- Contract number
- CN212
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN212, Task Assignment No. 09. The contracting parties are FDEP and Dodstone Group Architects, represented by consultant Joel L. Dodson, AIA. The project involves Beach Access Day Use Restroom ADA Modifications at T.H. Stone Memorial St. Joseph Peninsula State Park, with Project No. 6M111C. The change order was processed on December 10, 2020, and approved by FDEP officials including Budget Representative Greg Turral, Project Manager Don Finkbeiner, and Contract Manager Alyssa Skehan.
This change order constitutes a one-year time extension with no associated cost increase to allow the consultant to provide construction administration services. The original task completion date of December 30, 2020, was extended by 365 days to December 30, 2021. The total task amount remains $44,655.73, comprised of $500.00 in reimbursement and $44,155.73 in fixed fees, with no net increase or decrease in funding. The extension was requested because the project had not yet been put out to bid as of the change order date, and deliverables and performance measures remained as originally contracted.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN212 09 1 6M111C
T. H. Stone Memorial St. Joseph Peninsula State Park Beach Access Day Use Restroom ADA Modifications
Dodstone Group Architects
Karin Zawrotny 850-656-7326 kzawrotny@dodstone.com
Alyssa Skehan 850-245-2570 Philip.Stone@FloridaDEP.gov
This is a one year time extension to allow the consultant to provide construction administration services.
Please see request dated 12/10/2020 attached .
$ 500.00 $ 44,155.73 $ 44,655.73 $ 500.00 $ 44,155.73 $ 44,655.73 $ 0.00 $ 0.00 $ 0.00
$ 500.00 $ 44,155.73 $ 44,655.73
12/30/20
12/30/20
12/30/20
12/30/21
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2020.12.10 15:31:58 -05'00'
Don Finkbeiner Donald J. Finkbeiner Digitally signed by Donald J.
Finkbeiner Date: 2020.12.10 15:30:58 -05'00'
Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2020.12.18 08:30:17 -05'00'
Jody Dodson Joel L Dodson Digitally signed by Joel L Dodson Date: 2020.12.21 12:32:16 -05'00'
Michael W. Foster Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2020.12.21 13:37:54 -05'00'
$ 0.00
December 10, 2020
Mr. Donald Finkbeiner Project Manager Florida Department of Environmental Protection Bureau of Design & Construction 3900 Commonwealth Blvd. MS520 Tallahassee, Florida 32399
Re: T.H. Stone Memorial St. Joseph Peninsula State Park Beach Access Day Use Restroom ADA Modifications CN212, Task 09, 6M111C Change Order 01: Time Extension
Mr. Finkbeiner, Our contract completion date is currently listed as 12/31/2020. As the project has not yet been put out to bid, we recommend extending the contract time until 12/31/21.
This is a no cost time extension. Deliverables and Performance measures will remain as originally contracted.
Sincerely, Joel L. Dodson, AIA Principal Architect Dodstone Architects, Inc.