This document is a Task Assignment Notification Form (Task Assignment No. 24) under FDEP Contract CN306, executed between the Florida Department of Environmental Protection (FDEP) and Hydra Engineering and Construction, LLC. The project is designated as BDC Project No. 61428C and pertains to design and construction administration services for a new campground loop at Dr. Julian G. Bruce St. George Island State Park located in Franklin County, Florida. FDEP serves as the owner, with Ralph Perkins designated as the FDEP Contract Manager and Terry McCullum, Jr. as the Project Manager.
Hydra Engineering and Construction, LLC, represented by Leslie Weiss, P.E., C.G.C., is contracted to provide comprehensive design and permit documents along with construction administration for the campground expansion project. The total task amount is $285,032.41, comprised of $269,572.41 in fixed price costs and $15,460.00 in reimbursable expenses. The scope includes eight major phases: Subtask 1 (survey and geotechnical investigation), Subtask 2 (30% schematic design), Subtask 3 (environmental and permit applications), Subtask 4 (60% design development), Subtask 5 (90% construction documents), Subtask 6 (100% final documents), Subtask 7 (permitting services and bidding), and Subtask 8 (construction administration with multiple site visits). Payment is contingent upon FDEP approval of deliverables for each subtask. The contract execution occurred on July 11, 2023, with services commencing upon execution.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN306 24 FDEP 61428C
New Campground
Hydra Engineering and Construction, LLC.
Leslie Weiss, P.E., C.G.C. (850) 926-2593 lahope@hydraengineering.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Consultant is to provide design and permit documents and construction administration for the construction of a new campground loop at Dr. Julian G. Bruce St. George Island State Park, per attached proposal dated June 13, 2023
Terry McCullum, Jr. or successor
Upon Execution $ 269,572.41 Contract End Date $ 15,460.00
$ 285,032.41
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.27 09:02:16 -04'00'
Terry McCullum, Jr. Terry McCullum, Jr.
Digitally signed by Terry McCullum, Jr.
Date: 2023.06.30 09:09:36 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.07.05 10:45:19 -04'00'
Leslie Weiss Leslie Weiss Digitally signed by Leslie Weiss Date: 2023.07.05 11:21:25 -04'00'
Bryan Bradner
61428C 37501000068 080039/23 000286 U3100 134000 AD $ 285,032.41
$ 285,032.41
Dr. Julian G. Bruce St. George Island State Park
Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.07.11 10:50:42 -04'00'
HYDRA ENGINEERING & CONSTRUCTION, LLC
36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com
Rev. June 13, 2023
Terry McCullum Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: CN306-TA24, BDC Project No. 61428C St. George Island State Park Campgrounds
Dear Mr. McCullum:
Hydra Engineering & Construction, LLC is pleased to provide the attached proposal summary and man-hour documentation for the Campground Expansion at St. George Island State Park.
Please see the attached proposal summary and deliverables.
Sincerely, Leslie Weiss, P.E., C.G.C.
Hydra Engineering & Construction, LLC
Campground Expansion St. George Island State Park
Subtask 1A: Survey Description: Topographical design survey of campground expansion including new playground area. Limits of design survey are shown on sketch provided by project engineer.
Topographical design survey to include:
• Topographical Survey of paved roadway surface extending 10' outside the edge of pavement or edge of tree line.
• Location of visible utilities (no underground utilities will be located).
• Location of any cross drains, storm water structures and retaining walls within topographical corridor.
• Location of any trees 8" DBH or larger within the survey limits.
• Horizontal and vertical control points will be established and set appropriately throughout the length of the project.
• Topographical survey will be performed on 1 (one) foot contours and or spot elevations as needed.
• Topographical survey will be performed on NAVD 88 Vertical DATUM and Horizontal control will be on NAD 83/90.
Deliverable: Consultant will provide electronic copies (Autocad and pdf) digitally signed and sealed of the topographic survey.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1A
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Edwin Brown & Associates Survey Field Crew (3 Man Crew) $150.00 42.9 $6,435.00
Edwin Brown & Associates Licensed Surveyor $155.00 10 $1,550.00 Edwin Brown & Associates Drafting $80.00 24 $1,920.00 Edwin Brown & Associates Office Administrator $20.00 8 $160.00
Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80
Hydra Engineering & Construction, LLC Project Engineer $111.92 0.5 $55.96
Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total: $10,432.23
Total for Subtask 1A: (Fixed Price Cost + Reimbursable) = $10,432.23
Subtask 1B: Geotechnical Investigation:
Description:
Geotechnical Investigation for campground expansion including restroom installation, including one septic system, one building deep foundation, new roadway and one SWMF.
