CN-370000-CN212-T11CO1.pdf

PDF 419 KB Posted

Attached to
Master Agreement FL|CN212|aec15af757aa90b3e69d3dac479b0889
Contract number
CN212
Issued by
Florida

About this file

This document is a Task Assignment Change Order Form (Change Order No. 1) issued by the Florida Department of Environmental Protection (FDEP) for contract CN212, Task Assignment TA11. The project involves the Youth Camp Office at Wekiwa Springs State Park and is being executed by DodStone Architects as the primary consultant, with subcontractors including FSM Engineering, George & Associates Consulting Engineers, Southeastern Surveying, Ardaman & Associates, and others. The contract manager for FDEP is Philip Stone, and the project manager is Laura Ross. The change order was executed with digital signatures between June 2020 and January 2021.

The change order authorizes four additional service tasks valued at $14,882.18, bringing the total contract amount from $66,246.07 to $81,128.25. The tasks include: Subtask 1c (Site Surveying and Soils Testing) at $2,154.44, requiring topographic survey expansion and permeability testing for stormwater management; Subtasks 3d, 4c, and 7n (Fire Sprinkler Design) totaling $7,796.14, covering design services at 60% and 90% construction document phases plus shop drawing review; and Subtask 6d (Stormwater Design) at $4,931.60, for obtaining Orange County Development Engineering Division approval of on-site stormwater management facilities. All tasks are fixed-fee arrangements with no reimbursable costs. The project end date remains December 31, 2021, with no time extension. The change order addresses additional scope required for permitting, including building expansion impacts, sprinkler system requirements for R-3 occupancy classification, and stormwater management for increased impervious surface area.

View the file

Other files

File Type Posted
CN-370000-CN212-CMC1.pdf PDF
CN-370000-CN212-CMC2.pdf PDF
CN-370000-CN212-T10.pdf PDF
CN-370000-CN212-T11.pdf PDF
CN-370000-CN212-T15CO3.pdf PDF
CN-370000-CN212-T17.pdf PDF
CN-370000-CN212-T18.pdf PDF
CN-370000-CN212-T18CO1.pdf PDF
CN-370000-CN212-T23CO2.pdf PDF
CN-370000-CN212-T8CO2.pdf PDF
CN-370000-CN212-T9.pdf PDF
CN-370000-CN212-T9CO1.pdf PDF
CN-370000-CN212-TA05C01.pdf PDF
CN-370000-CN212-TA1.pdf PDF
CN-370000-CN212-TA14.pdf PDF
CN-370000-CN212.pdf PDF
PC-370000-CN212.pdf PDF
CN-370000-CN212-T15CO1.pdf PDF
CN-370000-CN212-T15CO2.pdf PDF
CN-370000-CN212-T18CO4.pdf PDF
CN-370000-CN212-T1CO2.pdf PDF
CN-370000-CN212-T22CO1.pdf PDF
CN-370000-CN212-T23CO4.pdf PDF
CN-370000-CN212-T24CO3.pdf PDF
CN-370000-CN212-T25.pdf PDF
CN-370000-CN212-T4.pdf PDF
CN-370000-CN212-T8.pdf PDF
CN-370000-CN212-T8CO3.pdf PDF
CN-370000-CN212-AM1.pdf PDF
CN-370000-CN212-CMC3.pdf PDF
CN-370000-CN212-T11CO2.pdf PDF
CN-370000-CN212-T12.pdf PDF
CN-370000-CN212-T13.pdf PDF
CN-370000-CN212-T14CO1.pdf PDF
CN-370000-CN212-T16.pdf PDF
CN-370000-CN212-T18CO2.pdf PDF
CN-370000-CN212-T18CO3.pdf PDF
CN-370000-CN212-T19CO1.pdf PDF
CN-370000-CN212-T21.pdf PDF
CN-370000-CN212-T22.pdf PDF
CN-370000-CN212-T23CO3.pdf PDF
CN-370000-CN212-T5.pdf PDF
CN-370000-CN212-T7.pdf PDF
CN-370000-CN212-T7CO1.pdf PDF
CN-370000-CN212-TA15.pdf PDF
CN-370000-CN212-TA3.pdf PDF
CN-370000-CN212-TA8 CO4.pdf PDF
CN-370000-CN212-T11CO3.pdf PDF
CN-370000-CN212-T14CO2.pdf PDF
CN-370000-CN212-T14CO3.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN212 TA11 1 61267C

