Document Summary

This is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) for design and permitting services related to a new Concession Building at Grayton Beach State Park in Walton County, Florida. The contract is awarded to Hydra Engineering & Construction, LLC, with support from various subconsultants including Dodstone Architects, R.E. Walsh Engineering, Bliss & Niytray, Florida Environmental and Land Services Inc. (FELSI), Edwin Brown & Associates, Environmental and Geotechnical Specialists Inc. (EGS), and Alan Holt Landscape Architect. The contract is identified as CN306, Task Assignment TA23, Project Number 61427C, with FDEP Contract Manager Ralph Perkins overseeing the work.

The project scope encompasses comprehensive design and permitting services structured in multiple phases: site surveys and geotechnical investigations (Subtasks 1A-1D totaling $28,205.92); 30% schematic design, environmental review, and permitting pre-applications (Subtasks 2A-3D totaling $29,647.43); 60% design development (Subtasks 4A-4E totaling $66,217.64); 90% construction documents (Subtasks 5A-5C totaling $35,264.42); 100% final documents (Subtasks 6A-6B totaling $7,832.81); permitting and bidding support (Subtasks 7A-7C totaling $9,425.11); and construction administration with multiple site visits (Subtasks 8A-8O totaling $47,181.63). The total contract value is $223,674.97, consisting of $211,925.57 in fixed price costs and $11,749.40 in reimbursable expenses. The project initiation date is upon execution, with a scheduled completion date of June 9, 2026. Payment is contingent upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN306-CMC1.pdf PDF
CN-370000-CN306-T10CO2.pdf PDF
CN-370000-CN306-T11CO1.pdf PDF
CN-370000-CN306-T19.pdf PDF
CN-370000-CN306-T20CO1.pdf PDF
CN-370000-CN306-T21CO1.pdf PDF
CN-370000-CN306-T22.pdf PDF
CN-370000-CN306-T23CO2.pdf PDF
CN-370000-CN306-T23CO3.pdf PDF
CN-370000-CN306-T23CO4.pdf PDF
CN-370000-CN306-T26CO1.pdf PDF
CN-370000-CN306-T28.pdf PDF
CN-370000-CN306-T31CO1.pdf PDF
CN-370000-CN306-T32CO1.pdf PDF
CN-370000-CN306-T33CO1.pdf PDF
CN-370000-CN306-T33CO2.pdf PDF
CN-370000-CN306-T3CO1.pdf PDF
CN-370000-CN306-T5CO1.pdf PDF
CN-370000-CN306-T8CO1.pdf PDF
CN-370000-CN306-A1.pdf PDF
CN-370000-CN306-T10.pdf PDF
CN-370000-CN306-T12.pdf PDF
CN-370000-CN306-T13CO1.pdf PDF
CN-370000-CN306-T13CO3.pdf PDF
CN-370000-CN306-T14CO1.pdf PDF
CN-370000-CN306-T15.pdf PDF
CN-370000-CN306-T15CO1.pdf PDF
CN-370000-CN306-T16CO2.pdf PDF
CN-370000-CN306-T17.pdf PDF
CN-370000-CN306-T18.pdf PDF
CN-370000-CN306-T19 CO1.pdf PDF
CN-370000-CN306-T20.pdf PDF
CN-370000-CN306-T22CO1.pdf PDF
CN-370000-CN306-T22CO2.pdf PDF
CN-370000-CN306-T23CO1.pdf PDF
CN-370000-CN306-T24CO1.pdf PDF
CN-370000-CN306-T28CO3.pdf PDF
CN-370000-CN306-T33.pdf PDF
CN-370000-CN306-T5CO2.pdf PDF
CN-370000-CN306-T6.pdf PDF
CN-370000-CN306-T1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN306-T10 CO1.pdf PDF
CN-370000-CN306-T10 CO1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN306-T11CO2.pdf PDF
CN-370000-CN306-T13CO2.pdf PDF
CN-370000-CN306-T16.pdf PDF
CN-370000-CN306-T16CO1.pdf PDF
CN-370000-CN306-T19CO3.pdf PDF
CN-370000-CN306-T1CO1.pdf PDF
CN-370000-CN306-T2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN306 TA23 FDEP-DRP 61427C

Grayton Beach State Park Concession Building

Hydra Engineering & Construction, LLC.

Leslie Weiss, P.E., C.G.C. (850) 926-2593 lahope@hydraengineering.com

Ralph Perkins, or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

This proposal is for providing Design & Permitting services associated with the new Concession Building to be located in the Northeast corner of the intersection of Main Park Road & Camp Area Road per attached proposal dated 6/9/2023.

