CN-370000-CN306-T16CO2.pdf
PDF 288 KB Posted
- Contract number
- CN306
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for contract CN306, Task Assignment No. 16, Change Order No. 02. The consulting firm Hydra Engineering & Construction, LLC, represented by Leslie Weiss, PE, CGC, is the contractor on this project. The document was prepared for the Ochlockonee River State Park Pave Campground Road project located in Ochlockonee River State Park, Florida, with project number 61483C. All approvals were digitally signed on February 17-21, 2025, by the Budget Representative, Project Manager, and Contract Manager at FDEP, as well as by the consultant and Contract Authority.
The change order addresses a time extension for construction administration activities. The original task end date was November 25, 2024; the present task end date is February 23, 2025; and the new task end date is June 23, 2025, representing a net change of 120 days. The task amount includes reimbursement of $523.24 and a fixed fee of $106,499.53, bringing the total task amount with all change orders to $107,022.77. There is no net increase or decrease in the task amount for this specific change order, as the monetary adjustment is $0.00. The justification for the extension is to allow for construction administration to be completed per the consultant's proposal dated February 14, 2025.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN306 16 02 61483C
Ochlockonee River State Park Pave Campground Road
Hydra
Leslie Weiss, PE, CGC 850-926-2593 lahope@hydraengineering.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Time extension to allow for construction administration to be completed per the attached proposal dated 2/14/2025.
$ 523.24 $ 92,385.78 $ 92,909.02 $ 523.24 $ 106,499.53 $ 107,022.77 $ 0.00 $ 0.00
$ 523.24 $ 106,499.53 $ 107,022.77
12/5/22
11/25/24
2/23/25
6/23/25
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2025.02.17 12:34:32 -05'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2025.02.17 12:49:37 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2025.02.17 15:33:38 -05'00'
Leslie Weiss, PE, CGC Leslie Weiss Digitally signed by Leslie Weiss Date: 2025.02.17 16:01:18 -05'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2025.02.21 08:51:49 -05'00'
$ 0.00
Carron, Theresa
From: Leslie Weiss <lahope@hydraengineering.com> Sent: Friday, February 14, 2025 4:44 PM To: Carron, Theresa Cc: Finkbeiner, Donald Subject: CN306 TA16 Ochlockonee Pave Campground Roads
Follow Up Flag: Follow up Flag Status: Flagged
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Good afternoon Teri, We would like to request a 120 day extension on the Ochlockonee Pave Campground Roads project number 61483C to allow for the construction to be completed. This will put the new task end date at June 23, 2025.
Thank you, Leslie Weiss, PE, GCG, F.ASCE President Hydra Engineering & Construction, LLC 36 Jasper Thomas Road Crawfordville, FL 32327 Office (850) 926-2593
File details come from the government source that posted it. Updated .