• Septic system: install 1-10 ft SPT coupled with 1 Double Ring Infiltration (DRI) Test
• Building Foundation: Install 4-40 Ft SPT Borings (160 Ft)
• New Roadway: Based on 1 boring per 100 LF, assuming 1,000 ft (10- 5Ft Hand Augers)
• Stormwater Management Facility (SWMF): Based on 2-20 Ft SPT Coupled with 1-5 Ft
Cased Hole.
Prepare a Geotechnical Report, Including:
Subsurface Materials Encountered, Measured Groundwater and Estimated "Normal" Seasonal High Groundwater Septic System: Provide Soil Classification and Infiltration Rate For Septic System Design (Septic System Design Performed By Others) New Roadway: Provide Subgrade Preparation and Over-Excavation Limits (If Applicable) (Pavement Design Performed by Others) Building Foundation: Provide Pile Capacity Curves for Timber and Concrete Piles, and Geo Design Parameters for Proposed Deep Foundations SWMF: Provide Geotechnical Design Parameters and Horizontal / Vertical Permeability Rate F\for SWMF
Assumptions:
• Environmental and Geotechnical Specialists, Inc. (EGS) will have access to the soil boring locations and has permission to be on site;
• EGS has approval and has permission to clear a 10 Ft wide path to access our soil boring locations, should it be required for access. Path will be cleared with a skid steer track unit with a mulching head attachment, and all brush and trees cleared will be mulched and will be placed on and around the proposed path. Care will be taken to avoid clearing of larger trees (tree diameters in excess of 6-Inches), but the Client understands that some larger trees will likely need to be removed in order to access soil boring location. This cost proposal is based on the understanding that the Client or Owner has coordinated with the property owner, and has obtained permission for us to clear, PRIOR to EGS mobilizing on site;
• Bid assumes that EGS can perform the work between the normal business hours of Monday through Friday, 7:00am to 5:00pm;
• EGS is not responsible for obtaining necessary permits (excluding utility locate ticket), should they be required, for the proposed site.
Deliverable: Consultant will provide Geotechnical report with attachments to project manager electronically in PDF format and mail hard copies on 8 ½” x11” sheets.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1B Geotech
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
EGS, Inc. Senior Engineer $202.31 12 $2,427.72 EGS, Inc. Engineering Intern $86.23 48 $4,139.04
EGS, Inc. Senior Engineering Technician $83.92 56 $4,699.52
EGS, Inc. ATV Drill Mobilization $632.49 1 $632.49
EGS, Inc. Auger Borings - Hand $8.59 50 $429.50 EGS, Inc. SPT-Track / ATV/ Skid 0-50ft $19.92 210 $4,183.20
EGS, Inc. Grout Boreholes - Track / ATV/ Skid 0-50Ft $7.60 210 $1,596.00
EGS, Inc. Extra SPT Samples - Track /ATV / Skid 0-50 ft $39.85 42 $1,673.70
EGS, Inc. 4-Inch Temporary Casing - Track / ATV/ Skid 0-50 FT $14.80 35 $518.00
EGS, Inc. Double Ring Infiltration (DRI) Test $379.49 1 $379.49
EGS, Inc.
Field Permeability 0-10 Ft - Piezometer (Cased Hole)
Method $379.49 1 $379.49
EGS, Inc. 2-Inch Temporary Piezometer Installation 0-50 Ft $25.30 10 $253.00
EGS, Inc. Particle Size Anlys AASHTO T88 (No Hydrometer) $40.48 26 $1,052.48
EGS, Inc. Liquid Limit AASHTO T89 $63.25 13 $822.25
EGS, Inc. Plastic Limit & Plasticity Index
AASHTO T90 $25.30 13 $328.90
EGS, Inc. Organic Content Ignition FM 1 T-267 $32.89 13 $427.57
EGS, Inc. Corrosion Series FM 5-550 through 5-553 $132.82 1 $132.82
Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80
Hydra Engineering & Construction, LLC Project Engineer $111.92 2.5 $279.80
Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total: $24,666.24
Total for Subtask 1B: (Fixed Price Cost + Reimbursable) = $24,666.24
Subtask 2A: 30% Architectural Schematic Design & Code Summary
Description: Dodstone will provide a single schematic design of new proposed configuration for restroom including any ramps or stairs required to access the building. A life safety sheet will be started and will summarize the major code requirements governing the project. It is our understanding that BDC would like us to provide plans similar to what is currently on site now, but modified to include an ADA compliant unisex restroom, and to incorporate the FL ADA stalls as required today. The structural system will be evaluated to determine if there is a substantial cost savings between the system used on the existing restroom on site (with exterior columns), or with a more conventional wood frame system. The schematic design will use a system similar to what is on site now, unless substantial savings are possible with a more conventional system.
