About this file
This is a Task Assignment Notification Form and detailed proposal for design and permitting services issued by the Florida Department of Environmental Protection (FDEP) to DodStone Architects for the Wekiwa Springs State Park Youth Camp Office project. The contract is identified as FDEP Contract No. CN212, Task Assignment No. TA11, with Project No. 61267C. The project manager is Laura Ross, and the FDEP contract manager is Jack Brady. DodStone Architects is represented by Karin Zawrotny. The project involves the design and permitting of a new Youth Camp Office facility, approximately 1,160 square feet with heated/cooled area and covered porch, to replace an existing infirmary at Wekiwa Springs State Park in Orange County, Florida.
The scope of work encompasses design and permitting services with a total task amount of $66,246.07, consisting of a fixed price cost of $63,003.15 and cost reimbursement not to exceed $3,242.92. Services span from execution through December 31, 2021, and include multiple subtasks: site-specific survey and data collection, pre-application meeting and site visit, program confirmation and schematic design, soil borings, 60% and 90% construction documents, 60% and 90% review meetings, 100% construction documents, bidding services, environmental resource permit, permitting services, and limited construction administration services. The proposal identifies participating subconsultants including George & Associates Consulting Engineers, Inc., FSM Engineering, Applied Research, Bliss & Niytray, Southeastern Survey & Mapping, and Ardaman & Associates, Inc. Construction Administration Subtasks 7a through 7m are noted as not currently authorized but can be initiated at a later date. Payment is to be made within 30 days of task completion and deliverable approval.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: I Task Assignment No.: Owner's Name: I Project No.:
CN212 TAll FDEP 61267C
Project Location: Project Name:
Wekiwa Springs State Park Youth Camp Office
Consultant Name:
DodStone Architects
Consultant Representative: Phone: Email:
Karin Zawrotny 850-656-7326 kzawrotny@dodstone.com
FDEP Contract Manager: Phone: Email:
Jack Brady or successor 850-245-2535 Jack.Brady@FloridaDEP.gov
Description of Task:
Consultant to provide design and permitting services per the proposal dated 2/19/2020. (Note that Construction
Administration Subtasks 7a through 7m are not currently authorized, but can be initiated at a later date.)
Project Manager: Laura Ross or successor
Start Date: I Upon execution Completion Date: I 12/3 l /2021
Greg Turral
Budget Representative, FDEP
Laura Ross
Project Manager, FDEP
Jack Brady
Contract Manager, FDEP
Joel Dodson
Consultant
Michael W. Foster, Jr.
Contract Authority, FDEP
Proiect # Grant# On!: Code
61267C 37503006080
29 digit FLAIR Code:
Schedule
Fixed Price Cost: $63,003.15 Cost Reimbursement not to exceed: $3,242.92
Total Task Amount: $ 66.246.07 Approval Signatures:
Greg Ory Tu rra I Digitally signed by Gregory Turral Date: 2020.03.04 17:06:29 -05'00'
Signature
La Ura S. Ross Digitally signed by Laura S. Ross Date: 2020.03.05 08:43:10 -05'00'
Signature
J a Ck B rad Y Digitally signed by Jack Brady Date: 2020.03.0610:10:22 -05'00'
Signature
Joel L Dodson
Signature
Digitally signed by Joel L Dodson Date: 2020.03.10 15:01 :39 -04'00'
Date
Date
Date
Cat/Year Fund Module Obiect Code EO
080039/19 423001 U3200 1315000 QK
Total:
Amount
$66,246.07
$66,246.07
ARCHITECTS
Total Costs for Subtask 4b: $741.00
Subtask 5 - Preparation of 100% Construction Documents
Description: Incorporate any comments received previously from DEP regarding the 90% Construction Document Submission.
Deliverables: : Deliverables will consist of pdf files the drawings and specifications developed during this phase of work. All submissions will be sent electronically in pdf format.
Schedule: As summarized under the Project Schedule summary.
Performance Measures: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely, and that the scope has not exceeded DEP's original intent.
Fees:
Subtask 5 Preparation of 100% Construction Documents
Total Fixed Firm Name Position Classification Hourlv Rate Hours Price Cost
Dodstone Architects Principal $168.00 1 $168.00
Registered Architect $133.00 3 $399.00
Graduate Architect $88.00 6 $528.00
CADD Operator $60.00 4 $240.00
$1 335.00
FSM En 1 ineer 110.15 2 s er 80.38 0.00
CADD Tech 49.23 3
Admin 34.02
A lied Research ineer 1 134.00
59.00 1 59.00
$193.00
Bliss & Niytray Principal $178.77 1 $178.77
Enqineer $83.43 4 $333.72
Sr. CAD Technician $93.86 4 $375.44
$887.93
Georqe & Associates Proiect Manaqer $129.00 4 $516.00
Project Manaqer II $76.44 2 $152.88
Sr. Enqineer Technician $72.00 6 $432.00
$1,100.88
Subtask 5 Preoaration of 100% Construction Documents $4,015.44
Dodstone Architects I 3011-1 Powell Road I Tallahassee, FL 32308 I 850.656.7326 I #AA26001632