01 33 00 - Submittal Procedures.pdf

PDF 500 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a Submittal Procedures specification document for the West Pump Station Replacement Project administered by Herbert, Rowland & Grubic, Inc. (HRG) as the Engineer for the Northwestern Chester County Municipal Authority in Pennsylvania. The project involves construction of a new suction lift style pump station with building and site improvements to replace the existing West Pump Station, including demolition of the existing below-grade package pump station, construction of sanitary sewer piping and associated manholes, installation of new pumps, construction of force main piping, and general site improvements. Bids for three separate contracts—General Construction (WPS-1), Electrical Construction (WPS-2), and Mechanical Construction (WPS-3)—will be received online until Wednesday, May 20, 2026 at 10:00 AM local time, with bids submitted on a lump sum basis. Contractors must submit all required submittals, including product data, shop drawings, samples, construction progress schedules, and proposed product and subcontractor lists within 15 days of the Notice to Proceed and in compliance with the detailed submittal procedures outlined in the specification.

The submittal procedures establish that all submittals must be transmitted electronically as PDF files to the project website and must include contractor certification verifying review, approval, and compliance with Contract Documents. The Engineer will review submittals within 15 days excluding delivery time, excluding weekends, and classify them as either Action Submittals requiring responsive action or Informational Submittals for knowledge purposes only. Submittals may be returned with one of four actions: "APPROVED," "APPROVED AS CORRECTED," "REVISE AND RESUBMIT," or "NOT APPROVED." Contractors are prohibited from fabricating products or beginning work until approved submittals have been received. The specification prohibits "mass submittals" defined as six or more submittals in one day or 20 or more in one week; such submittals may result in extended review timelines. Starting with the second resubmission, contractors may be charged by the Owner for Engineer time and expenses at standard rates, with charges offset against contractor payments.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
46 24 23 - Channel Sewage Grinders.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 33 00 – SUBMITTAL PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 33 00 - 1 000483.0450

SECTION 01 33 00 – SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Definitions.

B. Submittal procedures.

C. Construction progress schedules.

D. Proposed product & Subcontractor lists.

E. Product data.

F. Use of electronic CAD files of Project Drawings.

G. Shop Drawings.

H. Samples.

I. Other submittals.

J. Design data.

K. Test reports.

L. Certificates.

M. Manufacturer's instructions.

N. Manufacturer's field reports.

O. Erection Drawings.

P. Construction photographs.

Q. Contractor review.

R. Engineer review.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action.

B. Informational Submittals: Written and graphic information and physical Samples that do not require Engineer's responsive action. Submittals may be rejected for not complying

Herbert, Rowland & Grubic, Inc. 01 33 00 - 2 000483.0450 with requirements.

1.3 SUBMITTAL PROCEDURES

A. Transmit each submittal with Engineer-accepted form.

B. Sequentially number transmittal forms. Mark revised submittals with original number and sequential alphabetic suffix.

C. Identify: Project, Contractor, Subcontractor and supplier, pertinent Drawing and detail number, and Specification Section number appropriate to submittal.

1. Specification: Specification Number, Article Number (include the Paragraph

Letter if more than one item is included in the Article section) dash submittal number. Example: 03 30 00, 2.02-01 (1st submittal)

2. Plan Sheet: Plan and Sheet Number dash submittal number.

3. Mark revised resubmittals with original number and sequential alphabetic suffix.

D. Apply Contractor's stamp, signed or initialed, certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is according to requirements of the Work and Contract Documents.

Submittals not containing an executed certification stamp shall be returned.

E. Schedule submittals to expedite Project, and submit electronic submittals as PDF electronic files to Project Website. Coordinate submission of related items.

1. Submittals shall have the Contract Name, Contract Number, “Shop Drawing”, and

Submittal Identification Number in the subject line.

2. Engineer will review Submittal as received. PDF Submittal will be returned to

Contractor with comment(s) and Action using the same method as submitted.

3. APPROVED or APPROVED AS CORRECTED Submittals – will be provided on the

Project Website.

4. PDF electronic files: Where documents are scanned, all text shall be clearly readable and no information blurred/pixilated. Any non-readable text, blurred/pixilated information on a submittal will cause it to be rejected.

F. For each submittal for review, allow 15 days for the Engineer excluding delivery time to and from Contractor.

G. Identify variations in Contract Documents and product or system limitations that may be detrimental to successful performance of completed Work.

H. Allow 4”x4” space on submittals for Contractor and Engineer review stamps.

I. When revised for resubmission, identify changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements.

K. Submittals not requested will not be recognized nor processed.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 3 000483.0450

L. Incomplete Submittals: Engineer will not review. Complete submittals for each item are required. Delays resulting from incomplete submittals are not the responsibility of Engineer.

1.4 CONSTRUCTION PROGRESS SCHEDULES

A. Comply with Section 01 32 16 – Construction Progress Schedule

1.5 PROPOSED PRODUCT LIST

A. Within 15 days after date of Notice to Proceed, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.

B. For products specified only by reference standards, indicate manufacturer, trade name, model or catalog designation, and reference standards.

1.6 PRODUCT DATA

A. Product Data: Action Submittal: Submit to Engineer for review for assessing conformance with information given and design concept expressed in Contract Documents.

B. Distribute in accordance with Submittal Procedures above.

C. Mark each copy to identify applicable products, models, options, and other data.

Supplement manufacturers' standard data to provide information specific to this Project.

D. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

E. After review, produce copies and distribute according to "Submittal Procedures" Article and for record documents described in Section 01 73 00 – Execution Requirements.

1.7 ELECTRONIC CAD FILES OF PROJECT DRAWINGS

A. Electronic CAD Files of Project Drawings: May only be used to expedite production of Shop Drawings for the Project. Use for other Projects or purposes is not allowed.

B. Electronic CAD Files of Project Drawings: Distributed only under the following conditions:

1. Use of files is solely at receiver's risk. Engineer does not warrant accuracy of files.

Receiving files in electronic form does not relieve receiver of responsibilities for measurements, dimensions, and quantities set forth in Contract Documents. In the event of ambiguity, discrepancy, or conflict between information on electronic media and that in Contract Documents, notify Engineer of discrepancy and use information in hard-copy Drawings and Specifications.

2. CAD files do not necessarily represent the latest Contract Documents, existing conditions, and as-built conditions. Receiver is responsible for determining and complying with these conditions and for incorporating addenda and modifications.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 4 000483.0450

3. User is responsible for removing information not normally provided on Shop Drawings and removing references to Contract Documents. Shop Drawings submitted with information associated with other trades or with references to Contract Documents will not be reviewed and will be immediately returned.

4. Receiver shall not hold Engineer responsible for data or file clean-up required to make files usable, nor for error or malfunction in translation, interpretation, or use of this electronic information.

5. Receiver shall understand that even though Engineer has computer virus scanning software to detect presence of computer viruses, there is no guarantee that computer viruses are not present in files or in electronic media.

6. Receiver shall not hold Engineer responsible for such viruses or their consequences, and shall hold Engineer harmless against costs, losses, or damage caused by presence of computer virus in files or media.

1.8 SHOP DRAWINGS

A. Shop Drawings: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.

B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

C. When required by individual Specification Sections, provide Shop Drawings signed and sealed by a professional Engineer responsible for designing components shown on Shop Drawings.

1. Include signed and sealed calculations to support design.

2. Submit Shop Drawings and calculations in form suitable for submission to and approval by authorities having jurisdiction.

3. Make revisions and provide additional information when required by authorities having jurisdiction.

D. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information:

1. Dimensions.

2. Identification of products.

3. Fabrication and installation drawings.

4. Roughing-in and setting diagrams.

5. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

6. Shopwork manufacturing instructions.

7. Templates and patterns.

8. Schedules.

9. Compliance with specified standards.

10. Notation of coordination requirements.

11. Notation of dimensions established by field measurement.

12. Relationship to adjoining construction clearly indicated.

13. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 5 000483.0450

E. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches.

F. Submit electronic submittals via email as PDF electronic files.

1. The submittal requires the formatted shop drawing transmittal letter to be included as the cover sheet of the submittal on the Contractor’s letterhead. All show drawing and certification submissions are required to be on the form.

a. All shop drawings submitted to HRG for review shall bear the contractor’s certification that he has reviewed, checked and approved the shop drawings, all dimensions and that they are in conformance with the Contract Documents. Uncertified shop drawings will be returned to the Contractor for certification prior to review by HRG.

2. Scan the complete reviewed and approved shop drawing submittal as one PDF scan.

a. The scan attachment should be named per submittal.

3. The Engineer will review submittal as reviewed, comment and indicate action.

a. Engineer will submit responses on the Project Website (PDF) for the reviewed submittal to Contractor.

G. After review, produce copies and distribute according to "Submittal Procedures" Article and for record documents described in Section 01 77 00 – Closeout Procedures.

1.9 SAMPLES

A. Samples: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.

B. Samples for Selection as Specified in Product Sections:

1. Submit to Engineer for aesthetic, color, and finish selection.

2. Submit Samples of finishes, textures, and patterns for Engineer selection.

C. Submit Samples to illustrate functional and aesthetic characteristics of products, with integral parts and attachment devices. Coordinate Sample submittals for interfacing work.

D. Include identification on each Sample, with full Project information.

E. Submit number of Samples specified in individual Specification Sections; Engineer will retain one Sample.

F. Reviewed Samples that may be used in the Work are indicated in individual Specification Sections.

G. Samples will not be used for testing purposes unless specifically stated in Specification Section.

H. After review, produce copies and distribute according to "Submittal Procedures" Article and for record documents described in Section 01 77 00 – Closeout Requirements and Section 01 78 39 – Project Record Documents.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 6 000483.0450

1.10 OTHER SUBMITTALS

A. Closeout Submittals: Comply with Section 01 77 00 – Closeout Procedures.

B. Informational Submittal: Submit data for Engineer's knowledge as Contract administrator or for Owner.

C. Submit information for assessing conformance with information given and design concept expressed in Contract Documents.

