This transmittal form and instructions provide guidance for contractors to submit shop drawings, equipment data, material samples, or certificates of compliance for U.S. Army Corps of Engineers projects. Contractors must use this form to transmit required submittal items from the specifications, listing the item number, submittal type, number of copies, specification and drawing references, and requesting approval or noting variations. The form also provides action codes for the contractor and approving authority to note approval, requests for resubmission, acknowledgement of receipt, or disapproval. Instructions explain how to complete the form, numbering conventions for resubmittals, limitations on items per transmittal, and definitions of the submittal types and action codes.

The solicitation seeks proposals for a protective coatings contract at Joint Base Lewis-McChord in Washington to provide all labor, materials, equipment and management to complete maintenance, repair and minor construction tasks through task orders. The Army Materiel Command Mission and Installation Contracting Command at JBLM will issue task orders for a range of protective coatings applications and incidental related work. Offerors should be prepared to furnish all resources needed to accomplish task order requirements.

View the file

Other files

File Type Posted
Amendment W911S820B0002-0004.pdf PDF
Enclosure 1 - Government Responses v1 28April2020.pdf PDF
Attachment 4 - General Decision Number WA20200018 06MAR2020_Thurston.pdf PDF
Attachment 9 - Tech Spec 04 01 40 - Historic Structures.pdf PDF
Evaluation Factors for Award_20April2020.pdf PDF
Attachment 1 - Statement of Work_22April2020.pdf PDF
EXHIBITS AND ATTACHMENTS_22April2020.pdf PDF
Attachment 11 - Technical Specification 09 90 00 - Paint and Coatings.pdf PDF
Attachment 6 - General Decision Number WA20200029 13MAR2020_Jefferson.pdf PDF
Instuctions to Bidders_20April2020.pdf PDF
Attachment 10 - Technical Specification 09 67 23.13 - Standard Resinous Flooring.pdf PDF
Attachment 8 - Technical Specification 02 83 00 - Lead Remediation.pdf PDF
Attachment 3 - General Decision Number WA20200013 06MAR2020_Pierce.pdf PDF
Enclosure 1 - Government Responses.pdf PDF
Attachment 5 - General Decision Number WA20200020 13MAR2020_Yakima.pdf PDF
Attachment 7 - Technical Specification 02 82 14.00 10 - Asbestos Hazard Control Activities.pdf PDF
Amendment W911S820B0002-0003.pdf PDF
Attachment 2 - Price List-Technical Exhibit 1_22April2020.xlsx XLSX spreadsheet
Amendment W911S820B0002-0002.pdf PDF
Amendment W911S820B0002-0001.pdf PDF
Appendix H - Task Order SOW.docx DOCX document
Appendix I - Proposal Tech Review.xlsx XLSX spreadsheet
Appendix J - HJB-229 Construction And Demolition Disposal Transaction.pdf PDF
Appendix J - HJB 229 Instructions.pdf PDF
Attachment 3 - General Decision Number WA20190013 22NOV2019_Pierce.pdf PDF
Appendix F - Sustainable Acquisition Exception Form - HJB 225.pdf PDF
Appendix A - AF Form 3065 Invoice.xls XLS spreadsheet
Appendix E - Daily Contract Inspection Report.pdf PDF
Appendix B - Project Schedule Example.xlsx XLSX spreadsheet
Invitation for Bid_W911S8-20-B-0002.pdf PDF
Appendix G - Eng Form 4288 Submittal Register.xlsx XLSX spreadsheet
Appendix C - DA Form 5479 - CDR.pdf PDF
Attachment 1 - Statement of Work.pdf PDF
Attachment 2 - Price List-Technical Exhibit 1.xlsx XLSX spreadsheet
Attachment 4 - General Decision Number WA20190018 22NOV2019_Thurston.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

DATE TRANSMITTAL NO.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

TO:

PROJECT TITLE AND LOCATIONSPECIFICATION SEC. NO. (Cover only one section with each transmittal)

FROM: CONTRACT NO. CHECK ONE:

THIS TRANSMITTAL IS FOR: (Check one)

THIS IS A NEW TRANSMITTAL

THIS IS A RESUBMITTAL OF

TRANSMITTAL

FIO GA DA CR DA/CR DA/GA

ITEM

NO.