Del Cobb, or successor

Upon Execution $ 211,925.57 6/9/2026 $ 11,749.40

$ 223,674.97

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.15 11:01:12 -04'00'

Del Cobb Del Cobb Digitally signed by Del Cobb Date: 2023.06.15 14:08:53 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.15 16:37:35 -04'00'

Leslie Weiss, P.E., C.G.C. Leslie Weiss Digitally signed by Leslie Weiss Date: 2023.06.19 14:54:14 -04'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.06.22 15:44:43 -04'00'

61427C 37501016033 080039/23 000286 U3100 131500 AD $ 223,674.97

$ 223,674.97

HYDRA ENGINEERING & CONSTRUCTION, LLC

36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com

June 9, 2023

Del Cobb Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: CN306, BDC Project No. 61427C

Grayton Beach State Park – Concession Stand

Dear Mr. Cobb:

Hydra Engineering & Construction, LLC is pleased to provide the attached proposal summary and man-hour documentation for the proposed Concession Stand at Grayton Beach State Park.

Please see the attached proposal summary and deliverables.

Sincerely, Leslie Weiss, P.E., C.G.C.

Hydra Engineering & Construction, LLC

Grayton Beach State Park – New Concession Building

Subtask 1A: Survey Description: Edwin Brown & Association will provide a design survey for the new concession building to be located in the Northeast corner of the intersection of Main Park Road and Camp Area Road. Topographical design survey to include:

• Topographical Survey of paved roadway surface extending 20’ outside edge of existing pavement

• Location of all trees 8” in diameter trees within topographical corridor.

• Location of visible above ground utilities and existing sewer force main and water main. Force main and water main will need to be located by park personnel or others prior to field survey being performed.

• Horizontal and vertical control points will be established and set appropriately throughout the length of the project.

• Topographical survey will be performed on 1 (one) foot contours and or spot elevations as needed.

• Topographical survey will be performed on NAVD 88 Vertical DATUM and Horizontal control will be on NAD 83/90.

Deliverable: Consultant will provide electronic copies (Autocad and pdf) digitally signed and sealed of the topographic survey.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 1A

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

Edwin Brown & Associates Survey Field Crew (3 Man Crew) $150.00 28 $4,200.00

Edwin Brown & Associates Licensed Surveyor $155.00 4.4 $682.00 Edwin Brown & Associates Drafting $80.00 12 $960.00 Edwin Brown & Associates Office Administrator $20.00 8 $160.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Project Engineer $111.92 0.5 $55.96

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total: $6,369.23

Total for Subtask 1A: (Fixed Price Cost + Reimbursable) = $6,369.23

Subtask 1B: Geotechnical Investigation for Proposed Parking Facility:

Description:

Perform 4-5 Ft Hand Augers in Footprint of Proposed Parking Facility (20 Ft) Assumptions:

• Environmental and Geotechnical Specialists, Inc. (EGS) will have access to the soil boring locations and has permission to be on site;

• Bid assumes that EGS can perform the work between the normal business hours of Monday through Friday, 7:00am to 5:00pm;

• EGS is not responsible for obtaining necessary permits (excluding utility locate ticket), should they be required, for the proposed site.

Deliverable: Consultant will provide Geotechnical report with attachments to project manager electronically in PDF format and mail hard copies on 8 ½” x11” sheets.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 1B Geotech – Parking Lot

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

EGS, Inc. Senior Engineer $202.31 4 $809.24 EGS, Inc. Engineering Intern $86.23 16 $1,379.68

EGS, Inc. Senior Engineering Technician $83.92 24 $2,014.08

EGS, Inc. ATV Drill Mobilization $632.49 1 $632.49

EGS, Inc. Clearing Equipment $632.49 1 $632.49 EGS, Inc. Auger Borings - Hand $8.59 20 $171.80

EGS, Inc. Clearing (Skid steer) $126.39 4 $505.56

EGS, Inc. Laboratory Particle Size Analysis $40.48 4 $161.92

EGS, Inc. Laboratory- Organic Content Ignition $32.89 1 $32.89

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Project Engineer $111.92 2.5 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total: $6,931.22

Total for Subtask 1B: (Fixed Price Cost + Reimbursable) = $6,931.22

Subtask 1C: Geotechnical Investigation for Concession Building on Deep Foundation:

Description:

One (1) Proposed Elevated Concession Building (Deep Foundation Option), Install 4-40 Ft Deep SPT Soil Borings in Footprint Of Proposed Concession Building (160 Ft). Based on being allowed to clear a 10’ wide path with a clearing machine to access soil borings. Soil borings to be installed using a rubber track drill rig. Borings and trail line will be marker prior to mobilization in order to receive authorization prior to mobilization.

Deliverable: Consultant will provide Geotechnical report with attachments to project manager electronically in PDF format and mail hard copies on 8 ½” x11” sheets.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 1C Geotech

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

EGS, Inc. Senior Engineer $202.31 8 $1,618.48 EGS, Inc. Engineering Intern $86.23 24 $2,069.52

EGS, Inc. Senior Engineering Technician $83.92 24 $2,014.08

EGS, Inc. SPT-ATV 0-50 ft $19.92 160 $3,187.20

EGS, Inc. Extra SPT Samples ATV 0-50 ft $39.85 32 $1,275.20

EGS, Inc. Grout Boreholes-ATV 0-50 ft $7.60 160 $1,216.00

EGS, Inc. Laboratory Particle Size Analysis $40.48 16 $647.68

EGS, Inc. Laboratory-Liquid Limit $63.25 8 $506.00

EGS, Inc. Laboratory-Plastic Limit & Plasticity Index $25.30 8 $202.40

EGS, Inc. Laboratory- Organic Content Ignition $32.89 8 $263.12

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total: $13,422.87

Total for Subtask 1C: (Fixed Price Cost + Reimbursable) = $13,422.87

Subtask 1D: Geotechnical Investigation for Water Tank Foundation:

Description:

Install 1-10 Ft Deep SPT Soil Boring in Footprint Of Proposed Water Tank Shallow Foundation (10 Ft). Based on being allowed to clear a 10’ wide path with a clearing machine to access soil borings.