The scope includes a new building, approximately 2,000 sf under the roof. The restroom will need to be elevated one foot above the floodplain (approximately 11 feet in the air) with both a ramp and stair access provided. The restroom is to include the following:
Men’s Restroom
• 1 ADA compliant shower compartment
• 1 additional shower compartment
• 1 Florida ADA stall with toilet and lav
• 1 additional toilet stall
• 1 urinal
• 2 lavs
Women’s Restroom
• 1 ADA compliant shower compartment
• 1 additional shower compartment
• 1 Florida ADA stall with toilet and lav
• 2 additional toilet stalls
• 2 lavs
ADA compliant Unisex restroom
• 1 ADA compliant roll-in shower
• 1 toilet
• 1 lav
Other requirements
• Chase access
• 2 washers and 2 driers
• Hi-low water fountain with bottle filling station.
Deliverable: Floor plan, roof plan, and exterior elevations will be provided in pdf format. Sheet sizes will be 22”x34”, transmitted electronically in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2A
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 15 $1,995.00 Dodstone Architects Graduate Architect $88.00 20 $1,760.00 Dodstone Architects CADD Operator $60.00 19 $1,140.00 Dodstone Architects Clerical $48.41 2 $96.82 Biss & Niytray Principal $178.77 4 $715.08
Fixed Price Cost Total: $5,874.90
Total for Subtask 2A: (Fixed Price Cost + Reimbursable) = $5,874.90
Subtask 2B: NFPA 1-18
Description: Dodstone will attend a virtual or teleconference meetings set up by Hydra Engineers with the State Fire Marshal and with the local fire chief serving the St. George Island. The intent of the meetings will be to discuss what options are available to address NFPA 1-18 and to determine which option(s) will be acceptable by the permitting agencies.
Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2B – NFPA 1-18
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Dodstone Architects Registered Architect $133.00 6 $798.00
Hydra Engineering & Construction, LLC Principal Engineer $279.80 6 $1,678.80
Fixed Price Cost Total: $2,476.80
Total for Subtask 2B: (Fixed Price Cost + Reimbursable) = $2,476.80
Subtask 2C: 30% Civil Submittal
Description: Hydra will provide two alternative designs showing the proposed campground loop configuration and the proposed restroom facility. 30% Plans consisting of a cover sheet, general notes, existing conditions, Site Plan and Utility Plan sheets for the water installation to the Campgrounds, and septic system design at the proposed restroom. Hydra will have one site visit to review the existing utility configuration.
Deliverable: ANSI D sheet size drawings will be transmitted electronically in Portable Document Format (PDF).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2C
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 120 $13,430.40
Hydra Engineering & Construction, LLC Principal Engineer $279.80 20 $5,596.00
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $19,089.34
Total for Subtask 2C: (Fixed Price Cost + Reimbursable) = $19,089.34
Subtask 2D: 30% Electrical Design Description: Preparation of drawings showing new work will be presented as necessary to establish proposed system configuration and layout as necessary to establish electrical service load for the two preliminary campground layouts and bathhouse. One site visit projected to accomplish field work. One site visit to coordinate any necessary service modifications with the electrical utility will be accomplished and general scope of electrical service modifications will be depicted on the drawings.
Deliverable ANSI D sheet size drawings will be transmitted electronically in Portable Document Format (PDF). Project specifications index will be provided on the drawings.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 2D – 30% Electrical Design
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
R.E. Walsh Engineering Sr. Engineer $149.93 72 $10,794.96
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Fixed Price Cost Total: $11,354.56
Total for Subtask 2D: (Fixed Price Cost + Reimbursable) = $11,354.56
Subtask 3A: Environmental Report and Environmental Site Inspection Description: Florida Environmental and Land Services, Inc. (FELSI) will conduct a site visit of the project area and will perform a wetland delineation based upon State and Federal guidelines within the vicinity of the park improvements. The wetland line will be flagged using numbered flagging tape marked with Wetland Delineation. Wetland points or locations will be collected concurrent with the fieldwork using GPS. A general and protected species survey will also be conducted in conjunction with the fieldwork and GPS used to locate any observed environmental features. If endangered and/or protected species or special habitat are found on site, additional fieldwork or mapping of those species may be required. This information will be used in completion of the exemption application and to formulate a species protection plan for Gopher Tortoises and shoreline nesting birds if needed.
Deliverable: Consultant will site report in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3A Environmental Report
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Florida Environmental & Land Services, Inc.