(See

Note 3)

USACE

ACTION

CODE

(Note 9)

SUBMITTAL

TYPE CODE

(See Note 8)

NO.

OF

COPIES

SPEC.

PARA. NO.

DRAWING

SHEET NO.

CONTRACTOR

REVIEW

CODE

VARIATION

Enter "Y" if requesting a variation

(See Note 6)

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.)

a. i.c. d. e. f. g. h.b.

CONTRACT DOCUMENT

REFERENCE

REMARKS

SECTION II - APPROVAL ACTION

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

NAME OF CONTRACTOR SIGNATURE OF CONTRACTOR

NAME AND TITLE OF APPROVING AUTHORITY SIGNATURE OF APPROVING AUTHORITY DATEENCLOSURES RETURNED (List by item No.)

REPLACES EDITION OF MAR 95, WHICH IS OBSOLETE.ENG FORM 4025-R, MAR 2012

INSTRUCTIONS

1. Section I will be initiated by the Contractor in the required number of copies.

2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.

4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.

5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.

7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.

8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following:

SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports

SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal

Action Codes in column i of Section I. The Submittal Action Codes are:

A -- Approved as submitted.

B -- Approved, except as noted on drawings. Resubmission not required.

C -- Approved, except as noted on drawings. Refer to attached comments.

Resubmission required.

D -- Will be returned by separate correspondence.

E -- Disapproved. Refer to attached comments.

10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

F -- Receipt acknowledged.

X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify)

K -- Government concurs with intermediate design. (For D-B contracts)

R -- Design submittal is acceptable for release for construction. (For D-B contracts)

ENG FORM 4025-R, MAR 2012

Page of

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

CHECK ONE:

THIS TRANSMITTAL IS FOR: (Check one)

ITEM

NO.

(See Note 3)

USACE

ACTION

CODE

(Note 9)

SUBMITTAL

TYPE CODE

(See Note 8)

NO.

OF

COPIES

SPEC.

PARA. NO.

DRAWING

SHEET NO.

CONTRACTOR

REVIEW

CODE

VARIATION

Enter "Y" if requesting a variation (See Note 6)

DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.)

a.

i.

c.

d.

e.

f.

g.

h.

b.

CONTRACT DOCUMENT

REFERENCE

SECTION II - APPROVAL ACTION

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

REPLACES EDITION OF MAR 95, WHICH IS OBSOLETE.

ENG FORM 4025-R, MAR 2012

INSTRUCTIONS

1. Section I will be initiated by the Contractor in the required number of copies.

2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.

4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.

5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.

7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.

8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following:

SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports

SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal Action Codes in column i of Section I. The Submittal Action Codes are:

A -- Approved as submitted. B -- Approved, except as noted on drawings. Resubmission not required. C -- Approved, except as noted on drawings. Refer to attached comments. Resubmission required. D -- Will be returned by separate correspondence. E -- Disapproved. Refer to attached comments.

10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

F -- Receipt acknowledged.

X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify) K -- Government concurs with intermediate design. (For D-B contracts) R -- Design submittal is acceptable for release for construction. (For D-B contracts)

ENG FORM 4025-R, MAR 2012

1.0 darwin.chen@usace.army.mil 2012-03-27 Forms Design Team Darwin Chen

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

2012-03-29

CurrentPage:
PageCount:
No1_DateTime:
No2_Transmittal:
No3_To:
No8_Pro_Title:
No7_Specification:
No4_From:
No5_Cont_No:
No6a_CheckBox: 0
No6b_CheckBox: 0
No6_Transmittal:
No9a_CheckBox: 0
No9b_CheckBox: 0
No9c_CheckBox: 0
No9d_CheckBox: 0
No9e_CheckBox: 0
No9f_CheckBox: 0
ITEM NO. (See Note 3):
DESCRIPTION OF SUBMITTAL ITEM

(Type size, model number/etc.):

SUBMITTAL TYPE CODE (See Note 8):
NO. OF COPIES:
SPEC. PARA. NO.:
DRAWING SHEET NO. :
CONTRACTOR REVIEW CODE
VARIATION Enter "Y" if requesting a variation (See Note 6):
USACE ACTION CODE (Note 9) :
Remarks:
Contractor_Name:
Contractor_Signature:
Authority_Name:
Authority_Signature:
Authority_DateTime:
Enclosures: