36C25225R0004 0004.docx
DOCX document 181 KB Posted
- Solicitation number
- 36C25225R0004
About this file
This is Amendment 0004 to solicitation 36C25225R0004 for the replacement of a boiler plant at the Oscar G. Johnson VA Medical Center in Iron Mountain, MI. The amendment extends the proposal due date to February 3, 2025 at 11:59 PM CST.
The amendment primarily provides answers to vendor questions regarding technical specifications for asbestos abatement quantities, electrical requirements, instrumentation cables, VFD specifications, switchboard details, fencing requirements, and fuel tank specifications. Key clarifications include: no temporary steam will be required as the new plant will be operational before removing the old system; the VA will supply cameras, emergency phones, and WiFi devices while the contractor must furnish and install gas detection sensors; spray fireproofing will not be required on new construction; and all exterior windows must be blast resistant. The boilers will have a fuel consumption rate of 116.6 gph each at full fire, requiring pump flow rates of minimum 6 gpm. The amendment also includes attached documents showing site visit sign-in sheets and electric heater product data.
View the file
Other files
Show 40 more
Latest 50 of 57 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) None
01-21-2025
585-25-1-6951-0003
585-21-115
Department of Veterans Affairs
GLAC (69D)
115 South 84th Street, Suite 101
Milwaukee WI 53214-1476
Department of Veterans Affairs
GLAC-MILWAUKEE (69D)
Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25225R0004 12-16-2024
X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 02-03-2025 23:59 CST
Project 585-21-115 Boiler Plant at the Oscar G. Johnson VA Medical Center in Iron Mountain, MI
Amendment 0004 hereby incorporates the details provided on the following pages(s) into solicitation requirements.
Acknowledge amendment in your offer in Block 19 of the SF-1442.
Kristi Kluck Contracting Officer
SOLICITATION 36C252250004
AMENDMENT 0004
January 21, 2025
Project: 585-21-115 Replace Boiler Plant
| Location: | Oscar G. Johnson VA Medical Center | |
| 325 E. H Street | ||
| Iron Mountain, MI 49801 |
AMENDMENT 0004 hereby incorporates the following clarifications/change(s) into the solicitation package:
A. Vendor Questions
Question 5, received 1/2/2025 “I’ve been reading thru the specs and drawings for this project and I can’t seem to find an asbestos survey or information sheet to give approximate quantities of pipe insulation, fittings or amount of gaskets that are going to be abated. In section 02 82 13.13 - 1.1 Summary of Work, Part B in the Extent of Work it says ‘Below is a brief description of the estimated quantities of asbestos containing materials to be abated by Glovebag method. But no quantities are listed.’ Could you please provide a little more insight to the amount of asbestos that needs to be remove.”
VA REPLY: There is no hazmat master plan. Available quantities and descriptions can be found on Drawings MD121 and MD201 and Spec Section 02 82 13.13.
Question(s) 9, received 1/6/2025:
9.1. “#2. Ref drawing ES171: At the fuel tank Keyed Note 14 and detail 1/ES501 are pointed to the same location. Do we need both a 16”X16” junction box and a receptacle pedestal/power distribution panel?.”
VA REPLY: No, Panel is at the end of the circuit so no junction box is needed unless necessary for ease of installation.
9.2 “#3. Ref drawing ES171- Note on the east side of fuel tank; 24” dia. Manhole. Can a better description be provided for the manhole and what it serves?”
VA REPLY: It serves to route all circuits, list in the annotation below emergency phone (EP4) scada conductors, lighting conductors, and FO cable for security.
9.3. “#4. Ref drawing EP121- Who is providing the following VFD’s 2-119-PMO-001, 2-119 PMO-002, 2-119-PMO-003, 2-119-PMO-004, 2-119-PMO-005?
VA REPLY: The contractor, VFD to be furnished with the pumps they serve.