Principal Environmental Consultant $109.83 18 $1,976.64
Florida Environmental & Land Services, Inc. Staff Asst. $60.00 16 $960.00
Hydra Engineering & Construction, LLC Principal Engineer $279.80 0.5 $139.90
Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92
Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Cost Price Total: $3,220.23
Total for Subtask 3A: (Fixed Price Cost + Reimbursable) = $3,220.23
Subtask 3B: Environmental Resource Permit Application
Description: It is not clear if the improvements will cause wetland impacts or impacts to wetland buffers, FELSI will prepare and submit the required ERP permit application Sections A and C to the Northwest Florida Water Management District. This cost includes the response to one request for additional information. The application fee is included in the reimbursable expenses for $1,500.00. Section E of the application has many items which refers to stormwater, which will be completed by Hydra. FELSI assistance is included. This task includes a site visit with agency personnel to verify wetlands or impact areas.
Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3B Environmental Resource Permit Application
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Florida Environmental & Land Services, Inc.
Principal Environmental Consultant $109.83 24 $2,635.92
Florida Environmental & Land Services, Inc. Staff Project Asst. $60.00 7.5 $450.00
Hydra Engineering & Construction, LLC Principal Engineer $279.80 15 $4,197.00 Hydra Engineering & Construction, LLC Project Engineer $111.92 40 $4,476.80 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Cost Price Total: $11,822.66
Reimbursable Cost:
Permit Fees $1,500.00 Printing N/A Electronic submittals Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile)
0 miles * trip * 0.445 = $0.00
Reimbursable Total Cost $1,500.00
Total for Subtask 3B: (Fixed Price Cost + Reimbursable) = $13,322.66
Subtask 3C: Preparation of Section 404 or Army Corps Application (if necessary)
Description: The State FDEP now processes the 404 permitting for wetland impacts. If needed, FELSI will prepare and submit the required application and respond to one Request for Additional Information, if needed.
Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3C Preparation of Section 404 or Army Corps Application
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Florida Environmental & Land Services, Inc. Principal Environmental $109.83 12 $1,317.96
Florida Environmental & Land Services, Inc. Staff Project Asst. $60.00 3 $180.00
Hydra Engineering & Construction, LLC Principal Engineer $279.80 0.5 $139.90
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Cost Price Total: $1,700.80
Total for Subtask 3C: (Fixed Price Cost + Reimbursable) = $1,700.80
Subtask 3D: FWC Incidental Take Permit Application
Description: FELSI will prepare and submit an FWC Incidental Take Permit application if required. This application includes a summary of an environmental survey, construction methods and coordination with all agencies to create a plan to avoid impacts to the protected species or their habitats. The permit fee is not included and may vary by species and amount of impact.
Alternatively, if a permit is not required but a formal analysis is for permitting, an analysis of the habitats and methods of avoiding impacts to the beach mouse, shorebird nesting habitat and other potentially impacted protected species will be prepared. The permit fee is not included and may vary by species and amount of impact.
Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3D FWC Incidental Take Permit Application
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Florida Environmental & Land Services, Inc. Principal Environmental $109.83 11 $1,208.13
Florida Environmental & Land Services, Inc. Staff Project Asst. $60.00 6 $360.00
Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Cost Price Total: $1,879.40
Reimbursable Cost:
Permitting Fees Unknown at this time Printing N/A Electronic submittals Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile)
0 miles * trip * 0.445 = $0.00
Reimbursable Total Cost $0.00
Total for Subtask 3D: (Fixed Price Cost + Reimbursable) = $1,879.40
Subtask 3E: FDEP Potable Water System Permit Application
Description: Preparation of Florida Department of Environmental Protection Potable Water System Permit application for the extension of the water system to the campgrounds. It also includes Response to Comments during the application process. Applications will be provided to the FDEP Project Manager for signature prior to submittal.
Deliverable: Consultant will provide the permit application in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3E
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Hydra Engineering &
Construction, LLC Project Engineer $111.92 50 $5,596.00
Hydra Engineering & Construction, LLC Principal Engineer $279.80 5 $1,399.00
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $7,057.94
Reimbursable Cost:
Permit Application Fee $860.00 Printing N/A Electronic submittals Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile)
0 miles * 1 trip * 0.445 = $0.00
Reimbursable Total Cost $860.00
Total for Subtask 3E: (Fixed Price Cost + Reimbursable) = $7,917.94
Subtask 3F: Wave Force Analysis
Description: Determine the significant wave height and wave period during the 100-year storm event. Calculate the expected wave energy acting on the pilings below the 100-year flood elevation. Prepare a report summarizing the method of calculations, supporting documents, and wave forces acting on the proposed pilings. HWA will be provided with a topographical survey of the area, proposed pilings size, and proposed piling elevations. The report will be provided to the structural engineer for design of the proposed restroom.
