CN-370000-CN306-T13CO2.pdf

PDF 481 KB Posted

Attached to
Master Agreement FL|CN306|0213c5976ed74492a857f85bd20cc16d
Contract number
CN306
Issued by
Florida

About this file

This document is a Task Assignment Change Order (CO2) issued by the Florida Department of Environmental Protection (FDEP) for work performed by Hydra Engineering & Construction, LLC at Gamble Rogers State Park in Florida. The change order was approved on January 25-31, 2024, and involves modifications to an existing task assignment related to road paving and sewer connection work. The FDEP Contract Manager is Ralph Perkins, and the consultant representative is Leslie Weiss, P.E. The project is managed through the Bureau of Design and Construction under Project No. 61364C.

The change order authorizes additional work for wastewater upgrades at Gamble Rogers State Park, increasing the total task amount from $93,257.72 to $156,032.41 through a net increase of $62,774.69 in reimbursable and fixed fee costs. The work comprises ten subtasks including sanitary sewer survey ($6,579.66), 30% civil design plans ($9,632.10), FDEP wastewater permit application ($10,076.14 including $500 permit fee), City of Flagler Beach utility coordination ($9,576.14), environmental report and site inspection ($2,560.74), and progressive design phases at 60%, 90%, and 100% completion levels for civil and electrical plans, totaling $62,274.69 in fixed costs and $500 in reimbursable expenses. The task execution period was extended from the original end date of December 31, 2023, to February 18, 2026, representing a 414-day extension. Payment is contingent upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN306-CMC1.pdf PDF
CN-370000-CN306-T10CO2.pdf PDF
CN-370000-CN306-T11CO1.pdf PDF
CN-370000-CN306-T19.pdf PDF
CN-370000-CN306-T20CO1.pdf PDF
CN-370000-CN306-T21CO1.pdf PDF
CN-370000-CN306-T22.pdf PDF
CN-370000-CN306-T23CO2.pdf PDF
CN-370000-CN306-T23CO3.pdf PDF
CN-370000-CN306-T23CO4.pdf PDF
CN-370000-CN306-T26CO1.pdf PDF
CN-370000-CN306-T28.pdf PDF
CN-370000-CN306-T31CO1.pdf PDF
CN-370000-CN306-T32CO1.pdf PDF
CN-370000-CN306-T33CO1.pdf PDF
CN-370000-CN306-T33CO2.pdf PDF
CN-370000-CN306-T3CO1.pdf PDF
CN-370000-CN306-T5CO1.pdf PDF
CN-370000-CN306-T8CO1.pdf PDF
CN-370000-CN306-T1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN306-T10 CO1.pdf PDF
CN-370000-CN306-T10 CO1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN306-T11CO2.pdf PDF
CN-370000-CN306-T16.pdf PDF
CN-370000-CN306-T16CO1.pdf PDF
CN-370000-CN306-T19CO3.pdf PDF
CN-370000-CN306-T1CO1.pdf PDF
CN-370000-CN306-T2.pdf PDF
CN-370000-CN306-T23.pdf PDF
CN-370000-CN306-T24.pdf PDF
CN-370000-CN306-T24CO2.pdf PDF
CN-370000-CN306-T24CO3.pdf PDF
CN-370000-CN306-T25.pdf PDF
CN-370000-CN306-T25CO2.pdf PDF
CN-370000-CN306-T27.pdf PDF
CN-370000-CN306-T27CO2.pdf PDF
CN-370000-CN306-T28CO1.pdf PDF
CN-370000-CN306-T31.pdf PDF
CN-370000-CN306-T5.pdf PDF
CN-370000-CN306-T6CO1.pdf PDF
CN-370000-CN306-T6CO2.pdf PDF
CN-370000-CN306-T7.pdf PDF
CN-370000-CN306-T8.pdf PDF
CN-370000-CN306-A1.pdf PDF
CN-370000-CN306-T10.pdf PDF
CN-370000-CN306-T12.pdf PDF
CN-370000-CN306-T13CO1.pdf PDF
CN-370000-CN306-T13CO3.pdf PDF
CN-370000-CN306-T14CO1.pdf PDF
CN-370000-CN306-T15.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN-306 13 CO2 61364C