9.4. “#5. Ref drawing EP601- Can wire and conduit size be provided for runs from 2-120B-480E-SWBD-001 to 2-120A-480-ATS-001 and 2-120A-480-ATS-002?”
| VA REPLY: |
| - 2 sets of (4) 250kcmil and (1) #3 ground in 2-1/2” conduit to 2-120B-480E-SWBD-001 |
| - 1 set of (4) 300kcmil and (1) #4 ground in 2-1/2” conduit to 120A-480-ATS-001 |
| - 1 set of (4) #1 and (1) #8 ground in 1” conduit to 120A-480-ATS-002 |
9.5. “#6. Drawing EP604- All conduits on the cable & conduit schedule are labeled RMC, can EMT be used instead? Other drawings show EMT conduit. Example would be drawing EI121 keyed notes 1 and 2.”
VA REPLY: Yes, the specifications maintained EMT as an option, RMC was used as the design basis for conduit fill calcs.
9.6. “#7. Can location of the following be identified? Emergency Fuel Oil Shut Off – Panel C circuit 14/16/18”.
VA REPLY: See DWG-22367-EP401_A.REV01 ELECTRICAL TEMPORARY FUEL TANK POWER - BASEMENT LEVEL
9.7. “#8. Can wire sizes be confirmed for Panel 02-PP3 circuit 13/15, the ground is larger than the hot?”
VA REPLY: (2)#10 Hot (1) #12 GND
| 9.8. | “9. Drawing EI501- Is the electrical contractor to supply the lift station annunciator panel? And the Boiler Safety Testing Panel?” | |
| VA REPLY: Yes. | ||
| 9.9. | “10. Will a cable schedule be provided for the electrical instrumentation?” | |
| VA REPLY: Instrumentation cables and conductor’s schedules should be submitted by the Boilers and BAS/HVAC controls contractors. Instrumentation wiring is selected based on manufacturer specific requirements for their devices and preferred location. | ||
| 9.10. | “11. Who is responsible for the SCADA work?” | |
| VA REPLY: Contractor is responsible for the installation, programming, and training of VA Staff on operation of the SCADA System. | ||
| 9.11. | “12. Who is to supply and install the following: | |
| Cameras | ||
| Emergency Phones | ||
| Gas Detection sensors | ||
| WIFI devices | ||
| POE Security Switch (Drawing ET501)” |
VA REPLY:
· Cameras - VA supplied / Contractor installed.
· Emergency Phones – VA supplied / Contractor installed.
· Gas Detection sensors – Contractor furnished and installed
· WIFI devices - VA supplied / Contractor installed.
· POE Security Switch (Drawing ET501) - VA to supply POE security switch; Contractor to supply remaining components as specified on parts list on ET501. Contractor to install.
9.12. “13. Are switchboards 2-120A-480N-SWBD-001 and 2-120B-480E-SWBD-001 provided?”
VA REPLY: These should be included in the bid; they are not existing. Square D I-Line was used as the design basis.
Question(s) 10, received 1/7/2025:
10.1 “14. On drawing MP501 detail 5 Steam Meter. What instruments are this detail assigned to? The P&IDs for the Steam system are all shown as Vortex Shedding Flow Meters, not differential Pressure. See below.”
VA REPLY: Specification 29 03 11 under section 2.8 Flow Meter reads "As an option, pressure compensation and the compensated flow rate shall be performed and displayed by a boiler plant controller receiving signals from the flow meter and from a pressure transmitter.
10.2 “15. On drawing EI121 Instrument TG34028 is shown near Condensate Receiver Pump 2-119-PMP-001 but is not shown on P&ID D-633 or D-634. Please advise where this instrument is located.”
VA REPLY: Instrument in question is a temperature sensor for soft makeup -water heat exchanger, this device is shown on process drawings D-645.
10.3 “16. Are any of the solenoid valves air operated?”
VA REPLY: As per 23 09 11 and 23 09 23 control valves shall be electric or electronic driven/operated.
10.4 “17. Will there be an instrumentation cable schedule to use for bidding purposes on this project? If not, what should we base our proposal on to determine types of cables, routes, and lengths? Who will be responsible to provide a cable list after the project is awarded if one is not provided by the engineer?”
VA REPLY: Instrumentation cables and conductor’s schedules should be submitted by the Boilers and BAS/HVAC controls contractors. Instrumentation wiring is selected based on manufacturer specific requirements for their devices and preferred location.
Question 13, received 1/9/2025:
13.1 “On page GC103, Detail 2 lists Western perimeter Fence. Is this fence to be the fence included on page CS501?”
VA REPLY: Detail 2 calling out the fence is the same as the keynote 3 on CS171, but is not 3/CS501 Security Fence. This fence is to match the existing fence to the south and is covered by spec 323119 Decorative Steel Fences and Gates.
| 13.2 | “On page GC103, Detail 3 lists a Ram gate. What is the exact length for this gate? it seems like 27' we just want to be sure.” |
| Will the operator for this gate be installed in the island curb that is to be installed, or can the operator be installed before the curb? |
VA REPLY: Length should be about 28’. Can be installed either way, but a 6” pad is called out on CS501.
13.3 “On page Cs171, Detail 9 lists a double swing gate. Is this gate to stretch the full length of the parking way, or is this to be the 28' listed on detail page CS501?
Also there seems to be fence connected to this gate, but there is no detail calling out what type of fence. Is this to be the security fence listed on page CS501?”
VA REPLY: The double swing gate is to be 28' as listed on 2/CS501. The east/west fence is the same as detail 3/CS501 and is covered by 323113 Chain Link Fences and Gates.
Question 15, received 1/13/2025:
| 15.1 | “Can you clarify the following please? (It seems different people in the office are reading this and interpreting it a little differently than I am). | |
| [Under SOLICITATION INSTRUCTION AND EVALUATION FACTORS]: | ||
| C. | CPARS Past Performance (Pass / Fail). Offerors shall not include this information; Contracting Officer will retrieve this information directly from CPARS. | |
| i. Offeror, or subcontractors, shall have no negative findings in the CPARS-FAPIIS database during the last five (5) years. | ||
| ii. Offeror, or subcontractor, shall have no CPARS evaluations whereby the contracting officer would NOT recommend them for similar requirements due to the offer’s ability to perform in accordance with the contract’s most significant requirements database during the last five (5) years. | ||
| iii. | If offer, or subcontractor, has no CPARS evaluations, the same requirements apply to past performance submissions received from previous customers. |
If the General Contractor has CPARS evaluations in the system, are we still required to send out the PPQ evaluations to past clients, or are the PPQ only required if there are NO CPARS available.
VA REPLY: The VA recommend including PPQ with your offer. Some previous contracts demonstrating high qualifications for this project may not be in CPARS. It is sometimes good to get PPQ from customers outside the government.
Question 16, received 1/13/2025:
| 16.1 | “I'm reaching out in regards to the upcoming boiler plant replacement project at Iron Mountain VAMC. |
| I was reading through the scope and did not see any lines or provisions for portable rental boilers during the project. | |
| We have worked at several out VA facilities throughout the country providing temporary steam when needed. Please advise if this is something we can work with yourself, or the winning contractor with. I appreciate your time and look forward to hearing back.” |
VA REPLY: There is no need for temporary steam on this project. The new plant will be operable before the old system is removed. If there is any other work you are interested in, you can contact the prime vendor once award is finalized. Information on the awardee will be published to www.SAM.gov once award is finalized.
Question(s) 18, received 1/13/2025
18.1 “18. Ref drawing SD141- keynote 1 represents removing all catwalks and platforms on the mezzanine level. During site visit I noted a upper mezzanine along the west wall which is made up of structural steel framing and concrete deck. This deck is about 6’+ wide and 58’+- long with additional service catwalks jutting out from it. Does this upper deck, connected service catwalks and stairs require removal despite not shown on drawings?”
VA REPLY: The upper deck running north-south along the west wall of the existing boiler plant is to remain.
| 18.2 | “19. Ref drawing SD141 & MD161- a large steel coal hopper between north south column lines 2 & 3 and east west column lines A thru F. Does this hopper remain, or does it require removal? If being removed does lead paint exist? Is the bunker empty?” |
| VA REPLY: Coal hopper is to remain (and is empty). |
18.3 “20. Ref spec 02 41 00- Part 1.2 of this section related to lead paint removal section 02 83 33.13. Is lead paint present on any materials or components being removed under this project? If so what materials and or components scheduled” VA REPLY: Potential for lead paint within the existing structure is unknown. Catwalks specified for demolition date to current boiler installation in the late 1980’s but original plant structures are much older.
18.4 “21. Ref spec 02 82 13.13- Will quantities be provided for asbestos abatement or is the only abatement needed noted on drawings MD121, MD201?”
VA REPLY: There is no hazmat master plan. Available quantities and descriptions can be found on Drawings MD121 and MD201 and Spec Section 02 82 13.13.
18.5 “22. Ref drawing CD171, keynote 12- Is the abandoned tank empty or has it been filled with a slurry? Is the tank steel or fiberglass?”
VA REPLY: The abandoned tank noted on CD171 is recorded as “closed” by EGLE but the records do not describe its final state in detail. Assume that it is grout filled. Based on vintage and some photos discovered by the VA, it appears to be a steel tank.
18.6 “23. Ref drawing SB171 general note 7- Is fireproofing required on any structural steel for this project? If so will specifications and a schedule be provided?”
VA REPLY: Spray fireproofing will not be required on the new construction.
Question 19, received 1/9/2025
19.1 “One additional question: The schedules on drawing MK602 has two blowdown separators listed 2-119-TK-003 and 2-201-TK-006. When I do a search on the drawings the only one that shows up is 2-119-TK-003 on drawing MK121, is there truly 2 blowdown separators required?”
VA REPLY: Temporary Blowdown Separator 2-201-TK-006 is found under construction document GC102. Temporary blowdown separator is needed to reroute existing boilers blowdown from legacy blowdown vault to sanitary waste (see PP122 keyed note#1 for plumbing details).
Question(s) 20, received 1/13/2025
| 20.1 | “There is a platform shown at the exterior fuel tank on C, that is not shown on the structural drawings. Can steel details for this platform be provided? |
| VA REPLY: This platform is to be designed by tank manufacturer to the dimensions and arrangement as shown on the drawings. Refer to specification section 231000 2.2.C and General Note 5 on MP171. | |
| 20.2 | “Confirm that all exposed steel (columns, beams, trusses, metal decks) is to receive spray-fireproofing, please provide specification.” |
| VA REPLY: The building is classified as Type II-000, which does not require ratings of structural framing. Therefore, we did not provide a spray on fire proofing spec and the special inspections portion of the project manual indicated that it is “not used.” | |
| 20.3 | “What is the existing BAS system?” |
| VA REPLY: The existing BAS is a BACnet protocol network with main workstation (server) at the Maintenance area. | |
| 20.4 | “Confirm that a systems integrator will be required on this project.” |
| VA REPLY: System integrator shall integrate required Boiler controls BACnet points and new building HVAC controls to campus BAS network. | |
| 20.5 | “Confirm that (3) separate individuals will be required to fill the superintendent, SSHO & CQC system manager roles.” |
| VA REPLY: | |
| 20.6 | “Confirm that a Special Inspector of Record is required.” |
| VA REPLY: Confirmed. | |
| 20.7 | “Is the existing roofing system under warranty? If so, please provide roofing contractor’s information.” |
| VA REPLY: Negative, there is no existing warranty on record. | |
| 20.8 | “Please confirm blast requirements for exterior windows.” |
| VA REPLY: All Exterior windows are to be blast resistant. Refer to Specification Section 08 56 53 Blast Resistant Windows as well as 08 80 00 - Glazing, Paragraph 3.12 for glazing requirements specific to exterior windows. | |
| 20.9 | “Are there Environmental reports associated with the existing fuel tank?” |
| VA REPLY: The existing buried fuel tank is on record with EGLE as being “Closed in Ground.” | |
| 20.10 | “Is there a quantity or amount that should be assumed or used as an allowance for handling/removal of contaminated soils? |
| VA REPLY: Is there a quantity or amount that should be assumed or used as an allowance for handling/removal of contaminated soils? |
Question 22 received 1/14/2025: Internal VA question; no information provided via amendment.
Questions(s) 23, received, 1/14/2025:
23.1 “On drawing MP501 detail 5 Steam Meter. What instruments are this detail assigned to? The P&IDs for the Steam system are all shown as Vortex Shedding Flow Meters, not differential Pressure. See below:
| VA REPLY: Specification 29 03 11 under section 2.8 Flow Meter reads "As an option, pressure compensation and the compensated flow rate shall be performed and displayed by a boiler plant controller receiving signals from the flow meter and from a pressure transmitter. | ||
| 23.2 | “On drawing EI121 Instrument TG34028 is shown near Condensate Receiver Pump 2-119- PMP-001 but is not shown on P&ID D-633 or D-634. Please advise where this instrument is located.” | |
| VA REPLY: Instrument in question is a temperature sensor for soft makeup -water heat exchanger, this device is shown on process drawings D-645. | ||
| 23.3 | “Are any of the solenoid valves air operated?” | |
| VA REPLY: As per 23 09 11 and 23 09 23 control valves shall be electric or electronic driven/operated. | ||
| 23.4 | “Will there be an instrumentation cable schedule to use for bidding purposes on this project? If not, what should we base our proposal on to determine types of cables, routes, and lengths? Who will be responsible to provide a cable list after the project is awarded if one is not provided by the engineer?” | |
| VA REPLY: Instrumentation cables and conductor’s schedules should be submitted by the Boilers and BAS/HVAC controls contractors. Instrumentation wiring is selected based on manufacturer specific requirements for their devices and preferred location. |
Question 24 received 1/14/2025: Internal VA question; no information provided via amendment.
Question 25, received 1/14/2025:
| 25.1 | I have been working with a number of mechanical contractors on this project bid. I was not sure if I was suppose to send our information directly to you or if it needed to be grouped in under one of the contractors. I appreciate the information. I will continue to work with the contractors on our portion of the project bid, the boiler and Balance of Plant Controls, similar to the boiler plant controls we provided and continue to service at the Zablocki VA in Milwaukee. |
| On a project like this will your team post an approved list of contractors per the solicitation requirements? Thank you for your time and information. | |
| On a project like this will your team post an approved list of contractors per the solicitation requirements? | |
| VA REPLY: If you are going to work a general contractor or any subcontractors, then they should collect your info and the prime will include w/ their offer. | |
| There is not a list of approved contractors. There is an SBA website (Veteran Small Business Certification) that is open to the public, where you can search for SDVSOB contractors, via location, NAICS code, etc. etc. It includes all types of vendors and contractors (not just construction). | |
| You can also monitor the SAM.gov website and review the list of “interested vendors” (I think your company needs to be registered in SAM to get those details though). I recommend you register your company as an interested vendor on the SAM solicitation so other contractors might contact you as a potential supplier or sub. I don’t think a lot of people use this resource though. | |
| Also, Amendments #1, #2 and #3, previously posted to SAM.gov include site-visit attendee sign-in sheet. |
Question(s) 26, received 1/14/2025:
26.1 Can you tell me the relief valve pressure setting for the five heat exchangers on this job?
Mechanical HVAC Equipment:
| • | 2-200-HEX-001 | |
| • | 2-200-HEX-002 | |
| • | 2-202-HEX-001 | |
| VA REPLY: The above three items are 150 psi. |
Boiler Plant Mechanical Equipment:
| • | 2-119-HEX-001 | |||
| • | 2-200-HEX-003 | |||
| VA REPLY: The above two items are 150 psi. | ||||
| 26.2 what is the temperature of the liquid in the condensate transfer pumps? | ||||
| • | 2-119-PMP-001, -002 | |||
| VA REPLY: The temperature is 212 F. |
Question 27, received 1/14/2025:
Proposed alternate request: Thin Tech:
There is a material called Tabs that is specified to be used with the thin brick on the project. Some of the masons have asked me if we could bid On a product called Thin Teck by Glen Gary. I would be happy to send you the product information to look at so we can see if either product Would do the job. Thank you for your consideration The system that’s most like TAB’s is our Classic.
However, the best system we have for exterior use is the Thin Tech Elite. This system has air chambers that allow for drainage and does not require a drainage barrier. It only requires the initial Water Resistant or Tyvek layer by Glen Gary.
VA REPLY: This proposed alternate is not acceptable; contractors shall provide specified requirements.
TABS has Pre-Bent Corner Panel - Glen-Gery does not.
Fire Testing - TABS 2 hours, Thin Tech only 1 hour.
