01 78 39 - Project Record Documents.pdf

PDF 478 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a specification section for project record documents required by Herbert, Rowland & Grubic, Inc. for construction work. The specification establishes requirements for maintaining comprehensive documentation throughout the project lifecycle, including one on-site set of record documents consisting of marked-up drawings, specifications, addenda, change orders, reviewed shop drawings, product data, samples, and manufacturer's instructions. Contractors must record actual revisions to the work concurrently with construction progress, at minimum weekly, maintaining entries that are complete and accurate for future owner reference. Record drawings must be marked with erasable red pencil to show actual installation conditions, with particular attention to concealed elements including dimensional changes, foundation depths, underground utility locations and depths, electrical circuitry revisions, equipment locations, and concealed utilities. New drawings must be prepared when existing contract or shop drawings cannot adequately depict actual installations, and all record drawings must be identified, dated, and stamped with the contractor's name.

The specification requires submission of a Manual for Materials and Finishes in two preliminary draft copies for engineer review before work commences, followed by one copy of completed volumes before substantial completion and two sets of revised final volumes within ten days after final inspection, with a PDF composite electronic indexed file due within ten days after final inspection. The manual must include product data with catalog numbers, sizes, composition, color and texture designations, manufacturer's care and maintenance recommendations, cleaning agents and methods, precautions against detrimental agents, and recommended maintenance schedules. Contractors must also assemble miscellaneous record submittals including material and equipment test and inspection reports and equipment and material delivery slips, organized and bound in a retrievable format with appropriate identification.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
46 24 23 - Channel Sewage Grinders.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 39 – PROJECT RECORD DOCUMENTS

Herbert, Rowland & Grubic, Inc. 01 78 39 - 1 000483.0450

SECTION 01 78 39 – PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Project record documents.

2. Manual for Materials and Finishes

3. Miscellaneous Record Submittals

B. Related Sections

1. Section 01 77 00 – Closeout Procedures: general closeout procedures.

2. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 PROJECT RECORD DOCUMENTS

A. Maintain on Site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, product data, and Samples.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

2. Suppliers name and contact.

3. Product substitutions or alternates used.

4. Changes made by Addenda and modifications.

F. Record Drawings: Maintain one set of the Contract Drawings and Shop Drawings.

1. Preparation: Mark Drawings to show the actual installation. Require individual or entity who obtained record data to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an understandable drawing technique.

c. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

Herbert, Rowland & Grubic, Inc. 01 78 39 - 2 000483.0450

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings.

b. Revisions to details shown on Drawings.

c. Depths of foundations in relation to plant datum.

d. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

1) Depth of buried utility lines.

2) Dimension distances from permanent facility components that are parallel to utilities.

3) Dimension ends, corners, and junctions of buried utilities to permanent facility components using triangulation.

4) Identify and locate existing buried or concealed items encountered during Project.

e. Revisions to electrical circuitry.

f. Actual equipment locations.

g. Locations of concealed internal utilities.

h. Changes made by Addendum, Field Order, Change Order or Work Change

Directive.

i. Details not on the original Contract Drawings.

j. Field records for variable and concealed conditions.

k. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Addendum numbers, Field Order numbers, Work Change Directive numbers, Change Order numbers, and similar identification, where applicable.

7. Prepare new Drawings where neither the Contract Drawings nor Shop Drawings are not suitable to show actual installation.

a. New Drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.

8. Format: Identify and date each Record Drawing; include the designation

"PROJECT RECORD DRAWING" in a prominent location.

a. Cross out Engineer's title block and seal from all sheets and stamp all sheets with name of Contractor.

b. Record Drawings: Organize Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

1.3 MANUAL FOR MATERIALS AND FINISHES

A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Engineer will review draft and return one copy with comments.

Herbert, Rowland & Grubic, Inc. 01 78 39 - 3 000483.0450

B. For equipment or component parts of equipment put into service during construction and operated by Owner, submit documents within ten days after acceptance.

C. Submit one copy of completed volumes before Substantial Completion. Draft copy be reviewed and returned after Substantial Completion, with Engineer comments. Revise content of document sets as required prior to final submission.

D. Submit two sets of revised final volumes within ten days after final inspection.

E. Submit in PDF composite electronic indexed file of final manual within ten days after final inspection.

F. Building Products, Applied Materials, and Finishes: Include product data, with catalog number, size, composition, and color and texture designations. Include information for re-ordering custom-manufactured products.

G. Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.

H. Moisture Protection and Weather Exposed Products: Include product data listing applicable reference standards, chemical composition, and details of installation. Include recommendations for inspections, maintenance, and repair.

I. Additional Requirements: As specified in individual product Specification Sections.

J. Include listing in table of contents for design data, with tabbed fly sheet and space for insertion of data.

1.4 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:

1. Material and equipment test and inspection reports.

2. Equipment and material delivery slips.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 78 39