Deliverable: Consultant will provide the Wave Analysis Report in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 3F
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost
Hans Wilson & Associates Principal Consultant / Professional Engineer $199.98 5 $999.90
Hans Wilson & Associates Engineer II / Project Manager II $105.00 16 $1,680.00
Hydra Engineering & Construction, LLC Project Engineer $111.92 5 $559.60
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $3,862.04
Total for Subtask 3F: (Fixed Price Cost + Reimbursable) = $3,862.04
Subtask 4A: 60% Architectural Plans
Description: The design team will prepare construction drawings that incorporate any comments received from Hydra, BDC and/or the permitting agencies during the previous subtasks. This proposal assumes that one of the schematic floor plans submitted previously has been selected by DEP by the start of this phase of work. The drawings will be developed to a level sufficient to describe the overall design intent. A booklet will be included containing cut sheets of the anticipated products and materials that will be used a basis of design for the building. Work is limited to 5’ beyond the building footprint. Any engineering, design services, or cut sheets for products required beyond that point are assumed to be provided by Hydra.
Deliverable: Deliverables will consist of pdf files of the following:
Life Safety plan Building Floor Plan Reflected Ceiling Plan Roof Plan
Exterior elevations Interior elevations of the restrooms Overall Building Section (2) Typical wall sections (1) Restroom Accessory, Door, Hardware, Louver, Window, Finish schedules started Structural Roof Framing plan Structural Foundation/Floor Framing Plan Cut sheets of proposed basis-of-design materials used in the building and summary of required structural corrections.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 4A
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 52 $6,916.00 Dodstone Architects Graduate Architect $88.00 45 $3,960.00 Dodstone Architects CADD Operator $60.00 33 $1,980.00 Dodstone Architects Clerical $48.41 3 $145.23 Bliss & Niytray Principal $178.77 4 $715.08 Bliss & Niytray Engineer $83.43 32 $2,669.76 Bliss & Niytray CADD Operator $93.86 24 $2,252.64
Fixed Price Cost Total: $18,974.71
Total for Subtask 4A: (Fixed Price Cost + Reimbursable) =$18,974.71
Subtask 4B: 60% Civil Plans
Description: 60% Plans consisting of updates from the 30% design review comments for the cover sheet, general notes, existing conditions, Site Plan, Master Utility Plan, Grading Plan, erosion control sheets, and construction details.
Deliverable: Consultant will provide 22”x34” sheet size drawings transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 4B
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 80 $8,953.60 Hydra Engineering & Construction, LLC Principal Engineer $279.80 15 $4,197.00 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $13,213.54
Total for Subtask 4B: (Fixed Price Cost + Reimbursable) =$13,213.54
Subtask 4C: 60% Opinion of Probable Construction Costs
Description: A projected construction cost will be provided based upon the 60% Construction Document submission. These will be broken down to include major architectural and structural.
Site costs, MEP costs and costs associated with anything 5’ beyond the building footprint will be provided by Hydra.
Deliverable: Consultant will provide the Opinion of Probable Construction Costs in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 4C
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 4 $532.00 Dodstone Architects Clerical $48.41 8 $387.28 Bliss & Niytray Principal $178.77 2 $357.54 Hydra Engineering & Construction, LLC Project Engineer $111.92 5 $559.60 Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Fixed Price Cost Total: $2,564.02
Total for Subtask 4C: (Fixed Price Cost + Reimbursable) = $2,564.02
Subtask 4D: 60% Electrical Design
Description: Drawings will present selected campground distribution system plan, bathhouse circuiting and switching as well as lighting fixture selection; plumbing layout, plumbing fixture selection, HVAC configuration and equipment selection, and all supporting unedited equipment and panel schedules.
Deliverable ANSI D sheet size drawings will be transmitted electronically in Portable Document Format (PDF). Project specifications index will be provided on the drawings.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Subtask 4D – 60% Electrical Design
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
R.E. Walsh Engineering Sr. Engineer $149.93 98 $14,693.14
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Fixed Price Cost Total: $15,252.74
Total for Subtask 4D: (Fixed Price Cost + Reimbursable) = $15,252.74
Subtask 4E: Water Tank (NFPA 1-18)
Description: If it is determined during Subtask 2B that a water tank will be required to satisfy NFPA 1-18, Bliss & Nyitray will provide engineering services for the required foundation.
Should a water tank not be required, these services will not be provided and no fees charged.