Wekiwa Springs State Park Youth Camp Office

DodStone Architects

Karin Zawrotny 850-656-7326 kzawrotny@dodstone.com

Philip Stone 850-245-2570 Philip.Stone@FloridaDEP.gov

Consultant to provide additional surveying, soils testing, fire sprinkler design, and stormwater design per proposal dated 6/10/2020.

$ 3,242.92 $ 63,003.15 $ 66,246.07 $ 3,242.92 $ 63,003.15 $ 66,246.07

$ 0.00 $ 14,882.18 $ 14,882.18 $ 3,242.92 $ 77,885.33 $ 81,128.25

3/11/2020

12/31/2021

12/31/2021

12/31/2021

Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2020.06.30 15:18:41 -04'00'

Laura Ross Laura S. Ross Digitally signed by Laura S. Ross Date: 2020.07.01 07:58:56 -04'00'

Philip Stone P.T. Stone Digitally signed by P.T. Stone Date: 2020.08.28 15:47:29 -04'00'

Joel Dodson Joel L Dodson Digitally signed by Joel L Dodson Date: 2020.08.31 10:20:36 -04'00'

Michael W. Foster Jr. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2021.01.25 13:53:34 -05'00'

61267C 37503006080 080039/19 67500 U3200 131500 XR $ 14,882.18

$ 14,882.18

June 10, 2020

Ms. Laura Ross Project Manager Florida Department of Environmental Protection Bureau of Design and Construction

Re: CN212 TA11 CO#1

The Youth Camp Office Wekiwa Springs State Park Additional Services regarding:

Location of Sanitary Cleanout Building Sprinkler Systems Storm Water Management

Ms. Ross, We are submitting this proposal to address some of the additional scope that is required in order to be able to acquire a permit for the building as currently proposed.

Background

The previous building that this structure replaces was approximately 1,200 sf. The current design is 1,624 sf of heated-and-cooled area and 2,268 sf under-roof. In addition, DEP requested that a walkway encircle the building. It is estimated that the sidewalk will add another 1,173 sf of impervious area. During the pre-submittal meeting, the Development Engineering Division of Orange County indicated that any increase beyond the original impervious would require the design and construction of a stormwater management facility to provide water quality treatment. This facility will have to be reviewed and approved by the Development Engineering Division of Orange County. To complete this work, a soil boring will need to be taken where the water retention is proposed in order to determine the properties of the soils in this location. The survey area will also need to be expanded to include this area.

Onsite discussions revealed that the existing sewer line connecting to the building has undergone repairs in the past. A new line between the building and nearby manhole was recommended by the design team and accepted by DEP. Orange County requires that all trees impacted by construction be identified. The survey area will need to be expanded to locate these.

During the Pre-Application meeting, the use of the building was discussed with the Orange County Building Department. They indicated that the building will need to be listed as both a Business Occupancy and as a Residential Property. As such the more stringent requirements for each will need to be addressed. As a Business Occupancy, full ADA compliance must be met. In addition, as the building is over 1,500 sf, a hi-lo water fountain will need to be included. The R classification will require the windows in all bedrooms to be sized to allow for egress. In addition, a sprinkler system must be provided. The only aspect of this that requires additional services is the inclusion of the sprinkler system.

Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AA26001632

Task 1c: Site Surveying and Soils Testing Description: Southeastern Surveying will request a design ticket from Sunshine 811 as required and provide the utility contact information received from the Design Ticket. Southeastern Surveying will provide a Topographic Survey meeting the Standards of Practice as prescribed by the Florida Board of Professional Land Surveyors in Chapter 5J-17FAC, Section 472.027 of the Florida Statues. The survey will focus on two areas of the site, and include the following:

Between Proposed construction site and Manhole:

• Locate and detail the sanitary cleanout to include size, type, top elevation, and invert elevation.

