01 77 00 - Closeout Procedures.pdf

PDF 474 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a Closeout Procedures specification document for the West Pump Station Replacement Project administered by the Northwestern Chester County Municipal Authority in Pennsylvania. The document establishes the requirements and procedures that the contractor must follow upon project completion, including submissions of maintenance manuals, project record documents, digital construction photographs, facility startup and testing, system adjustments and balancing, and demonstrations to the Owner's operating personnel. The contractor must submit an initial punch list indicating incomplete items, anticipated completion dates, and the value of nonconforming work before requesting Certification of Substantial Completion. Prerequisites for substantial completion include obtaining releases from authorities having jurisdiction and utility companies, delivering tools and spare parts to the Owner, performing final lock changeover, removing temporary facilities, and conducting final cleaning of the project site.

The closeout procedures establish a phased inspection and certification process, with the Engineer responsible for determining whether work meets substantial and final completion standards. Upon substantial completion, the Engineer prepares a Certificate of Substantial Completion accompanied by a verified final punch list, allowing the Owner occupancy while the contractor completes remaining items within a stipulated timeframe. Final completion requires submission of warranties, maintenance bonds, final payment requests with releases, accounting statements for contract changes, contractor affidavits regarding payment of debts and lien releases, and surety consent to final payment. The contractor must reimburse the Owner for Engineer re-inspection costs resulting from incomplete or defective work. Final cleaning requirements include sanitizing equipment and fixtures, cleaning operating equipment filters, removing debris from roofs and drainage systems, sweeping paved areas, and removing all waste materials and construction facilities from the site.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
46 24 23 - Channel Sewage Grinders.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 77 00 – CLOSEOUT PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 77 00 - 1 000483.0450

SECTION 01 77 00 – CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Closeout procedures.

B. Testing, adjusting, and balancing.

C. Final cleaning.

1.2 SUBMITTALS

A. Product Data: For cleaning agents.

B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

C. Closeout Submittals:

1. Certificates of Release: From authorities having jurisdiction.

2. Certificate of Insurance: For continuing coverage.

3. Submittals as required by various specification sections.

1.3 CLOSEOUT PROCEDURES

A. Prerequisites to Substantial Completion: Complete following items before requesting Certification of Substantial Completion, either for entire Work or for portions of Work:

1. Submit maintenance manuals, Project record documents, digital images of construction photographs, and other similar final record data in compliance with this Section.

2. Complete facility startup, testing, adjusting, balancing of systems and equipment, demonstrations, and instructions to Owner's operating and maintenance personnel as specified in compliance with this Section.

3. Conduct inspection to establish basis for request that Work is substantially complete. Create comprehensive list (initial punch list) indicating items to be completed or corrected, value of incomplete or nonconforming Work, reason for being incomplete, and date of anticipated completion for each item. Include copy of list with request for Certificate of Substantial Completion.

4. Obtain and submit releases enabling Owner's full, unrestricted use of Project and access to services and utilities. Include certificate of occupancy, operating certificates, and similar releases from authorities having jurisdiction and utility companies.

5. Deliver tools, spare parts, extra stocks of material, and similar physical items to Owner.

6. Make final change-over of locks eliminating construction master-key system and transmit keys directly to Owner. Advise Owner's personnel of change-over in security provisions.

Herbert, Rowland & Grubic, Inc. 01 77 00 - 2 000483.0450

7. Discontinue or change over and remove temporary facilities and services from Project Site, along with construction tools, mockups, and similar elements.

8. Perform final cleaning according to this Section.

B. Substantial Completion Inspection:

1. When Contractor considers Work to be substantially complete, submit to

Engineer:

a. Written certificate that Work, or designated portion, is substantially complete.

b. List of items to be completed or corrected (initial punch list).

2. Upon receipt of request for Substantial Completion, Owner and Engineer will make inspection to determine whether Work or designated portion is substantially complete.

3. Should Engineer determine that Work is not substantially complete:

a. Engineer will promptly notify Contractor in writing, stating reasons for its opinion.

b. Contractor shall remedy deficiencies in Work and send second written request for Substantial Completion to Engineer.

c. Engineer will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes

Engineer's inspection.

4. When Engineer finds that Work is substantially complete, Engineer will:

a. Prepare Certificate of Substantial Completion on EJCDC C-625 - Certificate of Substantial Completion, accompanied by Contractor's list of items to be completed or corrected as verified and amended by Engineer and Owner (final punch list).

b. Submit preliminary Certificate to Owner for review.

c. Submit final Certificate to Owner and Contractor for their written acceptance of responsibilities assigned to them in Certificate.

5. After Work is substantially complete, Contractor shall:

a. Allow Owner occupancy of Project under provisions stated in Certificate of Substantial Completion.

b. Complete Work listed for completion or correction within time period stipulated.

C. Prerequisites for Final Completion: Complete following items before requesting final acceptance and final payment.

1. When Contractor considers Work to be complete, submit written certification that:

a. Contract Documents have been reviewed.

b. Work has been examined for compliance with Contract Documents.

c. Work has been completed according to Contract Documents.

d. Work is completed and ready for final inspection.

2. Submittals: Submit following:

a. Final punch list indicating all items have been completed or corrected.

b. Final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required.

Herbert, Rowland & Grubic, Inc. 01 77 00 - 3 000483.0450

c. Specified warranties, workmanship/maintenance bonds, maintenance agreements, and other similar documents.

d. Accounting statement for final changes to Contract Sum.

e. Contractor's affidavit of payment of debts and claims on form in Section

00 65 19.16.

f. Contractor affidavit of release of liens on form in Section 00 65 19.16.

g. Consent of surety to final payment on form in Section 00 65 19.19.

3. Perform final cleaning for Contractor-soiled areas according to this Section.

D. Final Completion Inspection:

1. After receipt of request for final inspection, Engineer will make inspection to determine whether Work or designated portion is complete.

2. Should Engineer or Owner consider Work to be incomplete or defective:

a. Engineer will promptly notify Contractor in writing, listing incomplete or defective Work.

b. Contractor shall remedy stated deficiencies and send second written request to Engineer that Work is complete.

c. Engineer and Owner will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes

Engineer's and Owner's inspection. Contractor shall reimburse Owner for the costs of Engineer for re-inspections due to incomplete work.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. Execute final cleaning prior to final Project assessment.

B. Clean equipment and fixtures to sanitary condition with appropriate cleaning materials.

C. Clean filters of operating equipment.

D. Clean debris from roofs, gutters, downspouts, and drainage systems.

E. Clean Site; sweep paved areas, rake clean landscaped surfaces.

F. Remove waste and surplus materials, rubbish, and construction facilities from Site.

END OF SECTION 01 77 00

File details come from the government source that posted it. Updated .