Soil borings to be installed using a rubber track drill rig. Borings and trail line will be marker prior to mobilization in order to receive authorization prior to mobilization.

Deliverable: Consultant will provide Geotechnical report with attachments to project manager electronically in PDF format and mail hard copies on 8 ½” x11” sheets.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 1D Geotech

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

EGS, Inc. Senior Engineer $202.31 1 $202.31 EGS, Inc. Engineering Intern $86.23 4 $344.92

EGS, Inc. Senior Engineering Technician $83.92 4 $335.68

EGS, Inc. SPT-ATV 0-50 ft $19.92 10 $199.20

EGS, Inc. Extra SPT Samples ATV 0-50 ft $39.85 2 $79.70 EGS, Inc. Grout Boreholes-ATV 0-50 ft $7.60 10 $76.00

EGS, Inc. Laboratory Particle Size Analysis $40.48 1 $40.48

EGS, Inc. Laboratory- Organic Content Ignition $32.89 1 $32.89

Hydra Engineering & Construction, LLC Principal Engineer $279.80 0.5 $139.90

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total: $1,482.55

Total for Subtask 1D: (Fixed Price Cost + Reimbursable) = $1,482.55

Subtask 2A: 30% Architectural Schematic Design & Code Summary

Description: Dodstone will provide two alternative designs showing the new proposed configuration for the concession building as well as any ramps or stairs required to access the building. One option will be oriented parallel to the park entrance drive, and the other will be oriented parallel to the turn-off to the camp area. A life safety sheet will be started and will summarize the major code requirements governing the project.

Deliverable: For each scheme, floor plans, roof plans, and exterior elevations will be provided in pdf format. Sheet sizes will be 22”x34”, transmitted electronically in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2A

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 20 $2,660.00 Dodstone Architects Graduate Architect $88.00 30 $2,640.00 Dodstone Architects CADD Operator $60.00 25 $1,500.00 Dodstone Architects Clerical $48.41 2 $96.82

Biss & Niytray Principal $178.77 2 $357.54 Fixed Price Cost Total: $7,422.36

Total for Subtask 2A: (Fixed Price Cost + Reimbursable) = $7,422.36

Subtask 2B: Pre-application Meeting with Walton County

Description: Dodstone and Hydra will attend one virtual or teleconference meeting with the Walton County permitting department. The intent of the meeting will be to determine what permit applications will be required, the time frame for their reviews, and the type of Development Order for this project.

Deliverable: Meeting minutes in pdf format of any meetings attended, transmitted electronically in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2B

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 3 $399.00 Hydra Engineering &

Construction, LLC Principal Engineer $279.80 8 $2,238.40

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total: $2,668.87

Reimbursable Cost:

Permitting fees: $25.00 for Walton County Pre-Application Meeting Printing N/A Electronic submittals Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

0 * 1 trip * 0.445 =

Reimbursable Total Cost $25.00

Total for Subtask 2B: (Fixed Price Cost + Reimbursable) = $2,693.87

Subtask 2C: NFPA 1-18

Description: Dodstone will attend a virtual or teleconference meetings set up by Hydra Engineers with the State Fire Marshal and with the local fire chief serving this area. The intent of the meetings will be to discuss what options are available to address NFPA 1-18 and to determine which option(s) will be acceptable by the permitting agencies.

Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2C – NFPA 1-18

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Dodstone Architects Registered Architect $133.00 6 $798.00

R.E. Walsh Engineering Principal Engineer $149.93 2 $299.86

Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60

Fixed Price Cost Total: $1,657.46

Total for Subtask 2C: (Fixed Price Cost + Reimbursable) = $1,657.46

Subtask 2D: 30% Civil Submittal

Description: Hydra will provide two alternative designs showing the new proposed configuration for the concession building and corresponding parking facilities. One option will be oriented parallel to the park entrance drive, and the other will be oriented parallel to the turn-off to the camp area.

Deliverable: ANSI D sheet size drawings will be transmitted electronically in Portable Document Format (PDF).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 2D

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 60 $6,715.20

Hydra Engineering & Construction, LLC Principal Engineer $279.80 15 $4,197.00

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $10,975.14

Total for Subtask 2D: (Fixed Price Cost + Reimbursable) = $10,975.14

Subtask 3A: Environmental Report and Environmental Site Inspection

Description: Florida Environmental and Land Services, Inc. (FELSI) will conduct a site visit of the project area and will perform a wetland delineation based upon State and Federal guidelines. The wetland line will be flagged using numbered flagging tape marked with Wetland Delineation.