• Obtain spot elevations on natural found and existing improvements suitable for interpolation of one-foot contours to be shown on the final drawing.

• Establish a minimum of two (2) site benchmarks.

• Topographic coverage will be limited to the area outlined in yellow on the attached areal exhibit dated May 14, 2020.

• Locate trees 6-inch and greater diameter breast height (DBH)

Survey expansion to address location of building and stormwater retention

• Obtain spot elevations on natural found and existing improvements suitable for interpolation of one-foot contours to be shown on the final drawing Sealant between the exterior precast panels

• Topographic coverage will be limited to the area outlined in yellow on the attached areal exhibit dated May 14, 2020.

• Locate trees 6-inch and greater diameter breast height (DBH) Note: The area required for this work would have been less if the initial survey had been shifted to the NW of the original building site. Dodstone will be covering 100% of the costs for Southeastern Survey to perform the portion of the survey related to the building location and stormwater retention.

Ardaman & Associates will perform a field permeability test at the location of the proposed stormwater swale. The field permeability test will include installing a solid-walled PVC casing, snugly fit, into a 4-inch diameter auger boring. The bottom of the pipe will be open and raised 1 foot above the bottom of the boring. The bottom 1 foot of the boring will be gravel-packed. The rate water is taken in by the formation is measured and used to calculate permeability. The test will be run as a “constant head” test by maintaining the water level in the casing at ground surface level, or as a “falling head” test in which the rate of water drop will be measured. (Note: the costs listed below assume that this work will be conducted at the same time as the soil borings for use in verifying the soil’s load bearing characteristics below the foundations. If conducted at a separate time, additional charges would apply).

Deliverables: Deliverables will consist of electronic pdf files of the site specific survey sheets and an electronic autocad file of the site specific topographical survey and electronic copies in pdf format of the report prepared by Ardaman & Associates.

Schedule: 25 working days from written receipt of notice to proceed.

Performance Requirements: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 1c Site Surveying and Soils Testing

Firm Name Position Classification

Hourly Rate Hours

Total Fixed

Price Cost

Dodstone Architects Registered Architect $133.00 2 $266.00

$266.00

Southeastern Survey & Mapping

4-person Survey Crew $202.35 3 $607.05

2-person Survey Crew $118.13 2 $236.26 to manhole Surveyor & Mapper $101.64 0.5 $50.82

Sr. Surveyor & Mapper $174.79 0.5 $87.40

$981.53

Southeastern Survey & Mapping

4-person Survey Crew $202.35 2 $404.70

2-person Survey Crew $118.13 1 $118.13 for stormwater Surveyor & Mapper $101.64 0.5 $50.82

Sr. Surveyor & Mapper $174.79 0.5 $87.40

$661.05 Credit associated with shift of building to the NW 100% -$661.05 $0.00

George & Associates Project Manager $129.00 1 $129.00 $129.00

Ardaman & Associates, Inc.

Principal Engineer $191.46 0.5 $95.73

Asst. Project Engineer $93.03 1 $93.03

CAD Operator $60.00 0.5 $30.00

Word Processor $48.30 0.5 $24.15

Subtotal Engineering

Services $242.91

Mobilization of Equip $200.00 1 $200.00

Field Permeability Test $335.00 1 $335.00

Subtotal

Field $535.00

Subtask 1c Site Surveying and Soils Testing $2,154.44

Task 1c – Reimbursable Costs: $0

Total Task 1c Costs:

$2,154.44

Tasks 3d, 4c, and 7n: Fire Sprinkler Design Description: Engineering services will be provided by FSM Engineering to provide Fire Protection system that will comply with requirements for a R-3 type occupancy. The system will be designed to comply with the appropriate Florida Building Codes. Plans will indicate coverage and hazard area designations. A detailed fire sprinkler design including hydraulic calculations are excluded and are anticipated to be performed by the fire sprinkler sub-contractor.

Dodstone Architects will coordinate the drawings with this work, and show head locations on the reflected ceiling plans.