Deliverable: Foundation plans and tank details will be incorporated into the Construction Documents and be provided in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 4E
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects CADD Operator $60.00 2 $120.00 Dodstone Architects Clerical $48.41 1 $48.41 R.E. Walsh Engineering Sr. Engineer $149.93 0 $0.00 Bliss & Niytray Principal $178.77 2 $357.54 Bliss & Niytray Engineer $83.43 12 $1,001.16 Bliss & Niytray CADD Operator $93.86 8 $750.88 Hydra Engineering & Construction, LLC Project Engineer $111.92 16 $1,790.72
Hydra Engineering & Construction, LLC Principal Engineer $279.80 5 $1,399.00
Fixed Price Cost Total: $5,817.71
Total for Subtask 4E: (Fixed Price Cost + Reimbursable) = $5,817.71
Subtask 4F: Franklin County Dept. of Health Septic System Design & Permit Application
Description: Preparation of Florida Department of Environmental Protection / Franklin County Department of Health On-site Sewage Disposal System Permit application for the septic system to service the proposed restrooms. It also includes Response to Comments during the application process. Applications will be provided to the FDEP Project Manager for signature prior to submittal.
Deliverable: Consultant will provide the permit application in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 4F
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 4 $532.00 Dodstone Architects Clerical $48.41 8 $387.28
R.E. Walsh Engineering Sr. Engineer $149.93 12 $1,799.16 Hydra Engineering &
Construction, LLC Project Engineer $111.92 24 $2,686.08
Hydra Engineering & Construction, LLC Principal Engineer $279.80 4 $1,119.20
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $6,754.66
Reimbursable Cost:
Permit Application Fee $600.00 Printing N/A Electronic submittals Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile)
0 miles * 1 trip * 0.445 = $0.00
Reimbursable Total Cost $600.00
Total for Subtask 3E: (Fixed Price Cost + Reimbursable) = $7,354.66
Subtask 5A: 90% Architectural Construction Documents Description: The design team will prepare construction drawings that incorporate any comments received from Hydra or BDC during the previous subtasks. The drawings and specifications will be developed to a level sufficient for use in bidding and permitting services. The intent is that the only remaining changes between this and 100% are to address any comments received from BDC and to sign and seal the drawings.
Deliverable: Deliverables will consist of pdf files of the following:
90% Construction Document drawings
90% Architectural/Structural Booklet (at the discretion of the design team, some specifications may be shown on the drawings).
Fixed Price Cost:
Subtask 5A
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 51 $6,783.00 Dodstone Architects Graduate Architect $88.00 38 $3,344.00 Dodstone Architects CADD Operator $60.00 32 $1,920.00 Dodstone Architects Clerical $48.41 3 $145.23 Bliss & Niytray Principal $178.77 4 $715.08 Bliss & Niytray Engineer $83.43 32 $2,669.76 Bliss & Niytray CADD Operator $93.86 24 $2,252.64
Fixed Price Cost Total: $18,165.71
Total for Subtask 5A: (Fixed Price Cost + Reimbursable) = $18,165.71
Subtask 5B: 90% Civil Plans
Description: 90% Plans consisting of updates from the 60% design review comments for the cover sheet, general notes, existing conditions, Master Utility Plan, Site Plan, Grading Plan, erosion control sheets, and construction details.
Deliverable: Consultant will provide 22”x34” sheet size drawings transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 5B
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
Hydra Engineering & Construction, LLC Project Engineer $111.92 60 $6,715.20 Hydra Engineering & Construction, LLC Principal Engineer $279.80 20 $5,596.00 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $12,374.14
Total for Subtask 5B: (Fixed Price Cost + Reimbursable) =$12,374.14
Subtask 5C: 90% Opinion of Probable Construction Costs
Description: A projected construction cost will be provided based upon the 90% Construction Document submission. These will be broken down to include major architectural and structural elements. Site costs, MEP costs and costs associated with anything 5’ beyond the building footprint will not be included.
Deliverable: Consultant will provide the Opinion of Probable Construction Costs in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5C
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 1 $48.41 Bliss & Niytray Principal $178.77 2 $268.16 Hydra Engineering & Construction, LLC Project Engineer $111.92 2 $223.84 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80
Fixed Price Cost Total: $1,175.59
Total for Subtask 5C: (Fixed Price Cost + Reimbursable) = $1,175.59
Subtask 5D: 90% Electrical Design
Description: One site visit projected to verify final layout and coordinate conflicts with existing features. Drawings will present completed campground electrical distribution plan with system schematic depicting conductor sizing as well and the voltage drop for each section of the system; bathhouse electrical system plan, all necessary supporting details, panel schedules, power riser, maximum available fault current calculations; completed plumbing risers and pipe sizing; completed HVAC schedules and necessary details.
