Contract Summary

This is a Task Assignment Change Order Form (Change Order 01) issued by the Florida Department of Environmental Protection (FDEP) for design and permitting services related to the Topsail Hill Preserve State Park Visitor and Exhibit Center project. The contract involves the primary consultant Dodstone Architects and multiple subconsultants including S. Stinson & Associates, Inc., FELSI, Southern Earth Sciences, McGinniss & Fleming, Bliss & Niytray, George & Associates, and HealyKohler Design. The contract is executed under FDEP Contract No. CN 212, Task Assignment No. 24, and pertains to work at Topsail Hill State Park in Santa Rosa Beach, Florida, with a project completion date of November 10, 2024.

Change Order 01 adds $264,459.81 to the original contract amount of $27,195.28, bringing the total project cost to $291,655.09. The work encompasses nine major phases including site and utility surveys, wetland delineation and environmental surveys, geotechnical investigation and asbestos testing, 60%, 90%, and 100% construction document preparation, FDEP and Walton County permitting coordination, exhibit concept programming and design development, and exhibit construction documentation with digital artwork. Compensation is structured as fixed fees with reimbursable expenses for permits and printing costs totaling $2,950.00. Deliverables include technical reports, construction drawings, permit applications, and exhibit design packages. The schedule spans from contract execution through multiple design phases, with task durations ranging from 5 to 60 working days depending on phase dependencies and agency approvals.

View the file

Other files

File Type Posted
CN-370000-CN212-T15CO1.pdf PDF
CN-370000-CN212-T15CO2.pdf PDF
CN-370000-CN212-T18CO4.pdf PDF
CN-370000-CN212-T1CO2.pdf PDF
CN-370000-CN212-T22CO1.pdf PDF
CN-370000-CN212-T23CO4.pdf PDF
CN-370000-CN212-T24CO3.pdf PDF
CN-370000-CN212-T25.pdf PDF
CN-370000-CN212-T4.pdf PDF
CN-370000-CN212-T8.pdf PDF
CN-370000-CN212-T8CO3.pdf PDF
CN-370000-CN212-AM1.pdf PDF
CN-370000-CN212-CMC3.pdf PDF
CN-370000-CN212-T11CO1.pdf PDF
CN-370000-CN212-T11CO2.pdf PDF
CN-370000-CN212-T12.pdf PDF
CN-370000-CN212-T13.pdf PDF
CN-370000-CN212-T14CO1.pdf PDF
CN-370000-CN212-T16.pdf PDF
CN-370000-CN212-T18CO2.pdf PDF
CN-370000-CN212-T18CO3.pdf PDF
CN-370000-CN212-T19CO1.pdf PDF
CN-370000-CN212-T21.pdf PDF
CN-370000-CN212-T22.pdf PDF
CN-370000-CN212-T23CO3.pdf PDF
CN-370000-CN212-T5.pdf PDF
CN-370000-CN212-T7.pdf PDF
CN-370000-CN212-T7CO1.pdf PDF
CN-370000-CN212-TA15.pdf PDF
CN-370000-CN212-TA3.pdf PDF
CN-370000-CN212-TA8 CO4.pdf PDF
CN-370000-CN212-CMC1.pdf PDF
CN-370000-CN212-CMC2.pdf PDF
CN-370000-CN212-T10.pdf PDF
CN-370000-CN212-T11.pdf PDF
CN-370000-CN212-T15CO3.pdf PDF
CN-370000-CN212-T17.pdf PDF
CN-370000-CN212-T18.pdf PDF
CN-370000-CN212-T18CO1.pdf PDF
CN-370000-CN212-T23CO2.pdf PDF
CN-370000-CN212-T8CO2.pdf PDF
CN-370000-CN212-T9.pdf PDF
CN-370000-CN212-T9CO1.pdf PDF
CN-370000-CN212-TA05C01.pdf PDF
CN-370000-CN212-TA1.pdf PDF
CN-370000-CN212-TA14.pdf PDF
CN-370000-CN212.pdf PDF
PC-370000-CN212.pdf PDF
CN-370000-CN212-T11CO3.pdf PDF
CN-370000-CN212-T14CO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN 212 24 CO1 61434C

Topsail Hill State Park Visitor and Exhibit Center

Dodstone

Karin Zawrotny 850.656.7326 kzawrotny@dodstone.com

Ralph Perkins or successor 850-245-2460 ralph.perkins@floridadep.gov

The project consist of Phase II - Design and Permitting for visitor center and exhibits. See proposal dated 2.15.23

$ 0.00 $ 27,195.28 $ 27,195.28 $ 0.00 $ 27,195.28 $ 27,195.28

$ 2,950.00 $ 261,509.8 $ 264,459.8 $ 2,950.00 $ 288,705. $ 291,655.

