This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN212, Task Assignment No. 22. The contract involves Dodstone Architects, represented by Joel Dodson, serving as the consultant, with Ralph Perkins as the FDEP Contract Manager. The project is located at Wakulla Springs State Park and concerns Lodge Elevator Modifications.
The change order is a no-cost time extension only, with no modifications to the contract amount. The original task execution date was August 22, 2022, with an original end date of August 30, 2024. The extension adds 185 days, establishing a new task end date of March 3, 2025, to allow sufficient time for re-permitting and construction activities. The total task amount remains $138,025.52, comprised of a fixed fee of $138,025.52 with no reimbursable expenses. All required approvals were obtained and digitally signed between August 21-23, 2024, including signatures from the Budget Representative, Project Manager, Contract Manager, Consultant, and Contract Authority.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN212 22 2 6A011C
Wakulla Springs State Park Lodge Elevator Modifications
Dodstone Architects
Joel Dodson 850-656-7326 jdodson@dodstone.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
This is a time extension only. Please see attached request dated August 20, 2024.
$ 0.00 $ 128,656.02 $ 128,656.02 $ 0.00 $ 138,025.52 $ 138,025.52
$ 0.00 $ 0.00 $ 138,025.52 $ 138,025.52
8/22/22
8/30/24
8/30/24
03/03/25
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.08.21 11:04:10 -04'00'
Donald Finkbeiner Donald J. Finkbeiner Digitally signed by Donald J.
Finkbeiner Date: 2024.08.21 14:55:18 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.08.21 14:58:49 -04'00'
Joel Dodson Joel L Dodson Digitally signed by Joel L Dodson Date: 2024.08.22 12:48:28 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.08.23 13:16:57 -04'00'
$ 0.00
From: Karin Zawrotny To: Finkbeiner, Donald Subject: Wakulla Elevator time extension Date: Tuesday, August 20, 2024 1:05:43 PM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Don, We request a 'No-Cost' time extension for the CN212 TA22 Wakulla Springs - Lodge Elevator Modifications to allow sufficient time for re-permitting and construction. We recommend extending the contract to 3/3/2025.
Karin Zawrotny, AIA
LEED AP BD+C
Dodstone Architects
#AR0015211
3011-1 Powell Road Tallahassee, FL 32308 P: 850.656.7326 www.dodstone.com
Follow us on:
Facebook | Instagram mailto:kzawrotny@dodstone.com mailto:Donald.Finkbeiner@FloridaDEP.gov https://secure-web.cisco.com/1QcaTcA2BVzEtUV7ztxB4FV-MAex1XcBGXZP4JU6N7hIggzOOkhJq1SH9bfPd9YG3skJEZ8KAKLcVqRj1_IFUIMgHbJnvfNe76YMLONxQ8fIjHaVJMSQW3cjjTQknbLPNg9TEhsPYGD1h0M6nZYD5QKoyhKqAB643aHCHxLcNDAAEEbjMmwW3vGiyjogyCgSa5vd0gihTKyTSdrCh43faPZo5qSCjuXYqUIHit_6w3JZ_mgn-SNe9XkXYe2Ky8xs52tkWzUG0CcxxkNf36LsRnhbV4ob0K8NPgbEme2-MIiQVl6ozQu6D0uxKazJ-Ih25GhXeHD-zwq52DctI3uf6MA/https%3A%2F%2Fg.page%2FDodstoneArchitects%3Fshare https://secure-web.cisco.com/1QcaTcA2BVzEtUV7ztxB4FV-MAex1XcBGXZP4JU6N7hIggzOOkhJq1SH9bfPd9YG3skJEZ8KAKLcVqRj1_IFUIMgHbJnvfNe76YMLONxQ8fIjHaVJMSQW3cjjTQknbLPNg9TEhsPYGD1h0M6nZYD5QKoyhKqAB643aHCHxLcNDAAEEbjMmwW3vGiyjogyCgSa5vd0gihTKyTSdrCh43faPZo5qSCjuXYqUIHit_6w3JZ_mgn-SNe9XkXYe2Ky8xs52tkWzUG0CcxxkNf36LsRnhbV4ob0K8NPgbEme2-MIiQVl6ozQu6D0uxKazJ-Ih25GhXeHD-zwq52DctI3uf6MA/https%3A%2F%2Fg.page%2FDodstoneArchitects%3Fshare http://www.dodstone.com/ https://secure-web.cisco.com/1PbDzlYxakrT8RHnTkB6DqFt5BqzKRGvKppBcv-p8rpQN5R-I3DAkctkV2Of1Wd0OlDrfYKWB_7BACmBWUgYCz1hUKa_5SfcV-EGWr0kJyuDjsHW_M7ib6MtCAu2KW1q4POP4nwKb0yO0_4vN0kOf0NJ4ZLzHsR6PSQqDWOYkIgXzNA0AJlIHQYmYBFNxiHlJyykmj6Ca1T64tAMxtYetoCbWxXHFF-XJEDDHCf8B_f0TOq0Zy6BPTaxivHrXRPqHV5fqE-rqpILxdgDmadQyeBxuXGnASN1MscTtYv40Adfy886E8sneO-G9nUtCWcQsD_qiNvYv-TpWTgDc6-bCZg/https%3A%2F%2Fwww.facebook.com%2FDodstoneArchitects%2F https://secure-web.cisco.com/1kPZYJHnd36l6I8-qYB7AiaDyh9QLjn3n3z2ihoJeGyTNy9ELUEakH0zbgeA0cwLO0yuyt6rCXif_1qkwhyZaYP2Kqe90spwtUm9UhzQu9uYiI2aSKG4lZIZJ021RhC4ynrYBEqAUwrTrQl1i2uuT-ivN4N-5AVFW_85vkqCs1E2Ch9uUC-Q0D-a4cSGsZUVOslTaFkz2_8fIsp2TMgh5H6rF85OPqPPuRxnP5h0aadSLSB9j3vBaausKrziwyFEOH3CjgkwSW5Q7XRVWzLxfqIV0ydPX6pPu6cPE-ErIqQV-hXUQgUw5opqaL9l2SBu10dSnBBKHj4SOyWtDvTxXTA/https%3A%2F%2Fwww.instagram.com%2Fdodstone%2F
| 6A011C CN212 TA22 CO2 082024 - Alternate time.pdf |
| Wakulla Elevator time extension.pdf |
File details come from the government source that posted it. Updated .