1.11 TEST REPORTS

A. Informational Submittal: Submit reports for Engineer's knowledge as Contract administrator or for Owner.

B. Submit test reports for information for assessing conformance with information given and design concept expressed in Contract Documents.

1.12 CERTIFICATES

A. Informational Submittal: Submit certification by manufacturer, installation/application Subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or product but must be acceptable to Engineer.

1.13 MANUFACTURER'S INSTRUCTIONS

A. Informational Submittal: Submit manufacturer's installation instructions for Engineer's knowledge as Contract administrator or for Owner.

B. Submit printed instructions for delivery, storage, assembly, installation, startup, adjusting, and finishing, to Engineer in quantities specified for Product Data.

C. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

1.14 MANUFACTURER'S FIELD REPORTS

A. Informational Submittal: Submit reports for Engineer's knowledge as Contract administrator or for Owner.

B. Submit report within 5 days of observation to Engineer for information.

C. Submit reports for information for assessing conformance with information given and design concept expressed in Contract Documents.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 7 000483.0450

1.15 ERECTION DRAWINGS

A. Informational Submittal: Submit Drawings for Engineer's knowledge as Contract administrator or for Owner.

B. Submit Drawings for information assessing conformance with information given and design concept expressed in Contract Documents.

C. Data indicating inappropriate or unacceptable Work may be subject to action by Engineer or Owner.

1.16 CONTRACTOR REVIEW

A. Review for compliance with Contract Documents and approve submittals before transmitting to Engineer.

B. Contractor: Responsible for:

1. Determination and verification of materials including manufacturer's catalog numbers.

2. Determination and verification of field measurements and field construction criteria.

3. Checking and coordinating information in submittal with requirements of Work and of Contract Documents.

4. Determination of accuracy and completeness of dimensions and quantities.

5. Confirmation and coordination of dimensions and field conditions at Site.

6. Construction means, techniques, sequences, and procedures.

7. Safety precautions.

8. Coordination and performance of Work of all trades.

C. Stamp, sign or initial, and date each submittal to certify compliance with requirements of Contract Documents.

D. Do not fabricate products or begin Work for which submittals are required until approved submittals have been received from Engineer.

1.17 ENGINEER REVIEW

A. Do not make "mass submittals" to Engineer. "Mass submittals" are defined as six or more submittals or items in one day or 20 or more submittals or items in one week. If "mass submittals" are received, Engineer's review time will be extended as necessary to perform proper review. Engineer will review "mass submittals" based on priority determined by Engineer after consultation with Owner and Contractor.

B. Informational submittals and other similar data are for Engineer's information, do not require Engineer's responsive action, and will not be reviewed or returned with comment.

C. Submittals made by Contractor that are not required by Contract Documents may be returned without action.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 8 000483.0450

D. Submittal approval does not authorize changes to Contract requirements unless accompanied by Change Order, Field Order, or Work Change Directive.

E. Engineer's Action: Where action and return is required, Engineer will provide timely review of each submittal in accordance with the accepted Schedule of Submittals.

1. Submittals returned with "APPROVED" action indicates that the information submitted was found to be in conformance with the design concept and in compliance with the requirements of the Contract Documents. Contractor may proceed with performance of the work covered by the submittal.

2. Submittals returned with "APPROVED AS CORRECTED" action indicates that the information submitted was found to be in conformance with the design concept and in compliance with the requirements of the Contract Documents, provided the noted clarifications or corrections are completed. Submission of a corrected submittal indicating the changes noted by Engineer is required as part of the Project Record Documents. Contractor may proceed with performance of the work covered by the corrected submittal.

3. Submittals returned with "REVISE AND RESUBMIT" action indicate that: (1) information submitted is at least partially not in conformance with the design concept, (2) information submitted is at least partially not in compliance with the requirements of the Contract Documents, (3) submittal is incomplete and does not include all items required by the individual specification Sections, or (4) certifications or computations required by the individual specification Sections have not been included in the submittal. Submittal will be returned to Contractor noting the reasons for noncompliance. Contractor shall not proceed with the performance of the work covered by submittal until corrected information is submitted and approved.

4. Submittals returned with "NOT APPROVED" action indicates that the Engineer interprets the information submitted to be not in conformance with the design concept or not in compliance with the Contract Documents. Performance of the work shall not proceed until submittal is revised, resubmitted and approved.

F. Owner may offset payment due to Contractor to cover additional costs beyond the first resubmission review. Starting with the second resubmission, Contractor may be charged, by Owner, for the time and expenses of Engineer at Engineer's standard rates. Such charge shall be offset from Contractor's payment.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 33 00