Playground Equipment as explained in the proposal dated 2/17/2023.
Edward Straight or successor
Upon Execution $ 22,437.14 12/30/2025 $ 0.00
$ 22,437.14
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.22 15:45:32 -05'00'
Edward Straight Edward Straight Digitally signed by Edward Straight Date: 2023.02.22 09:41:23 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.23 10:10:13 -05'00'
Leslie Wiess Leslie Weiss Digitally signed by Leslie Weiss Date: 2023.02.23 21:04:58 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.02.27 09:12:32 -05'00'
61494C 37501000068 080039/23 423001 U3200 131500 QK $ 22,437.14
$ 22,437.14
HYDRA ENGINEERING & CONSTRUCTION, LLC
36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com
REVISED February 17, 2023
Edward Straight Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: CN306, BDC Project No. 61494C
St. George Island State Park: Playground Improvements and Pavilion Study
Dear Mr. Straight:
Hydra Engineering & Construction, LLC is pleased to provide the attached proposal summary and man-hour documentation for the St. George Island State Park playground improvements and Pavilion Study.
Please see the attached proposal summary and deliverables.
Sincerely, Leslie Weiss, P.E., C.G.C.
Hydra Engineering & Construction, LLC
Matson_D Text Box
TA20
Playground Improvements & Pavilion Study St. George Island State Park
Subtask 1: Playground – 30% Schematic Design
Description: Schematic Design and configuration of the proposed playground at St. George Island State Park - Sugar Hill Campgrounds. The topographic survey will be provided in a separate contract. Per Franklin County Planning Department, site plan permitting will not be required.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Alan Holt LA Landscape Architect $150.04 18 $2,700.72
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $4,218.62
Total for Subtask 1: (Fixed Price Cost + Reimbursable) = $4,218.62
Subtask 2: Playground – 100% Final Design
Description: Final Design and configuration of the proposed playground at St. George Island State Park Sugar Hill Campgrounds, incorporating the comments from schematic design. It includes providing an Opinion of Probable Construction Cost.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format and Autocad format to the project manager. The final plans will be digitally signed and sealed.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 2
Firm Name Position Classification
Hourly Rate Hours Total Fixed
Price Cost Alan Holt LA Landscape Architect $150.04 6 $900.24 Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC Project Engineer $111.92 6 $671.52
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $2,194.30
Total for Subtask 2: (Fixed Price Cost + Reimbursable) = $2,194.30
Subtask 3: Structural Investigation of Existing Pavilions
Description: Structural investigation of the 6 existing pavilions located along St. George Island beach, including photographs, sketches, details and a narrative of the work that would need to be done. The investigation will determine if repairs to the individual pavilions are feasible or not.
Deliverable: Report prepared in pdf format, digitally signed and sealed.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 3
Rate Hours Total Fixed
Price Cost GS Preble Engineering Structural Engineer $158.04 20 $3,160.80 Hydra Engineering & Construction, LLC Project Engineer $111.92 4 $447.68
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $4,231.02
Total for Subtask 3: (Fixed Price Cost + Reimbursable) = $4,231.02
Subtask 4: 30% Schematic Plans for Pavilion Repairs
Description: Based on the recommendations of the Structural Investigation, plans with repair details will be provided.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 4
Firm Name Position Classification
Hourly Rate Hours Total Fixed Price
Cost GS Preble Engineering Structural Engineer 158.04 25 $3,951.00 Hydra Engineering & Construction, LLC Project Engineer $111.92 24 $2,686.08
Hydra Engineering & Construction, LLC Principal Engineer $279.80 6 $1,678.80
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $8,378.82
Total for Subtask 4: (Fixed Price Cost + Reimbursable) = $8,378.82
Subtask 5: 100% Final Plans for Pavilion Repairs Description: Final plans for the repairs to the applicable pavilions, incorporating the comments from schematic design. It includes providing an Opinion of Probable Construction Cost.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format and autocad format to the project manager. The final plans will be digitally signed and sealed.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, Subtask 5
Rate Hours Total Fixed
Price Cost GS Preble Engineering Structural Engineer $158.04 12 $1,896.48 Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Cost Price Total: $3,414.38
Total for Subtask 5: (Fixed Price Cost + Reimbursable) = $3,414.38
Project Schedule:
Activity Duration (Calendar Days) Dates Subtask 1: Playground - 30% Schematic Design
45 Upon Receiving Authorization
Subtask 2: Playground - 100% Construction Drawings
30 Upon Receiving Authorization
Subtask 3: Structural Analysis of Ex. Pavilions
45 TBD
Subtask 4: 30% Schematic Plans for Pavilion Repairs
45 TBD
Subtask 5: 100% Final Plans for Pavilion Repairs
30 TBD
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1 Playground - 30% Schematic Design $4,218.62 $0.00
Subtask 2 Playground - 100% Construction Drawings $2,194.30 $0.00
Subtask 3 Structural Analysis of Ex.
Pavilions $4,231.02 $0.00
Subtask 4 30% Schematic Plans for Pavilion Repairs $8,378.82 $0.00
Subtask 5 100% Final Plans for Pavilion Repairs $3,414.38 $0.00
Total Fixed Price Cost: $22,437.14 Total Reimbursable Cost: $0.00 Overall Total Cost: $22,437.14
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)