This is a specification section for project record documents required by Herbert, Rowland & Grubic, Inc. for construction work. The specification establishes requirements for maintaining comprehensive documentation throughout the project lifecycle, including one on-site set of record documents consisting of marked-up drawings, specifications, addenda, change orders, reviewed shop drawings, product data, samples, and manufacturer's instructions. Contractors must record actual revisions to the work concurrently with construction progress, at minimum weekly, maintaining entries that are complete and accurate for future owner reference. Record drawings must be marked with erasable red pencil to show actual installation conditions, with particular attention to concealed elements including dimensional changes, foundation depths, underground utility locations and depths, electrical circuitry revisions, equipment locations, and concealed utilities. New drawings must be prepared when existing contract or shop drawings cannot adequately depict actual installations, and all record drawings must be identified, dated, and stamped with the contractor's name.
The specification requires submission of a Manual for Materials and Finishes in two preliminary draft copies for engineer review before work commences, followed by one copy of completed volumes before substantial completion and two sets of revised final volumes within ten days after final inspection, with a PDF composite electronic indexed file due within ten days after final inspection. The manual must include product data with catalog numbers, sizes, composition, color and texture designations, manufacturer's care and maintenance recommendations, cleaning agents and methods, precautions against detrimental agents, and recommended maintenance schedules. Contractors must also assemble miscellaneous record submittals including material and equipment test and inspection reports and equipment and material delivery slips, organized and bound in a retrievable format with appropriate identification.
View the file
Other files
Show 40 more
Latest 50 of 171 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 78 39 – PROJECT RECORD DOCUMENTS
Herbert, Rowland & Grubic, Inc. 01 78 39 - 1 000483.0450
SECTION 01 78 39 – PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes
1. Project record documents.
2. Manual for Materials and Finishes
3. Miscellaneous Record Submittals
B. Related Sections
1. Section 01 77 00 – Closeout Procedures: general closeout procedures.
2. Individual Sections for specific requirements for Project Record Documents of the
Work in those Sections.
1.2 PROJECT RECORD DOCUMENTS
A. Maintain on Site one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Reviewed Shop Drawings, product data, and Samples.
6. Manufacturer's instruction for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress, not less than weekly.
E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:
1. Manufacturer's name and product model and number.
2. Suppliers name and contact.
3. Product substitutions or alternates used.
4. Changes made by Addenda and modifications.
F. Record Drawings: Maintain one set of the Contract Drawings and Shop Drawings.
1. Preparation: Mark Drawings to show the actual installation. Require individual or entity who obtained record data to prepare the marked-up Record Prints.
a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.
b. Accurately record information in an understandable drawing technique.
c. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.
Herbert, Rowland & Grubic, Inc. 01 78 39 - 2 000483.0450
2. Content: Types of items requiring marking include, but are not limited to, the following:
a. Dimensional changes to Drawings.
b. Revisions to details shown on Drawings.
c. Depths of foundations in relation to plant datum.
d. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
1) Depth of buried utility lines.
2) Dimension distances from permanent facility components that are parallel to utilities.
3) Dimension ends, corners, and junctions of buried utilities to permanent facility components using triangulation.
4) Identify and locate existing buried or concealed items encountered during Project.
e. Revisions to electrical circuitry.
f. Actual equipment locations.
g. Locations of concealed internal utilities.
h. Changes made by Addendum, Field Order, Change Order or Work Change
Directive.
i. Details not on the original Contract Drawings.
j. Field records for variable and concealed conditions.
k. Record information on the Work that is shown only schematically.
3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings.
4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.
5. Mark important additional information that was either shown schematically or omitted from original Drawings.
6. Note Addendum numbers, Field Order numbers, Work Change Directive numbers, Change Order numbers, and similar identification, where applicable.
7. Prepare new Drawings where neither the Contract Drawings nor Shop Drawings are not suitable to show actual installation.
a. New Drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.
8. Format: Identify and date each Record Drawing; include the designation
"PROJECT RECORD DRAWING" in a prominent location.
a. Cross out Engineer's title block and seal from all sheets and stamp all sheets with name of Contractor.
b. Record Drawings: Organize Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.
1.3 MANUAL FOR MATERIALS AND FINISHES
A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Engineer will review draft and return one copy with comments.
Herbert, Rowland & Grubic, Inc. 01 78 39 - 3 000483.0450
B. For equipment or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance.
C. Submit one copy of completed volumes before Substantial Completion. Draft copy be reviewed and returned after Substantial Completion, with Engineer comments. Revise content of document sets as required prior to final submission.
D. Submit two sets of revised final volumes within ten days after final inspection.
E. Submit in PDF composite electronic indexed file of final manual within ten days after final inspection.
F. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Include information for re-ordering custom-manufactured products.
G. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.
H. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair.
I. Additional Requirements: As specified in individual product Specification Sections.
J. Include listing in table of contents for design data, with tabbed fly sheet and space for insertion of data.
1.4 MISCELLANEOUS RECORD SUBMITTALS
A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:
1. Material and equipment test and inspection reports.
2. Equipment and material delivery slips.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION - Not Used
END OF SECTION 01 78 39