Appendix B - Project Schedule Example.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Protective Coatings
- Solicitation number
- W911S820B0002
About this file
This document contains an example project schedule template and details of a federal contract opportunity for protective coatings services. The project schedule template provides examples of work breakdown structures and duration estimates for preconstruction, major work items, and closeout activities. The federal contract opportunity posted by the Department of the Army Materiel Command Mission and Installation Contracting Command at Joint Base Lewis-McChord seeks to establish an indefinite delivery/indefinite quantity contract to provide all necessary plant, labor, tools, equipment and materials for a broad range of maintenance, repair and minor protective coatings construction work on real property and supported satellites. Individual task orders will be issued to the contractor to complete specific jobs varying in size and disciplines required for various protective coatings applications.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Example #1
| Example Project Schedule | ||
| Contract #: W911S8-20-D-XXX | Project Title: ______ | |
| Task Order #: _______________ |
| Days/Weeks | ||||||||||||||||||
| SOVs | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | |||
| CLIN XXXXAA: Preconstruction Activities | 12.00% | |||||||||||||||||
| Action 1 | 7.00% | |||||||||||||||||
| Action 2 | 5.00% | |||||||||||||||||
| CLIN XXXXAA: Major Location/Item of Work | 40.00% | |||||||||||||||||
| Action 1 | 15.00% | |||||||||||||||||
| Action 2 | 25.00% | |||||||||||||||||
| CLIN XXXXAB: Major Location/Item of Work | 35.00% | |||||||||||||||||
| Action 1 | 17.00% | |||||||||||||||||
| Action 2 | 15.00% | |||||||||||||||||
| Action 3 | 3.00% | |||||||||||||||||
| CLIN XXXXAB: Major Location/Item of Work | 8.00% | |||||||||||||||||
| Action 1 | 8.00% | |||||||||||||||||
| CLIN XXXXAB: Closeout | 5.00% | |||||||||||||||||
| Total: | 100.00% |
Example #2
| Project Schedule | Contract: W911S8-XX-D-00XX | ||||
| Project Number: XXXXX | |||||
| Project Title: Example | |||||
| CLIN | Work Activities | Start Date | Completion Date | Total Days | SOVs |
| CLIN AA | Preconstruction Activities | 9/1/19 | 9/15/19 | 14 | 12% |
| CLIN AA | Major Location/Item of Work | 9/16/19 | 10/25/19 | 39 | 30% |
| CLIN AB | Major Location/Item of Work | 10/26/19 | 11/5/19 | 10 | 35% |
| CLIN AB | Major Location/Item of Work | 11/6/19 | 12/1/19 | 25 | 18% |
| CLIN AB | Closeout | 12/2/19 | 12/16/19 | 14 | 5% |
| Total: | 100% |