Gamble Rogers State Park Road Paving & Sewer Connection

Hydra Engineering & Construction, LLC

Leslie Weiss, P.E. 850-926-2593 lahope@hydraengineering.com

Ralph Perkins or successor 850-245-2460 ralph.perkins@floridadep.gov

Please see the attached change order request for the Wastewater Upgrades, per the attached dated Jan,22, 2024

$ 719.62 $ 59,912.79 $ 60,632.41 $ 2,729.62 $ 90,528.10 $ 93,257.72 $ 500.00 $ 62,274.69 $ 62,774.69

$ 3,229.62 $ 152,802.79 $ 156,032.41

09/19/2022

12/31/2023

12/31/2024

02/18/2026

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.01.25 12:08:00 -05'00'

Rafael De Leon Rafael De Leon Digitally signed by Rafael De Leon Date: 2024.01.26 07:07:43 -05'00'

Ralph Perkins

Leslie Weiss

Bryan Bradner

61364C 37503000024 080039/23 423001 U3200 131500 QK $ 62,774.69

$ 62,774.69

Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.01.26 14:40:34 -05'00'

Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.01.31 13:25:15 -05'00'

Leslie Weiss Digitally signed by Leslie Weiss Date: 2024.01.26 16:50:33 -05'00'

HYDRA ENGINEERING & CONSTRUCTION, LLC

36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com

January 22, 2024

Rafael DeLeon Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: CN306, TA13, CO2

BDC Project No. 61364C TA-13 Change Order Request: Gamble Rogers State Park –Wastewater Upgrades

Dear Mr. DeLeon:

Please see the attached change order request with man-hour documentation for the Wastewater Upgrades at Gamble Roger State Park.

Please see the attached proposal summary and deliverables.

Sincerely, Leslie Weiss, P.E., C.G.C.

Hydra Engineering & Construction, LLC

Wastewater Upgrades Gamble Rogers State Park

Subtask 1D: Sanitary Sewer Survey Description: Limits of Survey are depicted on the attached Exhibit “A” (provided by the client).

The wastewater portion of the survey will include the roadway, shoulder area to within 15 feet, finished floor elevation of any buildings within the survey limits, all visible utilities, area of the existing septic systems. Septic areas to be shown to survey crews by park employees or representatives of the client.

Data collected sufficient to produce 1-foot contours.

Deliverable: Consultant will provide electronic copies (AutoCAD and pdf) digitally signed and sealed of the topographic survey.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 1D

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

O'Neal Surveying & Mapping, INC.

Survey Field Crew (3 Man Crew) $150.00 26 $3,900.00

O'Neal Surveying & Mapping, INC Licensed Surveyor $155.00 3 $465.00

O'Neal Surveying & Mapping, INC Drafting $80.00 22 $1,760.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $6,579.66

Total for Subtask 1D: (Fixed Price Cost + Reimbursable) = $6,579.66

Subtask 2C: 30% Civil Documents – Sanitary Sewer

Description: 30% Plans consisting of a cover sheet, general notes, existing conditions, Site Plan and Utility Plan sheets for the proposed sanitary sewer to the Maintenance area and a separate Utility

CN306 TA13 CO2

Plan for the Lift Station at the Beachside of the State Park. Hydra will have one site visit. It includes providing an Opinion of Probable Construction Cost.

Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2C

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Hydra Engineering &

Construction, LLC Project Engineer $111.92 48 $5,372.16

Hydra Engineering & Construction, LLC Principal Engineer $279.80 15 $4,197.00

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $9,632.10

Total for Subtask 2C: (Fixed Price Cost + Reimbursable) = $9,632.10

Subtask 2D: FDEP Wastewater Permit Application

Description: Preparation of Florida Department of Environmental Protection Domestic Wastewater Permit application for the sanitary sewer collection lines and the proposed lift stations. It also includes Response to Comments during the application process. Applications will be provided to the FDEP Project Manager for signature prior to submittal.