11.10.2021

11/10/2024

11/10/24

0.00

11/10/2024

Tamika Bass

Garland Sandel

Ralph Perkins

Jody Dodson

Bryan Bradner

Tamika Bass Digitally signed by Tamika Bass Date: 2023.03.21 08:47:05 -04'00'

61434C 37501000250 080039/23 000286 U3100 131500 AD $264,459.81

$264,459.81

Garland Sandel Digitally signed by Garland Sandel Date: 2023.03.21 10:36:00 -04'00'

Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.03.21 13:12:12 -04'00'

Jodie Dodson Digitally signed by Jodie Dodson Date: 2023.03.21 14:43:05 -04'00'

Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.04.11 10:20:43 -04'00'

Dodstone Architects | 3011-1 Powell Road | Tallahassee, FL 32308 | 850.656.7326 | #AR0015211

PO

Subtask 2a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Registered Architect $133.00 2.5 $332.50 Clerical $48.41 2 $96.82

$429.32

2 Person Survey Crew $125.00 12 $1,500.00 GPS Servey Crew $150.00 2 $300.00 Principal Surveyor $130.00 4 $520.00 Cadd Operator $80.00 12 $960.00

$3,280.00

Subtask 2a $3,709.32

Site & Utility Survey

Site & Utility Survey

Firm Name

Dodstone Architects

S.Stinson & Associates, Inc.

Subtask 2b

Position Classification Hourly Rate Hours Total Fixed Price Cost

Registered Architect $133.00 2.5 $332.50 Clerical $48.41 2 $96.82

$429.32

Principal Consultant $109.83 19.25 $2,114.22 Staff Assistant $60.00 11.25 $675.00

$2,789.22

Subtask 2b $3,218.54

Wetland Delineation & Environmental Survey

Wetland Delineation & Environmental Survey

Firm Name

Dodstone Architects

FELSI

Subtask 2c

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 5 $665.00 Clerical $48.41 2 $96.82

$845.82

Principal Engineer $127.00 12 $1,524.00 Project Engineer $115.00 12 $1,380.00 Staff Engineer $86.00 18 $1,548.00 Senior Engineering Technician

$60.00 8 $480.00

Engineering Technician $45.00 8 $360.00 Secretary $45.00 4 $180.00 Asbestos Consultant $127.00 12 $1,524.00

$6,996.00

Subtask 2c $7,841.82

Geotechnical Investigation, Lead & Asbestos Testing

Geotechnical Investigation, Lead & Asbestos Testing

Firm Name

Southern Earth Sciences

Subtask 3a 60% Construction Documents

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 3 $504.00 Registered Architect $133.00 60 $7,980.00 Graduate Architect $88.00 52 $4,576.00 CADD Operator $60.00 35 $2,100.00

$15,160.00

Principle/PE $125.74 67 $8,424.58 Engineer II $90.35 22 $1,987.70

$10,412.28

Principal $178.77 8 $1,430.16 Engineer $83.43 40 $3,337.20 CADD Operator $93.86 40 $3,754.40

$8,521.76

Chief Engineer $203.43 2 $406.86 Project Manager $129.00 46 $5,934.00 Project Engineer II $76.44 122 $9,325.68 Senior Engineer Technician $72.00 84 $6,048.00

$21,714.54

Subtask 3a 60% Construction Documents $55,808.58

Firm Name

Dodstone Architects

McGinniss & Fleming

Bliss & Niytray

George & Associates

Subtask 3b

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 1 $168.00 Registered Architect $133.00 4 $532.00 Graduate Architect $88.00 8 $704.00 CADD Operator $60.00 2 $120.00

$1,524.00

Principle/PE $125.74 4 $502.96 Engineer II $90.35 4 $361.40

$864.36

Principal $178.77 2 $357.54 Engineer $83.43 $0.00

$357.54

Chief Engineer $203.43 1 $203.43 Project Engineer II $76.44 4 $305.76

$509.19

Subtask 3b $3,255.0960% Construction Cost Projection

Dodstone Architects

McGinniss & Fleming

Bliss & Niytray

George & Associates

60% Construction Cost Projection

Firm Name

Subtask 3c

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 3 $399.00

$483.00

Project Manager $129.00 2 $258.00 $258.00

Subtask 3c $741.00

George & Associates

Response to Comments from 60% Submission

Firm Name

Dodstone Architects

Response to Comments from 60% Submission

Subtask 4

Position Classification Hourly Rate Hours Total Fixed Price Cost

Registered Architect $133.00 2.5 $332.50 Clerical $48.41 2 $96.82

$429.32

Project Manager $129.00 16 $2,064.00 Project Engineer II $76.44 36 $2,751.84 Senior Engineer Technician

$72.00 2 $144.00

$4,959.84

Subtask 4 $5,389.16

Dodstone Architects

FDEP Permitting

Firm Name

George & Associates

FDEP Permitting

Reimbursable Total $350.00

Subtask 5a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 3 $504.00 Registered Architect $133.00 60 $7,980.00 Graduate Architect $88.00 48 $4,224.00 CADD Operator $60.00 35 $2,100.00

$14,808.00

Principle/PE $125.74 52 $6,538.48 Engineer II $90.35 16 $1,445.60

$7,984.08

Principal $178.77 8 $1,430.16 Engineer $83.43 40 $3,337.20 CADD Operator $93.86 24 $2,252.64

$7,020.00

$406.86 $5,160.00 $6,268.08 $4,464.00

$16,298.94

Subtask 5a $46,111.02

George & Associates

90% Construction Documents

Firm Name

Bliss & Niytray

McGinniss & Fleming

90% Construction Documents

Subtask 5b

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 1 $168.00 Registered Architect $133.00 3 $399.00 Graduate Architect $88.00 4 $352.00 CADD Operator $60.00 2 $120.00

$1,039.00

Principle/PE $125.74 2 $251.48 Engineer II $90.35 2 $180.70

$432.18

Principal $178.77 2 $357.54 Engineer $83.43 $0.00

$357.54

Chief Engineer $203.43 1 $203.43 Project Engineer II $76.44 4 $305.76

$509.19

Subtask 5b $2,337.91Updated Construction Cost Projection

Updated Construction Cost Projection

Firm Name

Dodstone Architects

McGinniss & Fleming

Subtask 6

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 2 $336.00 Registered Architect $133.00 8 $1,064.00 Graduate Architect $88.00 6 $528.00 CADD Operator $60.00 4 $240.00

$2,168.00

Principle/PE $125.74 12 $1,508.88 Engineer II $90.35 4 $361.40

$1,870.28

Principal $178.77 1 $178.77 Engineer $83.43 4 $333.72 CADD Operator $93.86 8 $750.88

$1,263.37

Chief Engineer $203.43 3 $610.29 Project Manager $129.00 18 $2,322.00 Project Engineer II $76.44 27 $2,063.88 Senior Engineer Technician

$72.00 18 $1,296.00 $6,292.17

Subtask 6 $11,593.82

100% Construction Documents

Firm Name

Dodstone Architects

McGinniss & Fleming

Bliss & Niytray

100% Construction Documents

Subtask 7a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 3.5 $588.00 Registered Architect $133.00 22 $2,926.00 Graduate Architect $88.00 14 $1,232.00 CADD Operator $60.00 12 $720.00

$5,466.00

Principle/PE $125.74 37 $4,652.38 Engineer II $90.35 8 $722.80

$5,375.18

Principal $178.77 2 $357.54 Engineer $83.43 14 $1,168.02

$1,525.56

Chief Engineer $203.43 1 $203.43 Project Manager $129.00 34 $4,386.00 Project Engineer II $76.44 76 $5,809.44 Senior Engineer Technician

$72.00 10 $720.00

$11,118.87

Subtask 7a $23,485.61

Walton County Permitting

Bliss & Niytray

McGinniss & Fleming

Dodstone Architects

George & Associates

Firm Name

Walton County Permitting

$200.00 Printing Costs NTE $1,200.00 Reimbursable Total $1,400.00

Reimbursable Cost:

Walton County Minor Development Order

Subtask 9a

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 28 $3,724.00 Clerical $48.41 2 $96.82

$3,904.82

Design Principal $115.00 8 $920.00 Project Manager $91.00 24 $2,184.00 Content Developer $75.00 32 $2,400.00 Exhibit Designer $94.00 32 $3,008.00 Graphic Designer $78.00 16 $1,248.00

$9,760.00

Subtask 9a $13,664.82

Exhibit Concept/Programming 50%

Firm Name

Dodstone Architects

HealyKohler Design

Exhibit Concept/Programming 50%

Subtask 9b

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 16 $2,128.00 Clerical $48.41 2 $96.82