The results of a flow test are required in order to design this system. Robert George and Associates will develop a map of the existing water mains and develop a hydraulic model that demonstrations the available residual pressure at an established flowrate. Design calculations will be submitted to the State Fire Marshall and Orange County Building Department to assist in obtaining the required approvals and permits from those agencies.

Deliverables: Deliverables will be incorporated into the 60% (Task 3d) and 90% (Task 4c) Construction Document deliverables. In the 60% Submittals, head locations and basic pipe locations will be shown. In the 90% Submission, the specifications as required to acquire a permit and for the specialty engineer to complete the hydraulic calculations will be added. George & Associates, Consulting Engineers, Inc. will submit a Needed Fire Flow Report documenting the available residual pressure and flow for the new proposed building. The shops prepared by the specialty sub-contractor will be reviewed (Task 7n) during Construction Administration. Copies of those shops will be shared with DEP.

Schedule: No impact to the original delivery time table.

Performance Requirements: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 3d Sprinkler System - 60% CDs

Firm Name Position Classification

Hourly Rate Hours

Total Fixed

Price Cost

Dodstone Architects Registered Architect $133.00 4 $532.00

CADD Operator $60.00 2 $120.00 $652.00

FSM Engineering Principal/Senior Engineer $130.64 0.5 $65.32

Project Engineer $110.15 4 $440.60 Staff Engineer $80.38 3.5 $281.33 CADD Tech $49.23 5 $246.15 $1,033.40

George & Associates Project Manager $129.00 8 $1,032.00

II $76.44 20 $1,528.80

$2,560.80

Subtask 3d Sprinkler System - 60% CDs $4,246.20

Subtask 4c Sprinkler System - 90% CDs

Position Classification

Hourly Rate Hours

Total Fixed

Price Cost

Dodstone Architects Registered Architect $133.00 4 $532.00

CADD Operator $60.00 1 $60.00 $592.00

Engineer $130.64 0.5 $65.32

Project Engineer $110.15 4 $440.60 Staff Engineer $80.38 3.5 $281.33 CADD Tech $49.23 5 $246.15 $1,033.40

Associates Project Manager $129.00 6 $774.00

II $76.44 10 $764.40

$1,538.40

Subtask 4c Sprinkler System - 90% CDs $3,163.80

Subtask 7n Sprinkler System - shop review

Position Classification

Hourly Rate Hours

Total Fixed

Price Cost

Dodstone Architects Registered Architect $133.00 0.5 $66.50

$66.50

Engineer $130.64 0.5 $65.32

Project Engineer $110.15 2 $220.30 Admin $34.02 1 $34.02 $319.64

Subtask 7n Sprinkler System - shop review $386.14

Tasks 3d, 4c, and 7n – Reimbursable Costs: $0

Total Task 3d Costs (60% Design of Sprinkler System):

$4,246.20

Total Task 4c Costs (Completion of Sprinkler System Design):

$3,163.80

Total Task 7n Costs (Shop Review of Sprinkler System):

$386.14

Task 6d: Stormwater Design Description: George & Associates, Consulting Engineers, Inc. will assist in obtaining approval from the Development Engineering Division of Orange County for the construction of an on-site stormwater management facility for the increase of impervious are beyond the existing building footprint of approximately 1,200 square feet.

George & Associates, Consulting Engineers, Inc. will submit site plan drawings, narratives, and design calculations to the Development Engineering Division of Orange County to obtain a permit for the construction of an on-site stormwater management facility.

Deliverable: George & Associates, Consulting Engineers, Inc. will submit a copy of any necessary documents required to acquire a permit from the Development Engineering Division of Orange County.

Schedule: 30 working days from Performance Requirements: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 6d Stormwater Design

Firm Name Position Classification

Hourly Rate Hours

Total Fixed

Price Cost

Dodstone Architects Registered Architect $133.00 2 $266.00

$266.00

Associates Project Manager $129.00 8 $1,032.00

II $76.44 40 $3,057.60

Sr. Engineer Technician $72.00 8 $576.00

$4,665.60

Subtask 6d Stormwater Design $4,931.60

Task 6d – Reimbursable Costs: $0

Total Task 6d Costs:

$4,931.60

The total increase to the contract if all Tasks is accepted by DEP would be $14,882.18

Summary Provider Base

Service Additional

Service CO#1 CA Subtotal Reimb. Total Y/N

DS 483.00 999.00 999.00

SSM CO

GA 516.00

DS 350.00 2,801.00 542.92 3,343.92

GA 2,451.00

DS 266.00 2,154.44 2,154.44

SSM 981.53

GA 129.00

ARD 777.91

DS 4,312.00 665.00 6,615.00 6,615.00

GA 1,638.00

DS 319.50 3,536.07 3,536.07

AAI 3,216.57

DS 7,421.00 16,111.06 16,111.06

FSM 2,066.80

ARD 1,008.00

BNI 1,775.86

GA 3,839.40

DS 639.00 1,245.71 1,245.71

FSM 254.32

ARD 134.00

BNI 89.39

GA 129.00

DS 483.00 741.00 741.00

GA 258.00

DS 652.00 4,246.20 4,246.20

FSM 1,033.40

GA 2,560.80

DS 8,242.00 15,703.95 15,703.95

FMS 3,205.77

ARD 697.00

BNI 2,443.30

GA 1,115.88

DS 483.00 741.00 741.00

GA 258.00

DS 592.00 3,163.80 3,163.80

FSM 1,033.40

GA 1,538.40

DS 1,335.00 4,015.44 4,015.44

FSM 498.63

ARD 193.00

BNI 887.93

GA 1,100.88

DS 899.00 2,039.41 2,039.41

FSM 319.64

ARD 126.00

BNI 178.77

GA 516.00

DS 217.00 1,497.40 700.00 2,197.40

GA 1,280.40

DS 1,333.00 4,301.84 2,000.00 6,301.84

FSM 319.64

ARD 126.00

BNI 268.16

GA 2,255.04

DS 266.00 4,931.60 4,931.60

GA 4,665.60

DS 2,820.00 5,250.30 5,250.30

FSM 1,020.76

ARD 536.00

BNI 357.54

GA 516.00

DS 1,662.50 1,662.50 320.14 1,982.64

DS 1,662.50 1,662.50 320.14 1,982.64

DS 199.50 1,941.50 320.14 2,261.64

ARD 1,742.00

DS 199.50 1,636.54 320.14 1,956.68

FSM 1,437.04

DS 199.50 1,636.54 320.14 1,956.68

FSM 1,437.04

DS 133.00 1,283.14 320.14 1,603.28

BNI 1,150.14

DS 133.00 1,283.14 320.14 1,603.28

BNI 1,150.14

DS 133.00 1,681.00 321.92 2,002.92

GA 1,548.00

DS 133.00 2,808.52 321.92 3,130.44

GA 2,675.52

DS 1,995.00 1,995.00 320.14 2,315.14

DS 1,862.00 1,862.00 320.14 2,182.14

DS 66.50 386.14 386.14

FSM 319.64

Design Phase Fees: 35,568.29 16,940.94 9,564.45 CA fees: 23,750.37 8,790.96 5,317.74 Total 59,318.66 25,731.90 14,882.19

NTE

Subtask 7n

Sprinkler System -shop review

Y

Subtask 4c

Sprinkler System - 90% CDs

N

Subtask 6d

Stormwater Design N

Subtask 1c

Site Surveying and Soils Testing N

Subtask 3d

Sprinkler System - 60% CDs

N

N

N

N

Y

Y

YPermitting Services

Subtask 7b

Pre-Construction Site meeting

N

N

N

N

N

N

N

Subtask 7m

Architectural Final Completion Site Visit

Subtask 3b

Construction Cost Projection based upon

60% CDs

Subtask 7h

Structural Site Visit - Framing/Roof

Subtask 7g

Subtask 7a

Structural Site Visit - Foundation

Subtask 7j

Subtask 1a

Site Specific Survey & Data Collection

Subtask 3a

Preparation of 60% Construction Documents

Subtask 6b

Limited Construction Administration Services (excluding site visits)

Subtask 1b

Subtask 5 Preparation of 100% Construction Documents

Subtask 6c

Subtask 4a

Subtask 6a

Subtask 7c

Substantial Civil Site Visit

Subtask 7k

Architectural Substantial Completion Site Visit

Subtask 7f

Mechanical Site Visit

Subtask 7i

Interim Civil Site Visit

99,932.74 6,768.02 106,700.76

Subtask 2a

Subtask 4b

90% Review Meeting

Architectural Interim Site Visit 1

Electrical Site Visit

Subtask 7e

Subtask 3c

Subtask 2b

Pre-Application Meeting & Site Visit

Soil borings

Program Confirmation & Schematic Design

Plumbing Site Visit

Bidding Services

Environmental Resource Permit

Preparation of 90% Construction Documents

60% Review Meeting

Subtask 7d

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Proposed Project Schedule In all cases, the deliverables for a given Subtask will be provided to DEP on or before the time frame listed below. DEP review times are not listed, but are assumed to occur between each Subtask.

Written acceptance of a submission from DEP are assumed to include all comments pertaining to that submission. Receipt of additional comments later may require an extension of the subsequent deadline.

Task Work From Days Subtask 1a: Survey & Data Collection 25 Date of execution of agreement COMPLETED Subtask 1b: Pre-App Meeting 45 Date of execution of agreement COMPLETED Subtask 1c: Site Survey/Soil Test 25 Date of approval of CO#1 Subtask 2a: Programming & Schem.

Architectural portion 25 Date of execution of agreement COMPLETED Civil portion 20 DEP approval of Subtask 1a deliverables COMPLETED Subtask 2b: Soil Borings 20 Date of approval of CO#1 Subtask 3a: 60% CDs 30 DEP approval of Subtask 2a deliverables Subtask 3b: Cost Projection 5 Submission of Subtask 3a Subtask 3c: 60% Review Meeting 5 From date of review meeting Subtask 3d: 60% Sprinkler Design To be submitted along with Subtask 3a Subtask 4a: 90% CDs 25 DEP approval of Subtask 3a, 3b,& 3c deliverables Subtask 4b: 90% Review Meeting 5 From date of review meeting Subtask 4c: 90% Sprinkler Design To be submitted along with Subtask 4a

Summary Provider Base

Service Additional

Service CO#1 CA Subtotal Reimb. Total Y/N

DS 483.00 999.00 999.00

SSM CO

GA 516.00

DS 350.00 2,801.00 542.92 3,343.92

GA 2,451.00

DS 266.00 2,154.44 2,154.44

SSM 981.53

GA 129.00

ARD 777.91

DS 4,312.00 665.00 6,615.00 6,615.00

GA 1,638.00

DS 319.50 3,536.07 3,536.07

AAI 3,216.57

DS 7,421.00 16,111.06 16,111.06

FSM 2,066.80

ARD 1,008.00

BNI 1,775.86

GA 3,839.40

DS 639.00 1,245.71 1,245.71

FSM 254.32

ARD 134.00

BNI 89.39

GA 129.00

DS 483.00 741.00 741.00

GA 258.00

DS 652.00 4,246.20 4,246.20

FSM 1,033.40

GA 2,560.80

DS 8,242.00 15,703.95 15,703.95

FMS 3,205.77

ARD 697.00

BNI 2,443.30

GA 1,115.88

DS 483.00 741.00 741.00

GA 258.00

DS 592.00 3,163.80 3,163.80

FSM 1,033.40

GA 1,538.40

DS 1,335.00 4,015.44 4,015.44

FSM 498.63

ARD 193.00

BNI 887.93

GA 1,100.88

DS 899.00 2,039.41 2,039.41

FSM 319.64

ARD 126.00

BNI 178.77

GA 516.00

DS 217.00 1,497.40 700.00 2,197.40

GA 1,280.40

DS 1,333.00 4,301.84 2,000.00 6,301.84

FSM 319.64

ARD 126.00

BNI 268.16

GA 2,255.04

DS 266.00 4,931.60 4,931.60

GA 4,665.60

DS 2,820.00 5,250.30 5,250.30

FSM 1,020.76

ARD 536.00

BNI 357.54

GA 516.00

DS 1,662.50 1,662.50 320.14 1,982.64

DS 1,662.50 1,662.50 320.14 1,982.64

DS 199.50 1,941.50 320.14 2,261.64

ARD 1,742.00

DS 199.50 1,636.54 320.14 1,956.68

FSM 1,437.04

DS 199.50 1,636.54 320.14 1,956.68

FSM 1,437.04

DS 133.00 1,283.14 320.14 1,603.28

BNI 1,150.14

DS 133.00 1,283.14 320.14 1,603.28

BNI 1,150.14

DS 133.00 1,681.00 321.92 2,002.92

GA 1,548.00

DS 133.00 2,808.52 321.92 3,130.44

GA 2,675.52

DS 1,995.00 1,995.00 320.14 2,315.14

DS 1,862.00 1,862.00 320.14 2,182.14

DS 66.50 386.14 386.14

FSM 319.64

Design Phase Fees: 35,568.29 16,940.94 9,564.44 CA fees: 23,750.37 8,790.96 5,317.74 Total 59,318.66 25,731.90 14,882.18

NTE

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Pre-Application Meeting & Site Visit

Soil borings

Program Confirmation & Schematic Design

Plumbing Site Visit

Bidding Services

Environmental Resource Permit

Preparation of 90% Construction Documents

60% Review Meeting

99,932.74 6,768.02 106,700.76

Subtask 2a

Subtask 4b

90% Review Meeting

Architectural Interim Site Visit 1

Electrical Site Visit

Subtask 7e

Subtask 3c

Subtask 6a

Subtask 7c

Substantial Civil Site Visit

Subtask 7k

Architectural Substantial Completion Site Visit

Subtask 7f

Mechanical Site Visit

Subtask 7i

Interim Civil Site Visit

Subtask 7d

Site Specific Survey & Data Collection

Subtask 3a

Preparation of 60% Construction Documents

Subtask 6b

Limited Construction Administration Services (excluding site visits)

Subtask 1b

Subtask 5 Preparation of 100% Construction Documents

Subtask 6c

Subtask 4a

Subtask 7m

Architectural Final Completion Site Visit

Subtask 3b

Construction Cost Projection based upon

60% CDs

Subtask 7h

Structural Site Visit - Framing/Roof

Subtask 7g

Subtask 7a

Structural Site Visit - Foundation

Subtask 7j

Subtask 7b

Pre-Construction Site meeting

N

N

N

N

N

N

N

Subtask 1a

N

N

N

Y

Y

Y

Subtask 1c

Site Surveying and Soils Testing N

Subtask 3d

Sprinkler System - 60% CDs

N

Subtask 2b

Subtask 7n

Sprinkler System -shop review

Y

Subtask 4c

Sprinkler System - 90% CDs

N

Subtask 6d

Stormwater Design N

Permitting Services

Subtask 5: 100% CDs 15 DEP approval of Subtask 4a & 4b deliverables Subtask 6a: Bidding Services Bid Question Response 7 Written receipt of question Subtask 6b: Resource Permit 30 DEP approval of Subtask 5 deliverables Subtask 6c: Permitting Services 10 Delivery of Signed & Sealed Docs. 7 Permit Comment Response 10 Subtask 7a: Limited CA Services Review of shop drawings 10 Electronic receipt of shop drawings RFI response 10 Electronic/written receipt of question Delivery of dwg CAD files 25 Substantial Review site visit Subtask 7b: Pre-Con Meeting 5 From date of meeting Subtasks 7c – 7m (site visits) 5 From date of visit Subtask 7n: Review Sprinkler Shops 10 From receipt of shop drawing

All other Provisions, Terms, and Conditions as listed in the original contract would still apply.

Sincerely, Joel L. Dodson, AIA Principal Architect Dodstone Architects, Inc.