Deliverable: Consultant will provide the permit application in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2D

Firm Name Position Classification Hourly Rate Hours

Total Fixed

Price Cost Hydra Engineering &

Construction, LLC Project Engineer $111.92 60 $6,715.20

Construction, LLC Principal Engineer $279.80 10 $2,798.00

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $9,576.14

Reimbursable Cost:

Permit Application Fee $500.00 Printing N/A Electronic submittals Overnight Travel (if applicable)

N/A

Mileage (@ $0.445 per mile) 0 miles * 1 trip * 0.445 = $0.00 Reimbursable Total Cost $500.00

Total for Subtask 2D: (Fixed Price Cost + Reimbursable) = $10,076.14

Subtask 2E: City of Flagler Beach Utility Submittal

Description: Coordination with City of Flagler Beach and preparation of submittal drawings for the sanitary sewer collection lines and the proposed lift station. This subtask is required due to Gamble Rogers State Park ties into the City of Flagler Beach’s utilities. Please note that the contractor will be responsible for obtaining a Plumbing Permit and pay impact fees for tying into the City of Flagler Beach’s sanitary sewer system. These fees are not included in this proposal.

Deliverable: Consultant will provide the submittal documents in PDF format to the project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 2E

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Hydra Engineering &

Construction, LLC Project Engineer $111.92 60 $6,715.20

Hydra Engineering & Construction, LLC Principal Engineer $279.80 10 $2,798.00

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $9,576.14

Total for Subtask 2E: (Fixed Price Cost + Reimbursable) = $9,576.14

Subtask 3A: Environmental Report and Environmental Site Inspection Description: Florida Environmental and Land Services, Inc. (FELSI) will conduct a site visit of the project area and will perform a wetland delineation based upon State and Federal guidelines for the area of the sanitary sewer / wastewater improvements. The wetland line will be flagged using numbered flagging tape marked with Wetland Delineation. Wetland points or locations will be collected concurrent with the fieldwork using GPS. A general and protected species survey will also be conducted in conjunction with the fieldwork and GPS used to locate any observed environmental features. This information will be used in the SJRWMD Environmental Resource Permit application or application for exemption. If endangered and/or protected species are found on site, additional fieldwork or mapping of those species may be required.

This task does include a gopher tortoise survey of the wastewater portion of the project area.

Permitting and relocation of gopher tortoises is not included in this task. The survey and relocation will need to be completed at least 90 days prior to starting construction.

Deliverable: Consultant will site report in PDF format to the FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 3A Environmental Report

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost Florida Environmental & Land Services, Inc.

Principal Environmental Consultant $109.83 15 $1,647.45

Florida Environmental & Land Services, Inc. Staff Asst. $60.00 6 $360.00

Florida Environmental & Land Services, Inc. Senior Environmental Tech $54.00 5 $270.00

Hydra Engineering & Construction, LLC Principal Engineer $279.80 0.5 $139.90

Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92

Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Cost Price Total: $2,560.74

Total for Subtask 3A: (Fixed Price Cost + Reimbursable) = $2,560.74

Subtask 4A: 60% Civil Sanitary Sewer Plans

Description: 60% Plans consisting of updates from the 30% design review comments for the cover sheet, general notes, existing conditions, Master Utility Plan, Sanitary Sewer Plan & Profile sheets, erosion control sheets, and construction details. It also includes providing an Opinion of Probable Construction Cost.

Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 4A

Firm Name Position Classification Hourly Rate Hours

Total Fixed

Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 40 $4,476.80

Hydra Engineering & Construction, LLC Principal Engineer $279.80 15 $4,197.00

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $8,736.74

Total for Subtask 4A: (Fixed Price Cost + Reimbursable) =$8,736.74

Subtask 4B: 60% Electrical Documents

Description: New work will be presented as necessary to establish proposed system configuration and layout as necessary to establish electrical branch circuit for one new lift station and modification to existing electrical branch circuit to accommodate renovation of one existing lift station. All lift station equipment to be specified as part of civil work. Power to be derived from existing electrical panels located in the area. One site visit projected to accomplish in depth field work.

Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to the FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 4B

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost r.e. Walsh Engineering, Inc. Senior Engineer $149.93 29 $4,347.97

Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92

Hydra Engineering & Construction, LLC Principal Engineer $279.80 1 $279.80

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $4,802.63

Total for Subtask 4B: (Fixed Price Cost + Reimbursable) = $4,802.63

Subtask 5A: 90% Civil Plans

Description: 90% Plans consisting of updates from the 60% design review comments for the cover sheet, general notes, existing conditions, Master Utility Plan, plan and profile sheets for sanitary sewer, erosion control sheets, and construction details. It also includes providing an Opinion of Probable Construction Cost.

Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format to project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 5A

Firm Name Position Classification Hourly Rate Hours

Total Fixed

Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 30 $3,357.60

Hydra Engineering & Construction, LLC Principal Engineer $279.80 10 $2,798.00

Hydra Engineering & Construction, LLC Office Administrator $62.94 1 $62.94

Fixed Price Cost Total: $6,218.54

Total for Subtask 5A: (Fixed Price Cost + Reimbursable) =$6,218.54

Subtask 6A: 100% Civil Sanitary Sewer Plans

Description: 100% Civil Plans consisting of updates from the 90% design review comments. It also includes providing an Opinion of Probable Construction Cost.

Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format digitally signed and sealed to FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Subtask 6A

Firm Name Position Classification Hourly Rate Hours

Total Fixed

Price Cost Hydra Engineering & Construction, LLC Project Engineer $111.92 15 $1,678.80

Hydra Engineering & Construction, LLC Principal Engineer $279.80 5 $1,399.00

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total: $3,109.27

Total for Subtask 6A: (Fixed Price Cost + Reimbursable) = $3,109.27

Subtask 6B: 100% Electrical Plans

Description: 100% Electrical Plans consisting of updates from the 60% design review comments.

Deliverable: Consultant will provide 24”x36” sheet size drawings transmitted electronically in PDF format digitally signed and sealed to FDEP project manager.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 6B

Firm Name Position Classification Hourly Rate Hours

Total Fixed

Price Cost r.e. Walsh Engineering, Inc. Senior Engineer $149.93 8 $1,199.44

Hydra Engineering & Construction, LLC Project Engineer $111.92 1 $111.92

Hydra Engineering & Construction, LLC Principal Engineer $279.80 0.5 $139.90

Hydra Engineering & Construction, LLC Office Administrator $62.94 0.5 $31.47

Fixed Price Cost Total: $1,482.73

Total for Subtask 6B: (Fixed Price Cost + Reimbursable) = $1,482.73

Project Schedule:

Activity Duration (Calendar Days) Dates Subtask 1D- Sanitary Sewer Survey 60 Upon Receiving Authorization Subtask 2C: 30% Civil Sanitary Plans

45 TBD

Subtask 2D: FDEP Wastewater Permitting

60 TBD

Subtask 2E: City of Flagler Beach Permitting

60 TBD

Subtask 3A: Environmental Report 45 TBD Subtask 4A: 60% Civil Sanitary Sewer Plans

30 TBD

Subtask 4B: 60% Electrical Plans 30 TBD Subtask 5A: 90% Civil Sanitary Sewer Plans

30 TBD

Subtask 6A: 100% Civil Sanitary Sewer Plans

21 TBD

Subtask 6B: 100% Electrical Plans 21 TBD

Summary of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1D- Sanitary Sewer Survey $6,579.66 $0.00

Subtask 2C 30% Civil Sanitary Sewer Plans $9,632.10 $0.00

Subtask 2D FDEP Wastewater Permitting $9,576.14 $500.00

Subtask 2E City of Flagler Beach Utility Submittal $9,576.14 $0.00

Subtask 3A Environmental Report $2,560.74 $0.00

Subtask 4A 60% Civil Sanitary Sewer Plans $8,736.74 $0.00

Subtask 4B 60% Electrical Plans $4,802.63 $0.00

Subtask 5A 90% Civil Sanitary Sewer Plans $6,218.54 $0.00 Subtask 6A 100% Civil Sanitary Sewer Plans $3,109.27 $0.00

Subtask 6B 100% Electrical Plans $1,482.73 $0.00 Total Fixed Price Cost: $62,274.69 Total Reimbursable Cost: $500.00 Overall Total Cost: $62,774.69 Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)