$2,308.82

Design Principal $115.00 4 $460.00 Project Manager $91.00 24 $2,184.00 Content Developer $75.00 24 $1,800.00 Exhibit Designer $94.00 52 $4,888.00 Graphic Designer $78.00 20 $1,560.00

$10,892.00

Subtask 9b $13,200.82

Firm Name

Dodstone Architects

HealyKohler Design

Exhibit Concept/Programming 100%

Exhibit Concept/Programming 100%

Subtask 9c

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 16 $2,128.00 Clerical $48.41 2 $96.82

$2,308.82

Design Principal $115.00 8 $920.00 Project Manager $91.00 24 $2,184.00 Content Developer $75.00 48 $3,600.00 Exhibit Designer $94.00 46 $4,324.00 Graphic Designer $78.00 36 $2,808.00

$13,836.00

Subtask 9c $16,144.82

Exhibit Design Development 50%

Firm Name

Dodstone Architects

Exhibit Design Development 50%

Subtask 9d

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 17 $2,261.00 Graduate Architect $88.00 5 $440.00 Clerical $48.41 2 $96.82

$2,881.82

Design Principal $115.00 4 $460.00 Project Manager $91.00 24 $2,184.00 Content Developer $75.00 48 $3,600.00 Exhibit Designer $94.00 46 $4,324.00 Graphic Designer $78.00 36 $2,808.00

$13,376.00

Principal Mech PE $125.74 0.5 $62.87 Principal Elec PE $125.74 3 $377.22 Engineer II $90.35 3 $271.05

$711.14

Principal $178.77 0.5 $89.38 Engineer $83.43 2 $166.86 CADD Operator $93.86 2 $187.72

$443.96

Subtask 9d Exhibit Design Development 100% $17,412.92

Exhibit Design Development 100%

Firm Name

Dodstone Architects

HealyKohler Design

McGinniss & Fleming

Subtask 9e

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 16 $2,128.00 Graduate Architect $88.00 8 $704.00 Clerical $48.41 2 $96.82

$3,012.82

Design Principal $115.00 8 $920.00 Project Manager $91.00 12 $1,092.00 Content Developer $75.00 22 $1,650.00 Exhibit Designer $94.00 46 $4,324.00 Graphic Designer $78.00 24 $1,872.00

$9,858.00

Subtask 9e $12,870.82

Exhibit CDs 50%

Firm Name

Dodstone Architects

Exhibit CDs 50%

Subtask 9f

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 17 $2,261.00 Graduate Architect $88.00 5 $440.00 Clerical $48.41 2 $96.82

$2,881.82

Design Principal $115.00 4 $460.00 Project Manager $91.00 12 $1,092.00 Content Developer $75.00 22 $1,650.00 Exhibit Designer $94.00 44 $4,136.00 Graphic Designer $78.00 22 $1,716.00

$9,054.00

Principal Mech PE $125.74 0.5 $62.87 Principal Elec PE $125.74 3 $377.22 Engineer II $90.35 3 $271.05

$711.14

Principal $178.77 0.5 $89.38 Engineer $83.43 2 $166.86 CADD Operator $93.86 2 $187.72

$443.96

Subtask 9f $13,090.92

Firm Name

Dodstone Architects

HealyKohler Design

McGinniss & Fleming

Bliss & Niytray

Exhibit CDs 100%

Exhibit CDs 100%

Subtask 9g

Position Classification Hourly Rate Hours Total Fixed Price Cost

Principal $168.00 0.5 $84.00 Registered Architect $133.00 8 $1,064.00 Clerical $48.41 2 $96.82

$1,244.82

Design Principal $115.00 0 $0.00 Project Manager $91.00 8 $728.00 Content Developer $75.00 4 $300.00 Exhibit Designer $94.00 0 $0.00 Graphic Designer $78.00 120 $9,360.00

$10,388.00

Subtask 9g $11,632.82

HealyKohler Design

Digital Artwork

Digital Artwork

Firm Name

Summary Provider Base Service Additional

Service Subtotal Reimb. Total Subtask 2a DS $429.32 $3,709.32 $3,709.32

SSA $3,280.00

Subtask 2b DS $429.32 $3,218.54 $3,218.54

FELSI $2,789.22

Subtask 2c DS $845.82 $7,841.82 $7,841.82

SES $6,996.00

Subtask 3a DS $15,160.00 $55,808.58 $55,808.58 M&F $10,412.28

BNI $8,521.76

G&A $21,714.54

Subtask 3b DS $1,524.00 $3,255.09 $3,255.09 M&F $864.36

BNI $357.54

G&A $509.19

Subtask 3c DS $483.00 $741.00 $741.00 G&A $258.00

Subtask 4 DS $429.32 $5,389.16 350.00 $5,739.16 G&A $4,959.84

Subtask 5a DS $14,808.00 $46,111.02 $46,111.02 M&F $7,984.08

BNI $7,020.00

G&A $16,298.94

Subtask 5b DS $1,039.00 $2,337.91 $2,337.91 M&F $432.18

BNI $357.54

G&A $509.19

Subtask 6 DS $2,168.00 $11,593.82 $11,593.82 M&F $1,870.28

BNI $1,263.37

G&A $6,292.17

Subtask 7a DS $5,466.00 $23,485.61 1,400.00 $24,885.61 G&A $11,118.87 M&F $5,375.18

BNI $1,525.56

100% Construction Documents

CHANGE ORDER 1

60% Construction Documents

60% Construction Cost Projection

Response to Comments from 60%

Geotechnical Investigation, Lead &

Site & Utility Survey

Wetland Delineation & Environmental Survey

FDEP Permitting

Walton County Permitting

90% Construction Documents

Updated Construction Cost Projection

Subtask 9a DS $3,904.82 $13,664.82 1,200.00 $14,864.82

HK $9,760.00

Subtask 9b DS $2,308.82 $13,200.82 $13,200.82

HK $10,892.00

Subtask 9c DS $2,308.82 $16,144.82 $16,144.82

HK $13,836.00

Subtask 9d DS $2,881.82 $17,412.92 $17,412.92

HK $13,376.00

M&F $711.14

BNI $443.96

Subtask 9e DS $3,012.82 $12,870.82 $12,870.82

HK $9,858.00

Subtask 9f DS $2,881.82 $13,090.92 $13,090.92

HK $9,054.00

M&F $711.14

BNI $443.96

Subtask 9g DS $1,244.82 $11,632.82 $11,632.82

HK $10,388.00

Exhibit Concept/Programming 100%

Exhibit Concept/Programming 50%

Exhibit Design Development 50%

Exhibit Design Development 100%

Exhibit CDs 50%

Exhibit CDs 100%

Digital Artwork

(2a,2b,2c,3a,3b,3c,5 a,5b,5c,7) $69,690.77 $64,926.33 $134,617.10 $0.00 $134,617.10

(10a - 10g) $0.00 $98,017.94 $98,017.94 $1,200.00 $99,217.94

$69,690.77 $162,944.27 $232,635.04 $1,200.00 $233,835.04

(4,7a) $12,366.74 $16,508.03 $28,874.77 $1,750.00 $30,624.77 $82,057.51 $179,452.30 $261,509.81 $2,950.00 $264,459.81

Design Phases:

Building Design Phases:

Exhibits Design Phases:

Total Bidding & Permitting Change Order 1 Total

Summary Base Service Additional

Service Subtotal Reimb. Total Original Contract Sums $ $18, . $27,195.2 $0.00 $27,195.2

CO1 $82,057.51 $179,452.30 $261,509.81 $2,950.00 $264,459.81

Project Total $90, $197, . $288,705. $2,950.00 $291,655.

DD through Bidding Phases Working Days

Subtask 2a Site & Utility Survey 50 From Contract execution Subtask 2b Environmental Survey 50 From Contract execution Subtask 2c g , Asbestos Testing 50 From Contract execution

Subtask 3a 60% Construction Documents 60 From Contract execution Subtask 3b 60% Construction Cost Projection 5 From completion of 3a Subtask 3c

Response to Comments from 60% Submission 5 From Receipt of Comments

Subtask 4 FDEP Permitting 30 From completion of 3a

Subtask 5a 90% Construction Documents 45 From AHJ review of 4 Subtask 5b Updated Construction Cost Projection 5 From completion of 5a

Subtask 6 100% Construction Documents 10 From approval by WC & SFM

Subtask 7a Walton County Permitting 30 From completion of 5a

Subtask 9a Exhibit Concept/Programming 50% 22 From Execution of Contract Subtask 9b Exhibit Concept/Programming 100% 22 From approval of 10a Subtask 9c Exhibit Design Development 50% 22 From approval of 10b Subtask 9d Exhibit Design Development 100% 22 From approval of 10c Subtask 9e Exhibit CDs 50% 16 From approval of 10d Subtask 9f Exhibit CDs 100% 16 From approval of 10e Subtask 9g Digital Artwork 56 From approval of 10f

Change Order 01

File details come from the government source that posted it. Updated .