This is a technical specification document for identification of process piping systems prepared by Herbert, Rowland & Grubic, Inc. for the Northwestern Chester County Municipal Authority's West Pump Station Replacement Project in Pennsylvania. The specification section 40 05 53 establishes requirements for pipe identification materials and installation methods, including stencils and plastic pipe markers that comply with ASME A13.1 standards. The scope covers factory-fabricated plastic pipe markers from manufacturers such as Seton Identification Products and Craftmark Pipe Markers, as well as stencil painting with semigloss enamel. Installation requirements mandate that piping identification be applied after completion of coverings and painting, with identification located no more than 20 feet apart on straight runs, adjacent to valves and tees, at structure penetrations, and at obstructions. Plastic markers must be installed with corrosion-resistant mechanical fasteners or adhesive, and underground markers must be placed 6 to 8 inches below finished grade directly above buried pipe. All materials must meet manufacturer specifications and be inspected upon delivery in original packaging, with storage in clean, dry locations protected from moisture and dust.

The specification requires manufacturer product data submissions, shop drawings indicating wording, symbols, letter sizes, and color-coding schemes, and manufacturer certificates verifying compliance with specified requirements. Contractors must convene a preinstallation meeting minimum one week prior to commencing work and submit maintenance materials including special crimpers and installation tools for owner use. Letter height requirements vary based on pipe outer diameter: 1/2-inch letters for pipes up to 2 inches OD, 1-inch letters for 2.5 to 6 inches OD, and 1.75-inch letters for pipes exceeding 6 inches OD. The specification mandates that manufacturers have a minimum of three years' documented experience in producing identification products, and all work must comply with Northwestern Chester County Municipal Authority standards and applicable reference standards outlined in related project sections.

View the file

Other files

File Type Posted
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
46 24 23 - Channel Sewage Grinders.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

40 05 53 – IDENTIFICATION FOR PROCESS PIPING

Herbert, Rowland & Grubic, Inc. 40 05 53 - 1 000483.0450

SECTION 40 05 53 – IDENTIFICATION FOR PROCESS PIPING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Stencils.

2. Pipe markers.

B. Related Requirements:

1. Section 09 91 00 – Painting and Coating: Requirements for painting as specified by this Section.

1.2 REFERENCE STANDARDS

A. ASME International:

1. ASME A13.1 - Scheme for the Identification of Piping Systems.

1.3 PREINSTALLATION MEETINGS

A. Section 01 31 19 – Project Meetings: Requirements for preinstallation meeting.

B. Convene minimum one week prior to commencing Work of this Section.

1.4 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Product Data: Submit manufacturer's catalog literature for each specified product.

C. Shop Drawings:

1. Indicate list of wording, symbols, letter size, and color-coding for mechanical identification and valve chart and schedule.

2. Indicate valve tag number, location, function, and valve manufacturer's name and model number.

D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.

E. Manufacturer Instructions: Submit detailed instructions on installation requirements, including storage and handling procedures.

F. Qualifications Statement:

1. Submit qualifications for manufacturer.

1.5 CLOSEOUT SUBMITTALS

A. Section 01 77 00 – Closeout Requirements: Requirements for submittals.

Herbert, Rowland & Grubic, Inc. 40 05 53 - 2 000483.0450

B. Project Record Documents: Record actual locations of tagged valves; include valve tag numbers.

1.6 MAINTENANCE MATERIAL SUBMITTALS

A. Section 01 78 13 – Operations and Maintenance Manual Requirements: Requirements for maintenance materials.

B. Tools: Furnish special crimpers and other devices required for Owner to reinstall tags.

1.7 QUALITY ASSURANCE

A. Piping Color Scheme and Lettering Size: Comply with ASME A13.1.

B. Perform Work according to Northwestern Chester County Municipal Authority standards.

1.8 QUALIFICATIONS

A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Section 01 61 00 – Product Requirements: Requirements for transporting, handling, storing, and protecting products.

B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.

C. Store materials according to manufacturer instructions.

D. Protection:

1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.

2. Provide additional protection according to manufacturer instructions.

PART 2 - PRODUCTS

2.1 STENCILS

A. Description:

1. Quality: Clean-cut symbols.

2. Letters:

a. Up to 2-Inch OD of Insulation or Pipe: 1/2-inch-high letters.

b. 2-1/2- to 6-Inch OD of Insulation or Pipe: 1-inch-high letters.

c. More Than 6-Inch OD of Insulation or Pipe: 1-3/4-inch high letters.

B. Stencil Paint:

1. Description: Semigloss enamel.

2. As specified in Section 09 91 00 – Painting and Coating.

Herbert, Rowland & Grubic, Inc. 40 05 53 - 3 000483.0450

2.2 PIPE MARKERS

A. Plastic Pipe Markers:

1. Manufacturers:

a. Seton Identification Products

b. Craftmark Pipe Markers

c. Substitutions: Section 01 61 00 – Product Requirements.

2. Description:

a. Factory-fabricated, flexible, and semi-rigid plastic.

b. Preformed to fit around pipe or pipe covering.

c. Larger sizes may be of maximum sheet size, with spring fastener.

B. Plastic Tape Pipe Markers:

1. Description: Flexible, vinyl film tape with pressure-sensitive adhesive backing and printed markings.

PART 3 - EXECUTION

3.1 PREPARATION

A. Section 01 73 00 – Execution Requirements: Requirements for installation preparation.

B. Degrease and clean surfaces to receive adhesive for identification materials.

C. Stencil Painting: Prepare surfaces as specified in Section 09 91 00 – Painting and Coating.

3.2 INSTALLATION

A. According to manufacturer instructions.

B. Apply stencil painting as specified in Section 09 91 00 – Painting and Coating.

C. Install identifying devices after completion of coverings and painting.

D. Install plastic nameplates with corrosion-resistant mechanical fasteners or adhesive.

E. Labels:

1. Install labels with sufficient adhesive for permanent adhesion and seal with clear lacquer.

2. For unfinished covering, apply paint primer before applying labels.

F. Install underground plastic pipe markers 6 to 8 inches below finished grade, directly above buried pipe.

G. Piping:

1. Identify piping, concealed or exposed, with plastic pipe markers, or stenciled painting.

2. Identify service, flow direction, and pressure.

3. Install in clear view and align with axis of piping.

Herbert, Rowland & Grubic, Inc. 40 05 53 - 4 000483.0450

4. Locate identification not to exceed 20 feet on straight runs, including risers and drops, adjacent to each valve and tee, at each side of penetration of structure or enclosure, and at each obstruction.

END OF SECTION 40 05 53