Deliverable ANSI D sheet size drawings will be transmitted electronically in Portable Document Format (PDF). Project specifications index will be provided on the drawings.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 5D – 90% Electrical Design
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
R.E. Walsh Engineering Sr. Engineer $149.93 94 $14,093.42
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC
Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $14,715.96
Total for Subtask 5D: (Fixed Price Cost + Reimbursable) = $14,715.96
Subtask 6A: 100% Architectural Construction Documents
Description: The design team will prepare construction drawings that incorporate any comments received from Hydra or BDC during the previous subtasks. The drawings and specifications will be developed to a level sufficient for use in bidding, permitting, and construction services.
Deliverable: Deliverables will consist of pdf files of the following:
Signed and Sealed 100% Construction Document drawings labeled for Permit Review Signed and Sealed 100% Architectural/Structural/Mechanical/Electrical Specification Booklet (at the discretion of the design team, some specifications may be shown on the drawings).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 6A
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 15 $1,995.00 Dodstone Architects Graduate Architect $88.00 6 $528.00 Dodstone Architects CADD Operator $60.00 6 $360.00 Dodstone Architects Clerical $48.41 2 $96.82 Bliss & Niytray Principal $178.77 4 $715.08 Bliss & Niytray Engineer $83.43 8 $667.44 Bliss & Niytray CADD Operator $93.86 12 $1,126.32
Fixed Price Cost Total: $5,656.66
Total for Subtask 6A: (Fixed Price Cost + Reimbursable) = $5,656.66
Subtask 6B: 100% Civil Plans
Description: 100% Civil Plans consisting of updates from the 90% design review comments.
Deliverable: Consultant will provide 22”x34” sheet size drawings transmitted electronically in PDF format digitally signed and sealed to FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 6B
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Hydra Engineering & Construction, LLC Project Engineer $111.92 15 $1,678.80 Hydra Engineering & Construction, LLC Principal Engineer $279.80 4 $1,119.20 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total: $2,860.94
Total for Subtask 6B: (Fixed Price Cost + Reimbursable) = $2,860.94
Subtask 6C: 100% Electrical Design
Description: Corrections or modifications resulting from review of documents and final coordination with pump station design.
Deliverable ANSI D sheet size drawings will be transmitted electronically in Portable Document Format (PDF). Project specifications index will be provided on the drawings.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 6C – 100% Electrical Design
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
R.E. Walsh Engineering Sr. Engineer $149.93 29 $4,347.97
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Fixed Price Cost Total: $4,907.57
Total for Subtask 6C: (Fixed Price Cost + Reimbursable) = $4,907.57
Subtask 7A: Basic Architectural Permitting Services
Description: The building design team will provide an electronically signed and sealed drawing set and two printed signed and sealed sets on 22”x34” sheets for BDC’s use for acquiring a building permit. The design team will respond in writing to any permitting comments received. It is assumed that the permit application and delivery and/or upload of any drawings to Franklin County is being handled by others. All permit application fees are assumed be paid by others.
Deliverable: An electronic copy of the signed and sealed sets will be emailed to BDC for their use. A copy of any responses to comments will be issued in pdf format to BDC’s designated project manager. Two signed and sealed sets for use in acquiring the permit will be delivered to Hydra’s offices for permit submittals.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 7A
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 14 $1,862.00 Dodstone Architects Graduate Architect $88.00 3 $264.00 Dodstone Architects CADD Operator $60.00 2 $120.00 Dodstone Architects Clerical $48.41 2 $96.82 Bliss & Niytray Principal $178.77 2 $357.54
Fixed Price Cost Total: $2,784.36
Reimbursable Cost:
Permitting Fees $0.00 (Covered under separate subtasks) Printing NTE 500 (Receipt for printing cost will be included) Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile) 0 miles * trip * 0.445 = $0.00 Reimbursable Total Cost $500.00
Total for Subtask 7A: (Fixed Price Cost + Reimbursable) = $3,284.36
Subtask 7B: SFM Permit Application
Description: Dodstone will serve as the applicant on behalf of BDC and submit the drawings for permit review to the State Fire Marshall. The design team will respond to any comments received in writing.
Deliverable: A copy of any responses to comments will be issued in pdf format. The acceptance letter once acquired will be forwarded to BDC for their use.
Fixed Price Cost:
Subtask 7B
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 3 $399.00 Dodstone Architects Graduate Architect $88.00 3 $264.00 Dodstone Architects CADD Operator $60.00 3 $180.00 Dodstone Architects Clerical $48.41 1 $48.41
Fixed Price Cost Total: $975.41
Reimbursable Cost:
For permitting fees: Not to exceed $12,000. A receipt of the actual permit fee collected will be provided. Ten percent will be added to the amount charged.
Permitting Fees $12,000.00 Printing Electronic Submittal Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile) 0 miles * trip * 0.445 = $0.00 Reimbursable Total Cost $12,000.00
Total for Subtask 7B: (Fixed Price Cost + Reimbursable) = $12,975.41
Subtask 7C: Bidding Description: The Design team will respond in writing to any bid questions or comments received prior to the cut-off date established by BDC for such questions. Any necessary revisions to the drawings or specifications in response to those questions will be provided.
Deliverable: Response to bid questions will be delivered in pdf format within 10 working days of written receipt of those comments.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language
Subtask 7C
Rate Hours
Total Fixed
Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 14 $1,862.00 Dodstone Architects Graduate Architect $88.00 5 $440.00 Dodstone Architects CADD Operator $60.00 6 $360.00 Dodstone Architects Clerical $48.41 2 $96.82 Bliss & Niytray Principal $178.77 1 $178.77 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80
Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36
Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total $4,343.69
Total for Subtask 7C: (Fixed Price Cost + Reimbursable) =$4,343.69
Subtask 8A: Construction Administration
Description: The civil and architectural design team shall review electronically submitted shop drawings and shall respond to any questions submitted by the contractor related to the project in writing. Our understanding is that BDC will be self-performing the pay application reviews, therefore that service is excluded.
Deliverable: Copies of any RFI responses will be provided in pdf format. Copies of reviewed shop drawings will be provided in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 8A
Rate Hours
Total Fixed
Price Cost
Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 14 $1,862.00
Dodstone Architects Graduate Architect $88.00 8 $704.00 Dodstone Architects CADD Operator $60.00 6 $360.00 Dodstone Architects Clerical $48.41 2 $96.82 Bliss & Niytray Principal $178.77 1 $178.77 Bliss & Niytray Engineer $83.43 12 $1,001.16 Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60 Hydra Engineering & Construction, LLC Project Engineer $111.92 12 $1,343.04 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total $6,304.86
Total for Subtask 8A: (Fixed Price Cost + Reimbursable) =$6,304.86
Subtask 8B: Electrical Construction Administration
Description: Provide review and approval of shop drawing submittals. Provide written response for technical questions submitted (Request for Information, RFI) which arise during the course of construction.
Deliverable: Copies of any RFI responses will be provided in pdf format. Copies of reviewed shop drawings will be provided in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 8B
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost
R.E. Walsh Engineering Sr. Engineer $149.93 10 $1,499.30
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Fixed Price Cost Total: $2,058.90
Total for Subtask 8B: (Fixed Price Cost + Reimbursable) = $2,058.90
Subtask 8C: Pre-Construction Meeting
Description: Upon request by BDC, Dodstone will have one person from their office attend the Pre-Construction meeting on site. Dodstone will prepare minutes for the meeting.
Deliverable: Minutes from the meeting will be delivered in pdf format to BDC’s designated project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 8C
Rate Hours
Total Fixed
Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 7 $931.00 Dodstone Architects Clerical $48.41 1 $48.41 R.E. Walsh Engineering Sr. Engineer $149.93 10 $1,499.30 Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60 Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94
Fixed Price Cost Total $4,080.61
Total for Subtask 8C: (Fixed Price Cost + Reimbursable) =$4,080.61
Subtask 8D: Progress Site Visit #1 - Civil
Description: A progress site inspection by Hydra to review the status of the project during construction.
Deliverable: Site visit notes transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 8D
Rate Hours
Total Fixed
Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60
Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total $1,486.43
Total for Subtask 8D: (Fixed Price Cost + Reimbursable) =$1,486.43
Subtask 8E: Substantial Completion Site Visit - Civil
Description: Hydra attending a site visit for substantial completion inspection.
Deliverable: Site visit notes transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 8E
Rate Hours
Total Fixed
Price Cost Hydra Engineering & Construction, LLC Principal Engineer $279.80 3 $839.40 Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total $1,766.23
Total for Subtask 8E: (Fixed Price Cost + Reimbursable) =$1,766.23
Subtask 8F: Architectural Interim Site Visit 1
Description: The architect shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.
Deliverable: Field reports will be delivered within 5 working days of the site visit in pdf format.
Fixed Price Cost:
Subtask 8F
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 7.5 $997.50 Dodstone Architects Clerical $48.41 1 $48.41 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80
Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47
Fixed Price Cost Total $1441.18
Total for Subtask 8F: (Fixed Price Cost + Reimbursable) =$1,441.18
Subtask 8G: Architectural Interim Site Visit 2
Description: The architect shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.
Deliverable: Field reports will be delivered within 5 working days of the site visit in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 8G
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 7.5 $997.50 Dodstone Architects Clerical $48.41 1 $48.41 Hydra Engineering & Construction, LLC Principal…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .