CN-370000-CN212-T15CO3.pdf
PDF 1 MB Posted
- Contract number
- CN212
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a project involving Dodstone Architects, the consulting firm responsible for the O'Leno State Park Middle Campground Bathhouse Replacement/Renovation project. The change order was processed on April 3, 2024, and involves FDEP Contract No. CN212, Task Assignment No. 15, and Change Order No. CO3 for Project No. 61281 located at O'Leno State Park. The consultant representative is Joel Dodson of Dodstone Architects, and the FDEP Contract Manager is Ralph Perkins.
The change order represents a no-cost time extension of 150 days with no modification to the contract amount. The original task end date of June 30, 2022, was previously extended to April 26, 2024, and this change order extends it further to September 22, 2024. The total task amount remains unchanged at $62,646.15, comprised of a $122.50 reimbursement item and a $62,523.65 fixed fee. The original task execution date was August 31, 2021. The change order was approved by authorized FDEP representatives including Budget Representative Tamika Bass, Project Manager Uyles W. Keen Jr., Contract Manager Ralph Perkins, and Contract Authority Michael W. Foster Jr., P.E., as well as consultant Joel Dodson.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN212 15 CO3 61281
O'Leno State Park Middle Campground Bathhouse Replacement/Renovati
Dodstone Architects
Joel Dodson 850-656-7326 jdodson@dodstone.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Based upon where the project stands now, we are requesting a 150 day, no cost time extension.
$ 122.50 $ 62,523.65 $ 62,646.15 $ 122.50 $ 62,523.65 $ 62,646.15 $ 0.00 $ 0.00 $ 0.00
$ 122.50 $ 62,523.65 $ 62,646.15
08/31/2021
6/30/2022
04/26/2024
09/22/2024
Tamika Bass
Uyles W.Keen Jr.
Ralph Perkins
Joel Dodson
Michael W. Foster Jr., P.E.
$ 0.00
From: Karin Zawrotny To: Keen, Uyles (JR) Subject: O"Leno - time extension request Date: Friday, March 22, 2024 8:06:59 AM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
JR,
Our contract for O'Leno expires at the end of the next month. Based upon where the project stands now, we are requesting a 150 day, no cost time extension.
Karin Zawrotny, AIA
LEED AP BD+C
Dodstone Architects
#AR0015211
3011-1 Powell Road Tallahassee, FL 32308 P: 850.656.7326 www.dodstone.com