Wetland points or locations will be collected concurrent with the fieldwork using GPS. A general and protected species survey will also be conducted in conjunction with the fieldwork and GPS used to locate any observed environmental features. If endangered and/or protected species are found on site, additional fieldwork or mapping of those species may be required.

Deliverable: Consultant will site report in PDF format to the FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 3A Environmental Report

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Florida Environmental & Land Services, Inc.

Principal Environmental Consultant $109.83 10.5 $1,153.21

Florida Environmental & Land Services, Inc. Staff Asst. $60.00 15 $900.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 0.5 $139.90

Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Cost Price Total: $2,336.50

Total for Subtask 3A: (Fixed Price Cost + Reimbursable) = $2,336.50

Subtask 3B: Environmental Resource Permit Exemption Application

Description: It appears that the project will qualify for a “De Minimis” exemption pursuant to

373.406 Florida Statue. FELSI will prepare and submit the required ERP permit application to the Northwest Florida Water Management District. This cost includes the response to one request for additional information. Section E, Stormwater Requirements of the application will be completed by Hydra. FELSI assistance is included. As part of this application an analysis of the habitats and methods of avoiding impacts to protected species that may be affected is included.

Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 3B Environmental Resource Permit Exemption Application

Rate Hours Total Fixed

Price Cost Florida Environmental & Land Services, Inc.

Principal Environmental Consultant $109.83 11 $1,208.13

Florida Environmental & Land Services, Inc. Staff Project Asst. $60.00 5.5 $330.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 15 $4,197.00 Hydra Engineering & Construction, LLC Project Engineer $111.92 35 $3,917.20 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Cost Price Total: $9,715.27

Reimbursable Cost:

Permit Fees $100.00 Printing N/A Electronic submittals Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

0 miles * trip * 0.445 = $0.00

Reimbursable Total Cost $100.00

Total for Subtask 3B: (Fixed Price Cost + Reimbursable) = $9,815.27

Subtask 3C: Preparation of Section 404 or Army Corps Application (if necessary)

Description: It is not anticipated to be required, however, if federally protected wetlands are proposed for impact, FELSI will prepare and submit the required application and respond to one Request for Additional Information, if needed.

Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.

Subtask 3C Preparation of Section 404 or Army Corps Application (if necessary)

Rate Hours

Total Fixed

Price Cost Florida Environmental & Land Services, Inc. Principal Environmental $109.83 11 $1,208.13

Florida Environmental & Land Services, Inc. Staff Project Asst. $60.00 5.5 $330.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 0.5 $139.90

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Cost Price Total: $1,740.97

Total for Subtask 3C: (Fixed Price Cost + Reimbursable) = $1,740.97

Subtask 3D: FWC Incidental Take Permit Application

Description: Although not anticipated to be necessary, this task includes preparation and submittal of an FWC Incidental Take Permit application if required. This application includes a summary of an environmental survey, construction methods and coordination with all agencies to create a plan to avoid impacts to the protected species or their habitats. The permit fee is not included and may vary by species and amount of impact.

Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 3D FWC Incidental Take Permit Application

Rate Hours Total Fixed

Price Cost Florida Environmental & Land

Services, Inc. Principal Environmental $109.83 12.8 $1,405.82

Florida Environmental & Land Services, Inc. Staff Project Asst. $60.00 7 $420.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Cost Price Total: $2,137.09

Permitting Fees Unknown at this time Printing N/A Electronic submittals Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile)

0 miles * trip * 0.445 = $0.00

Reimbursable Total Cost $0.00

Total for Subtask 3D: (Fixed Price Cost + Reimbursable) = $2,137.09

Subtask 4A: 60% Architectural Plans

Description: The design team will prepare construction drawings that incorporate any comments received from Hydra, BDC and/or the permitting agencies during the previous subtasks. The drawings will be developed to a level sufficient to describe the overall design intent. A booklet will be included containing cut sheets of the anticipated products and materials that will be used a basis of design for the building. Work is limited to 5’ beyond the building footprint. Any engineering, design services, or cut sheets for products required beyond that point are assumed to be provided by Hydra. This proposal assumes that one of the previously submitted architectural designs is selected prior to the start of this phase.

Deliverable: Deliverables will consist of pdf files of the following:

Life Safety plan

Building Floor Plan Reflected Ceiling Plan

Roof Plan Exterior elevations Interior elevations of the restrooms and any areas with built-in cabinetry Overall Building Section (1) Typical wall sections (1) Restroom Accessory, Door, Hardware, Louver, Window, Finish schedules started Electrical plans Electrical risers begun Panel schedule begun Structural Roof Framing plan Structural Foundation/Floor Framing Plan

Cut sheets of proposed basis-of-design materials used in the building and summary of required structural corrections.

