01 77 00 - Closeout Procedures.pdf
PDF 474 KB Posted
- Attached to
- West Pump Station Replacement Project
- Solicitation number
- Not on record
- Issued by
- Chester County, Pennsylvania
About this file
This is a Closeout Procedures specification document for the West Pump Station Replacement Project administered by the Northwestern Chester County Municipal Authority in Pennsylvania. The document establishes the requirements and procedures that the contractor must follow upon project completion, including submissions of maintenance manuals, project record documents, digital construction photographs, facility startup and testing, system adjustments and balancing, and demonstrations to the Owner's operating personnel. The contractor must submit an initial punch list indicating incomplete items, anticipated completion dates, and the value of nonconforming work before requesting Certification of Substantial Completion. Prerequisites for substantial completion include obtaining releases from authorities having jurisdiction and utility companies, delivering tools and spare parts to the Owner, performing final lock changeover, removing temporary facilities, and conducting final cleaning of the project site.
The closeout procedures establish a phased inspection and certification process, with the Engineer responsible for determining whether work meets substantial and final completion standards. Upon substantial completion, the Engineer prepares a Certificate of Substantial Completion accompanied by a verified final punch list, allowing the Owner occupancy while the contractor completes remaining items within a stipulated timeframe. Final completion requires submission of warranties, maintenance bonds, final payment requests with releases, accounting statements for contract changes, contractor affidavits regarding payment of debts and lien releases, and surety consent to final payment. The contractor must reimburse the Owner for Engineer re-inspection costs resulting from incomplete or defective work. Final cleaning requirements include sanitizing equipment and fixtures, cleaning operating equipment filters, removing debris from roofs and drainage systems, sweeping paved areas, and removing all waste materials and construction facilities from the site.
View the file
Other files
Show 40 more
Latest 50 of 171 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 77 00 – CLOSEOUT PROCEDURES
Herbert, Rowland & Grubic, Inc. 01 77 00 - 1 000483.0450
SECTION 01 77 00 – CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Closeout procedures.
B. Testing, adjusting, and balancing.
C. Final cleaning.
1.2 SUBMITTALS
A. Product Data: For cleaning agents.
B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.
C. Closeout Submittals:
1. Certificates of Release: From authorities having jurisdiction.
2. Certificate of Insurance: For continuing coverage.
3. Submittals as required by various specification sections.
1.3 CLOSEOUT PROCEDURES
A. Prerequisites to Substantial Completion: Complete following items before requesting Certification of Substantial Completion, either for entire Work or for portions of Work:
1. Submit maintenance manuals, Project record documents, digital images of construction photographs, and other similar final record data in compliance with this Section.
2. Complete facility startup, testing, adjusting, balancing of systems and equipment, demonstrations, and instructions to Owner's operating and maintenance personnel as specified in compliance with this Section.
3. Conduct inspection to establish basis for request that Work is substantially complete. Create comprehensive list (initial punch list) indicating items to be completed or corrected, value of incomplete or nonconforming Work, reason for being incomplete, and date of anticipated completion for each item. Include copy of list with request for Certificate of Substantial Completion.
4. Obtain and submit releases enabling Owner's full, unrestricted use of Project and access to services and utilities. Include certificate of occupancy, operating certificates, and similar releases from authorities having jurisdiction and utility companies.
5. Deliver tools, spare parts, extra stocks of material, and similar physical items to Owner.
6. Make final change-over of locks eliminating construction master-key system and transmit keys directly to Owner. Advise Owner's personnel of change-over in security provisions.
Herbert, Rowland & Grubic, Inc. 01 77 00 - 2 000483.0450
7. Discontinue or change over and remove temporary facilities and services from Project Site, along with construction tools, mockups, and similar elements.
8. Perform final cleaning according to this Section.
B. Substantial Completion Inspection:
1. When Contractor considers Work to be substantially complete, submit to
Engineer:
a. Written certificate that Work, or designated portion, is substantially complete.
b. List of items to be completed or corrected (initial punch list).
2. Upon receipt of request for Substantial Completion, Owner and Engineer will make inspection to determine whether Work or designated portion is substantially complete.
3. Should Engineer determine that Work is not substantially complete:
a. Engineer will promptly notify Contractor in writing, stating reasons for its opinion.
b. Contractor shall remedy deficiencies in Work and send second written request for Substantial Completion to Engineer.
c. Engineer will re-inspect Work.
d. Redo and Inspection of Deficient Work: Repeated until Work passes
Engineer's inspection.
4. When Engineer finds that Work is substantially complete, Engineer will:
a. Prepare Certificate of Substantial Completion on EJCDC C-625 - Certificate of Substantial Completion, accompanied by Contractor's list of items to be completed or corrected as verified and amended by Engineer and Owner (final punch list).
b. Submit preliminary Certificate to Owner for review.
c. Submit final Certificate to Owner and Contractor for their written acceptance of responsibilities assigned to them in Certificate.
5. After Work is substantially complete, Contractor shall:
a. Allow Owner occupancy of Project under provisions stated in Certificate of Substantial Completion.
b. Complete Work listed for completion or correction within time period stipulated.
C. Prerequisites for Final Completion: Complete following items before requesting final acceptance and final payment.
1. When Contractor considers Work to be complete, submit written certification that:
a. Contract Documents have been reviewed.
b. Work has been examined for compliance with Contract Documents.
c. Work has been completed according to Contract Documents.
d. Work is completed and ready for final inspection.
2. Submittals: Submit following:
a. Final punch list indicating all items have been completed or corrected.
b. Final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required.
Herbert, Rowland & Grubic, Inc. 01 77 00 - 3 000483.0450
c. Specified warranties, workmanship/maintenance bonds, maintenance agreements, and other similar documents.
d. Accounting statement for final changes to Contract Sum.
e. Contractor's affidavit of payment of debts and claims on form in Section
00 65 19.16.
f. Contractor affidavit of release of liens on form in Section 00 65 19.16.
g. Consent of surety to final payment on form in Section 00 65 19.19.
3. Perform final cleaning for Contractor-soiled areas according to this Section.
D. Final Completion Inspection:
1. After receipt of request for final inspection, Engineer will make inspection to determine whether Work or designated portion is complete.
2. Should Engineer or Owner consider Work to be incomplete or defective:
a. Engineer will promptly notify Contractor in writing, listing incomplete or defective Work.
b. Contractor shall remedy stated deficiencies and send second written request to Engineer that Work is complete.
c. Engineer and Owner will re-inspect Work.
d. Redo and Inspection of Deficient Work: Repeated until Work passes
Engineer's and Owner's inspection. Contractor shall reimburse Owner for the costs of Engineer for re-inspections due to incomplete work.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION
3.1 FINAL CLEANING
A. Execute final cleaning prior to final Project assessment.
B. Clean equipment and fixtures to sanitary condition with appropriate cleaning materials.
C. Clean filters of operating equipment.
D. Clean debris from roofs, gutters, downspouts, and drainage systems.
E. Clean Site; sweep paved areas, rake clean landscaped surfaces.
F. Remove waste and surplus materials, rubbish, and construction facilities from Site.
END OF SECTION 01 77 00