01 29 00 - Payment Procedures.pdf

PDF 479 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a Payment Procedures specification document for the West Pump Station Replacement Project under Northwestern Chester County Municipal Authority in Pennsylvania. The document establishes the framework for contractor compensation, including the submission of a Schedule of Values within 15 days after Notice of Intent to Award, detailed breakdown of the Contract Price aligned with the Project Manual's Table of Contents, and identification of major specification sections, subcontract amounts, site mobilization, bonds, insurance, and Project Management costs. Contractors must submit Applications for Payment at stipulated intervals in electronic format, accompanied by construction photographs, partial releases of liens from subcontractors and vendors, updated construction schedules, and substantiating data as required by the Engineer. Initial Applications for Payment require submission of subcontractor lists, preliminary construction schedules, products lists, submittals schedules, and certificates of insurance, while Applications at Substantial Completion must include final Operation and Maintenance Manuals and test reports, and final payment applications require evidence of project closeout requirements, final Project Record Documents, and Contractor's Affidavits.

The payment terms require all amounts in the Schedule of Values to be rounded to the nearest whole dollar and total the full Contract Sum, with contractors responsible for furnishing all labor, materials, equipment, and tools necessary to complete the Work in a complete and acceptable manner without additional compensation for miscellaneous items not specifically mentioned in the Contract Documents. Payment will not be made for rejected products, including those wasted or disposed of improperly, determined unacceptable before or after placement, not completely unloaded from transporting vehicles, placed beyond required lines and levels, remaining on hand after completion, or associated with loading, hauling, and disposing of rejected materials. The Engineer maintains final authority to assess defective work and identify payment adjustments, with options including replacement of non-conforming work, remediation with payment adjustment, or retention of defective work with unit price adjustments at the Engineer's discretion.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
46 24 23 - Channel Sewage Grinders.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 29 00 – PAYMENT PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 29 00 - 1 000483.0450

SECTION 01 29 00 – PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Scope of Payment.

B. Schedule of Values.

C. Application for Payment.

D. Defect Assessment.

1.2 SCOPE OF PAYMENT

A. Contractor will receive and accept compensation provided for in the Contract as full payment for furnishing all materials, labor, tools, and equipment and for performing all Work in a complete and acceptable manner and for all risk, loss, damage, or expense of whatever character arising out of the nature of the Work or the prosecution thereof.

B. Contractor shall furnish all labor, materials, equipment, machinery, apparatus and tools and perform all operations necessary to install, equip, adjust and put into satisfactory operation the Work, and shall connect the various items or sections of the Work as to form a complete and properly operating whole. Any miscellaneous labor, materials, equipment or apparatus not specifically mentioned herein, or shown on the drawings, which may be found necessary to complete or perfect any portion of the Work in a substantial manner and in compliance with the requirements stated or implied by the Contract Documents, shall be furnished by the Contractor without additional compensation. This includes the cost of material disposal, water for testing and all testing costs including laboratory fees.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

B. Submit electronic file to Project website of schedule on Application for Payment Continuation Sheets.

C. Submit Schedule of Values as electronic file to Project website within 15 days after date Notice of Intent to Award.

D. Format:

1. Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.

Herbert, Rowland & Grubic, Inc. 01 29 00 - 2 000483.0450

2. Use Table of Contents of this Project Manual. Identify each line item with number and title of major Specification Section. Provide several line items for principal subcontract amounts, where appropriate.

3. Identify Site mobilization, bonds and insurance, and Project Management.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

E. Include in each line item amount of allowances as specified.

F. Include within each line item, direct proportional amount of Contractor's overhead and profit.

1. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

G. Revise schedule to list approved Change Orders with each Application for Payment.

1.4 APPLICATION FOR PAYMENT

A. Submit one electronic copy of each Application for Payment on form(s) provided in Section 00 62 76 – Contractors Application for Payment in accordance with requirements of the General Conditions.

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Content and Format: Use Schedule of Values for listing items in Application for Payment.

1. Execute by a person authorized to sign legal documents on behalf of Contractor.

Engineer will return incomplete applications without action.

2. Include amounts of Change Orders issued before last day of construction period covered by application.

C. Submit updated construction schedule with each Application for Payment.

D. Payment Period: Submit at intervals stipulated in the Agreement.

E. Submit executed originals with transmittal letter to Engineer by method ensuring receipt within 24 hours.

F. Substantiating Data: When Engineer requires substantiating information, submit data justifying dollar amounts in question. Include the following with Application for Payment:

1. Current construction photographs specified in Section 01 32 33 – Photographic

Documentation.

2. Partial release of liens from major Subcontractors and vendors.

3. Record Documents as specified in Section 01 77 00 – Closeout Requirements, for review by Owner, which will be returned to Contractor.

4. Affidavits attesting to off-Site stored products.

5. Construction Progress Schedule, revised and current as specified in Section 01 33

00 – Submittal Procedures.

G. Initial Application for Payment: Administrative actions and submittals that must precede

Herbert, Rowland & Grubic, Inc. 01 29 00 - 3 000483.0450 or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Contractor's Construction Schedule (preliminary if not final).

3. Products list.

4. Submittals Schedule (preliminary if not final).

5. Certificates of insurance and insurance policies.

H. Application for Payment at Substantial Completion: After issuance of the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete less the amounts certified by the Engineer as remaining.

1. Administrative actions and submittals that must precede or coincide with submittal of the Substantial Completion Application for Payment include the following:

a. Final Operation and Maintenance Manuals, as applicable.

b. Final test and field reports.

c. Draft Project Record Documents.

I. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following. Final Application will be prepared by the Engineer following completion of the final inspection per Section 01 77 00 – Closeout Procedures.

1. Evidence of completion of Project closeout requirements.

2. Final Project Record Documents.

3. Insurance certificates for products and completed operations and proof that taxes, fees, and similar obligations were paid.

4. Contractor's Affidavit: Submit on form provided by Engineer.

5. Consent of Surety to Final Payment: Submit on form provided by Engineer.

1.5 DEFECT ASSESSMENT

A. Replace the Work, or portions of the Work, not conforming to specified requirements.

B. If, in the opinion of Engineer, it is not practical to remove and replace the Work, Engineer will direct appropriate remedy or adjust payment.

C. The defective Work may remain, but unit sum/price will be adjusted to new sum/price at discretion of Engineer.

D. Defective Work will be partially repaired according to instructions of Engineer, and unit sum/price will be adjusted to new price at discretion of Engineer.

E. Individual Specification Sections may modify these options or may identify specific formula or percentage sum/price reduction.

F. Authority of Engineer to assess defects and identify payment adjustments is final.

G. Nonpayment for Rejected Products: Payment will not be made for rejected products for any of the following reasons:

Herbert, Rowland & Grubic, Inc. 01 29 00 - 4 000483.0450

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from transporting vehicle.

4. Products placed beyond lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 29 00