Subtask 4A

Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 50 $6,650.00 Dodstone Architects Graduate Architect $88.00 44 $3,872.00 Dodstone Architects CADD Operator $60.00 33 $1,980.00

Dodstone Architects Clerical $48.41 3 $145.23 R.E. Walsh Engineering Principal Engineer $149.93 50 $7,496.50 Bliss & Niytray Principal $178.77 2 $357.54 Bliss & Niytray Engineer $83.43 24 $2,002.32 Bliss & Niytray CADD Operator $93.86 24 $2,252.64

Fixed Price Cost Total: $25,092.23

Total for Subtask 4A: (Fixed Price Cost + Reimbursable) =$25,092.23

Subtask 4B: 60% Civil Plans

Description: 60% Plans consisting of updates from the 30% design review comments for the cover sheet, general notes, existing conditions, Site Plan, Master Utility Plan, Grading Plan, erosion control sheets, and construction details. It also includes providing an Opinion of Probable Construction Cost.

Deliverable: Consultant will provide 22”x34” sheet size drawings transmitted electronically in PDF format to project manager.

Subtask 4B

Rate Hours Total Fixed

Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 60 $6,715.20 Hydra Engineering & Construction, LLC Principal Engineer $279.80 15 $4,197.00 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $10,975.14

Total for Subtask 4B: (Fixed Price Cost + Reimbursable) =$10,975.14

Subtask 4C: 60% Opinion of Probable Construction Costs

Description: A projected construction cost will be provided based upon the 60% Construction Document submission. These will be broken down to include major architectural, structural, plumbing, electrical, and mechanical elements. This Opinion of Probable Construction Costs will also include site improvements such as the parking lot, grading and utilities.

Deliverable: Consultant will provide the Opinion of Probable Construction Costs in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 4C

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 4 $532.00 Dodstone Architects Clerical $48.41 8 $387.28 R.E. Walsh Engineering Principal Engineer $149.93 3 $449.79 Bliss & Niytray Principal $178.77 2 $357.54 Hydra Engineering & Construction, LLC Project Engineer $111.92 5 $559.60 Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60

Fixed Price Cost Total: $3,013.81

Total for Subtask 4C: (Fixed Price Cost + Reimbursable) = $3,013.81

Subtask 4D: Water Tank (NFPA 1-18)

Description: If it is determined during Subtask 2c that a water tank will be required to satisfy NFPA 1-18, Bliss & Nyitray will provide engineering services for the required foundation. R.E. Walsh Engineering will provide direction regarding required flow rates and design pressures. The selection / design of the actual tank is assumed to be performed by Hydra. R.E. Walsh Engineering shall also review any cut sheets provided by Hydra Engineering for their basis-of-design to confirm compliance. Should a water tank not be required, these services will not be provided and no fees charged.

Deliverable: Foundation plans and tank details will be incorporated into the Construction Documents and be provided in pdf format.

Subtask 4D

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects CADD Operator $60.00 2 $120.00 Dodstone Architects Clerical $48.41 1 $48.41 R.E. Walsh Engineering Principal Engineer $149.93 4 $599.72 Bliss & Niytray Principal $178.77 1 $178.77 Bliss & Niytray Engineer $83.43 2 $166.86 Bliss & Niytray CADD Operator $93.86 1 $93.86 Hydra Engineering & Construction, LLC Project Engineer $111.92 16 $1,790.72

Hydra Engineering & Construction, LLC Principal Engineer $279.80 5 $1,399.00

Fixed Price Cost Total: $4,747.34

Total for Subtask 4D: (Fixed Price Cost + Reimbursable) = $4,747.34

Subtask 4E: Walton County Development Order Permitting

Description: Hydra will prepare and submit to Walton County for a Minor Development Order application, assuming this is the required permit based on the Pre-Application Meeting. This permit application requires an environmental review, South Walton Fire District Review, Walton County School Board review, Drainage Report, Grading and Drainage Plans, Site Plan, Utility Plan, Site Lighting – Photometric Plans, Landscape Plan (signed and sealed), Environmental Assessment and a Traffic Analysis.

Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 4E Walton County Development Order Permitting

Rate Hours Total Fixed

Price Cost

Alan Holt, ASLA Landscape Architect Landscape Architect $150.04 12 $1,800.48 Hydra Engineering & Construction, LLC Project Engineer $111.92 80 $8,953.60 Hydra Engineering & Construction, LLC Principal Engineer $279.80 20 $5,596.00 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Cost Price Total: $16,413.02

Permitting Fees: Walton Co Minor Development Order $900.00 Permitting Fees: Walton Co Environmental Review $225.00 Permitting Fees: Walton Co Engineering Review $3,600.00 Permitting Fees: Walton Co School Board Review $200.00 Permitting Fees: Walton Co SWFD Fire Review $200.00 Mileage (@ $0.445 per mile) 0 miles * trip * 0.445 = $0.00 Reimbursable Total Cost $5,125.00

Total for Subtask 4E: (Fixed Price Cost + Reimbursable) = $21,538.02

Subtask 5A: 90% Architectural Construction Documents

Description: The design team will prepare construction drawings that incorporate any comments received from BD during the previous subtasks. The drawings and specifications will be developed to a level sufficient for use in bidding and permitting services. The intent is that the only remaining changes between this and 100% are to address any comments received from BDC and to sign and seal the drawings.

Deliverable: Deliverables will consist of pdf files of the following:

90% Construction Document drawings

90% Architectural/Structural/Mechanical/Electrical Specification Booklet (at the discretion of the design team, some specifications may be shown on the drawings).

Fixed Price Cost:

Subtask 5A

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 2 $336.00 Dodstone Architects Registered Architect $133.00 53 $7,049.00

Dodstone Architects Graduate Architect $88.00 44 $3,872.00 Dodstone Architects CADD Operator $60.00 32 $1,920.00 Dodstone Architects Clerical $48.41 3 $145.23 R.E. Walsh Engineering Principal Engineer $149.93 37 $5,547.41 Bliss & Niytray Principal $178.77 2 $357.54 Bliss & Niytray Engineer $83.43 16 $1,334.88 Bliss & Niytray CADD Operator $93.86 16 $1,501.76

Fixed Price Cost Total: $22,063.82

Total for Subtask 5A: (Fixed Price Cost + Reimbursable) = $22,063.82

Subtask 5B: 90% Civil Plans

Description: 90% Plans consisting of updates from the 60% design review comments for the cover sheet, general notes, existing conditions, Master Utility Plan, Site Plan, Grading Plan, erosion control sheets, and construction details.

Deliverable: Consultant will provide 22”x34” sheet size drawings transmitted electronically in PDF format to project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 5B

Rate Hours Total Fixed

Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 55 $6,155.60 Hydra Engineering & Construction, LLC Principal Engineer $279.80 20 $5,596.00 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $11,814.54

Total for Subtask 5B: (Fixed Price Cost + Reimbursable) =$11,814.54

Subtask 5C: 90% Opinion of Probable Construction Costs

Description: A projected construction cost will be provided based upon the 90% Construction Document submission. These will be broken down to include major architectural, structural, plumbing, electrical, and mechanical elements. This Opinion of Probable Construction Costs will also include site improvements such as the parking lot, grading and utilities.

Deliverable: Consultant will provide the Opinion of Probable Construction Costs in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 5C

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 0 $0.00 Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 1 $48.41 R.E. Walsh Engineering Principal Engineer $149.93 2 $299.86 Bliss & Niytray Principal $178.77 1.5 $268.15 Hydra Engineering & Construction, LLC Project Engineer $111.92 2 $223.84 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Fixed Price Cost Total: $1,386.06

Total for Subtask 5C: (Fixed Price Cost + Reimbursable) = $1,386.06

Subtask 6A: 100% Architectural Construction Documents

Description: The design team will prepare construction drawings that incorporate any comments received from BDC during the previous subtasks. The drawings and specifications will be developed to a level sufficient for use in bidding, permitting, and construction services.

Deliverable: Deliverables will consist of pdf files of the following:

Signed and Sealed 100% Construction Document drawings labeled for Permit Review

Signed and Sealed 100% Architectural/Structural/Mechanical/Electrical Specification Booklet (at the discretion of the design team, some specifications may be shown on the drawings).

Subtask 6A

Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 10 $1,330.00 Dodstone Architects Graduate Architect $88.00 2 $176.00 Dodstone Architects CADD Operator $60.00 7 $420.00 Dodstone Architects Clerical $48.41 2 $96.82 R.E. Walsh Engineering Principal Engineer 149.93 7 $1,049.51 Bliss & Niytray Principal $178.77 2 $357.54 Bliss & Niytray Engineer $83.43 8 $667.44 Bliss & Niytray CADD Operator $93.86 12 $1,126.32

Fixed Price Cost Total: $5,307.63

Total for Subtask 6A: (Fixed Price Cost + Reimbursable) = $5,307.63

Subtask 6B: 100% Civil Plans

Description: 100% Civil Plans consisting of updates from the 90% design review comments.

Deliverable: Consultant will provide 22”x34” sheet size drawings transmitted electronically in PDF format digitally signed and sealed to FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 6B

Firm Name Position Classification Hourly Rate Hours

Total Fixed

Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 12 $1,343.04 Hydra Engineering & Construction, LLC Principal Engineer $279.80 4 $1,119.20 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $2,525.18

Total for Subtask 6B: (Fixed Price Cost + Reimbursable) = $2,525.18

Subtask 7A: Basic Architectural Permitting Services

Description: The building design team will provide an electronically signed and sealed drawing set and two printed signed and sealed sets on 22”x34” sheets for BDC’s use for acquiring a building permit. The design team will respond in writing to any permitting comments received.

Deliverable: An electronic copy of the signed and sealed sets will be emailed to BDC for their use.

A copy of any responses to comments will be issued in pdf format to BDC’s designated project manager. Two signed and sealed sets for use in acquiring the permit will be delivered to Hydra’s offices for permit submittals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 7A

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 14 $1,862.00 Dodstone Architects Graduate Architect $88.00 3 $264.00 Dodstone Architects CADD Operator $60.00 2 $120.00 Dodstone Architects Clerical $48.41 2 $96.82 R.E. Walsh Engineering Principal Engineer $149.93 3 $449.79 Bliss & Niytray Principal $178.77 2 $357.54

Fixed Price Cost Total: $3,234.15

Permitting Fees $0.00 (Covered under separate subtasks) Printing 227 Sheets * $2.20 per sheet=$499.40 Overnight Travel (if applicable)

N/A

Reimbursable Total Cost $499.40

Total for Subtask 7A: (Fixed Price Cost + Reimbursable) = $3,733.55

Subtask 7B: SFM Permit Application

Description: Dodstone will serve as the applicant on behalf of BDC and submit the drawings for permit review to the State Fire Marshall. The design team will respond to any comments received in writing.

Deliverable: A copy of any responses to comments will be issued in pdf format. The acceptance letter once acquired will be forwarded to BDC for their use.

Fixed Price Cost:

Subtask 7B

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 3 $399.00 Dodstone Architects Graduate Architect $88.00 3 $264.00 Dodstone Architects CADD Operator $60.00 3 $180.00 Dodstone Architects Clerical $48.41 1 $48.41

Fixed Price Cost Total: $975.41

Reimbursable Cost:

• For permitting fees: Not to exceed $6,000. A receipt of the actual permit fee collected will be provided. Ten percent will be added to the amount charged.

Permitting Fees $6,000.00 Printing Electronic Submittal Overnight Travel (if applicable)

N/A

Reimbursable Total Cost $6,000.00

Total for Subtask 7B: (Fixed Price Cost + Reimbursable) = $6,975.41

Subtask 7C: Bidding Description: The Design team will respond in writing to any bid questions or comments received prior to the cut-off date established by BDC for such questions. Any necessary revisions to the drawings or specifications in response to those questions will be provided.

Deliverable: Response to bid questions will be delivered in pdf format within 10 working days of written receipt of those comments.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language

Fixed Price Cost:

Subtask 7C

Firm Name Position Classification Hourly Rate Hours

Total Fixed

Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 15 $1,995.00 Dodstone Architects Graduate Architect $88.00 5 $440.00 Dodstone Architects CADD Operator $60.00 5 $300.00 Dodstone Architects Clerical $48.41 2 $96.82 R.E. Walsh Engineering Principal Engineer 149.93 2 $299.86 Bliss & Niytray Principal $178.77 1 $178.77 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total $4,716.55

Total for Subtask 7C: (Fixed Price Cost + Reimbursable) =$4,716.55

Subtask 8A: Construction Administration

Description: The design team shall review electronically submitted shop drawings and shall respond to any questions submitted by the contractor related to the project in writing. Our understanding is that BDC will be self-performing the pay application reviews, therefore that service is excluded.

Deliverable: Copies of any RFI responses will be provided in pdf format. Copies of reviewed shop drawings will be provided in pdf format.

Subtask 8A

Rate Hours

Total Fixed

Price Cost Dodstone Architects Principal $168.00 1 $168.00 Dodstone Architects Registered Architect $133.00 14 $1,862.00 Dodstone Architects Graduate Architect $88.00 8 $704.00 Dodstone Architects CADD Operator $60.00 6 $360.00 Dodstone Architects Clerical $48.41 1 $48.41 R.E. Walsh Engineering Principal Engineer 149.93 11 $1,649.23 Bliss & Niytray Principal $178.77 2 $357.54 Bliss & Niytray Engineer $83.43 12 $1,001.16 Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60 Hydra Engineering & Construction, LLC Project Engineer $111.92 12 $1,343.04 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $8,084.45

Total for Subtask 8A: (Fixed Price Cost + Reimbursable) =$8,084.45

Subtask 8B: Pre-Construction Meeting

Description: Upon request by BDC, Hydra and Dodstone will have one person from their offices attend the Pre-Construction meeting on site. Dodstone will prepare minutes for the meeting.

Deliverable: Minutes from the meeting will be delivered in pdf format to BDC’s designated project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8B

Rate Hours

Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 8 $1,064.00

Dodstone Architects Graduate Architect $88.00 0 $0.00 Dodstone Architects CADD Operator $60.00 0 $0.00 Dodstone Architects Clerical $48.41 1 $48.41 Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60 Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36 Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total $2,714.31

Total for Subtask 8B: (Fixed Price Cost + Reimbursable) =$2,714.31

Subtask 8C: Progress Site Visit #1 - Civil

Description: A progress site inspection by Hydra to review the status of the project during construction.

Deliverable: Site visit notes transmitted electronically in PDF format to project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8C

Rate Hours

Total Fixed

Price Cost Hydra Engineering & Construction, LLC Principal Engineer $279.80 2 $559.60 Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,486.43

Total for Subtask 8C: (Fixed Price Cost + Reimbursable) =$1,486.43

Subtask 8D: Substantial Completion Site Visit - Civil

Description: Hydra attending a site visit for substantial completion inspection.

Deliverable: Site visit notes transmitted electronically in PDF format to project manager.

Subtask 8D

Rate Hours

Total Fixed

Price Cost Hydra Engineering & Construction, LLC Principal Engineer $279.80 3 $839.40 Hydra Engineering & Construction, LLC Project Engineer $111.92 8 $895.36 Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,766.23

Total for Subtask 8D: (Fixed Price Cost + Reimbursable) =$1,766.23

Subtask 8E: Architectural Interim Site Visit 1

Description: The architect shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered within 5 working days of the site visit in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8E

Rate Hours

Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 8.5 $1,130.50 Dodstone Architects Clerical $48.41 1 $48.41 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,574.18 Total for Subtask 8E: (Fixed Price Cost + Reimbursable) =$1,574.18

Subtask 8F: Architectural Interim Site Visit 2

Description: The architect shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered within 5 working days of the site visit in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8F

Rate Hours

Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 8.5 $1,130.50 Dodstone Architects Clerical $48.41 1 $48.41 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,574.18

Total for Subtask 8F: (Fixed Price Cost + Reimbursable) =$1,574.18

Subtask 8G: Architectural Substantial Completion Site Visit

Description: The architect shall visit the project site upon request by BDC and upon notification that the project is Substantially Complete. A report will be issued confirming if the project is Substantially Complete. A punch list will be generated noting any remaining items that need to be correct by Contractor.

Deliverable: Field report/punch list will be delivered in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8G

Rate Hours

Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 12 $1,596.00 Dodstone Architects Clerical $48.41 1.5 $72.61 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $2,063.88 Total for Subtask 8G: (Fixed Price Cost + Reimbursable) =$2,063.88

Subtask 8H: Architectural Final Completion Site Visit

Description: Upon notification that the punch list items listed in the reports generated during any/all of the other site visits (both by architect and any of their sub-consultants), and upon request by BDC, the architect will review the project to confirm that the punch list items have been corrected. A report will be issued noting if there are any items on the punch list that remain to be corrected by the contractor. Note, if the contractor has not completed all of the task listed on the punch list, our understanding is that BDC will self-perform any remaining site reviews.

Deliverable: Field report/punch list will be delivered in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8H

Rate Hours

Total Fixed

Price Cost Dodstone Architects Principal $168.00 0.5 $84.00 Dodstone Architects Registered Architect $133.00 11 $1,463.00 Dodstone Architects Clerical $48.41 0.5 $24.20 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,882.47

Total for Subtask 8H: (Fixed Price Cost + Reimbursable) =$1,882.47

Subtask 8I: Structural Site Visit 1

Description: The structural engineer shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8I

Rate Hours

Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 0.5 $24.20 Bliss & Niytray Principal $178.77 1 $178.77 Bliss & Niytray Project Engineer $119.18 8 $953.44 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,733.68

Total for Subtask 8I: (Fixed Price Cost + Reimbursable) =$1,733.68

Subtask 8J: Structural Site Visit 2

Description: The structural engineer shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered in pdf format.

Subtask 8J

Rate Hours

Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 0.5 $24.20 Bliss & Niytray Principal $178.77 1 $178.77 Bliss & Niytray Project Engineer $119.18 8 $953.44 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,733.68

Total for Subtask 8J: (Fixed Price Cost + Reimbursable) =$1,733.68

Subtask 8K: Structural Site Visit 3

Description: The structural engineer shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8K

Rate Hours

Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 0.5 $24.20 Bliss & Niytray Principal $178.77 1 $178.77 Bliss & Niytray Project Engineer $119.18 8 $953.44

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,733.68

Total for Subtask 8K: (Fixed Price Cost + Reimbursable) =$1,733.68

Subtask 8L: MEP Site Visit 1

Description: An engineer from R.E. Walsh Engineering shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8L

Rate Hours

Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 0.5 $24.20 R.E. Walsh Engineering Principal Engineer $149.93 7 $1,049.51 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,650.98

Total for Subtask 8L: (Fixed Price Cost + Reimbursable) =$1,650.98

Subtask 8M: MEP Site Visit 2

Description: An engineer from R.E. Walsh Engineering shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered in pdf format.

Subtask 8M

Rate Hours

Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 0.5 $24.20 R.E. Walsh Engineering Principal Engineer $149.93 7 $1,049.51 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,650.98

Total for Subtask 8M: (Fixed Price Cost + Reimbursable) =$1,650.98

Subtask 8N: MEP Substantial Site Visit

Description: An engineer from R.E. Walsh Engineering shall visit the project site upon request by BDC. A report will be issued noting progress observed on the site and any items punch list items noticed that warrant correction by the contractor.

Deliverable: Field reports will be delivered in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8N

Rate Hours

Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 0.5 $24.20

R.E. Walsh Engineering Principal Engineer $149.93 7 $1,049.51 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,650.98

Total for Subtask 8N: (Fixed Price Cost + Reimbursable) =$1,650.98

Subtask 8O: MEP Final Site Visit

Description: An engineer from R.E. Walsh Engineering shall visit the project site upon request by BDC. A report will be issued noting any remaining mechanical, electrical, or plumbing items on the punch list that remain to be corrected.

Deliverable: Field reports will be delivered in pdf format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 8O

Rate Hours

Total Fixed

Price Cost Dodstone Architects Registered Architect $133.00 2 $266.00 Dodstone Architects Clerical $48.41 0.5 $24.20 R.E. Walsh Engineering Principal Engineer $149.93 6 $899.58 Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total $1,501.05

Total for…