TABS has additional test data as part of spec; not provided by Glen-Gery
- ASTM E2273-03 Water Drainage
- Accelerated Weathering ICC Evaluation EG356
- ASTM E96-05 Water Vapor Transmission
- ASTM C1338-02 Fungi Resistance
- ASTM D1761 Lateral Resistance Testing
- ASTM D 3498 Mastic
- ASTM C-1135 Freeze Thaw Tensile Adhesion Properties
Question 28 received 1/15/2025: Internal VA question; no information provided via amendment.
Question 29 received 1/16/2025: Internal VA question; no information provided via amendment.
For the technical portion of this proposal, could you provide clarity on what you need presented for:
Part 3 - Specification 23 05 10 – Common Work Results for Boiler Plant and Steam Generation (Part 1.5 Quality Assurance):
(a) Products shall be the standard products of a manufacturer regularly engaged in the manufacture of the products for at least 3 years. The design, model and size of each item shall have been in satisfactory and efficient operation on at least three installations for approximately three years. However, digital electronics devices, software and systems such as controls, instruments, computer work station, shall be the current generation of technology and basic design that has a proven satisfactory service record of at least three years.
IS this for what we anticipate to use on this project, or what was used in past projects?
VA REPLY: Contractors need to demonstrate the item they will be providing meets the requirements outlined in the referenced specification. Provide information that demonstrates what (product) / who you are providing (manufacturer) is 1.) coming from a manufacturer w/ three years of experience, 2) has been successfully installed and operable in at least 3 jobs which have been in operation for at least 3 years
Question(s) 30, received 1/16/2025:
| 30.1 - On drawing MP 171 on the fuel oil tank, the fill line is shown as 1.5 inches. If the fill line is at that size filling the tank off of a delivery truck will take a long time. Is increasing the fill line size to 3” acceptable? | |
| VA REPLY: Yes, the fill line should be 3”. | |
| 30.2 - Is there a detailed drawing showing the transition from underground piping to aboveground piping for the outside fuel piping? | |
| VA REPLY: The transition is shown on MP504, Detail 3. The transition occurs near a flanged fitting. This transition would be inside the building in the trench. | |
| 30.3 - Is there a piping detail for the new generator room and where the tie in location is to the existing fuel loop from the new pump skid? | |
| VA REPLY: The tie in location is shown on MK401, Detail 2. | |
| 30.4 - Is there a drawing showing the piping details for the Heat Exchanger (2-200-HEX-003)? | |
| VA REPLY: Refer to D-616 for piping details. | |
| 30.5 - The new pump skid that we would be installing is 2-gpm. What is the consumption rate of the new boilers and generator that would be installed on this project? | |
| VA REPLY: The generator is not connected to this fuel supply. The basis of design boilers burn 116.6 gph each at full fire. Each pump should be able to supply all the boilers at one time by itself. Pump flow rate should be a minimum of 6 gpm instead of the 2 gpm as shown on the drawings. | |
| 30.6 - Is there going to be drainage for the piping trench for water intrusion? | |
| VA REPLY: There is a sump and drain inside the concrete trench at the end closest to the tank. This drain is routed to an oil water separator. The trench is sloped to this drain. | |
| 30.7 - Would installing double-walled fiber glass pipe be acceptable for the underground piping? This would omit the trench and need for pipe insulation. | |
| VA REPLY: A trench is desired either way to try to limit contaminated soils due to a potential future leak. Alternative containment pipe designs may be evaluated during construction, but the current design details are shown on MP504 and should be priced accordingly. | |
| 30.8 - In the specs for the above ground storage tank, it calls out for the bottom 3 feet of the inside of tank to have a liner per API RP 1631. This API section references “Interior Lining of Underground Storage Tanks”. Would this be applicable for this tank as well? | |
| VA REPLY: Yes, it will apply to this tank as well. |
Question 31 received 1/16/2025: Internal VA question; no information provided via amendment.
Question 34, received 1/16/2025:
| 34.1 | Do you have cut sheets on the existing Electric heater to be reused? |
| Should we make mounting and piping and electrical provisions for it in our skids? | |
| Is the temperature control system existing? |
VA REPLY: Existing electric heater product data is attached to this amendment.
The time and due date for offers have NOT changed since Amendment 0003.. Offers are due NLT Monday, February 3, 2025 at 11:59 p.m. CST.
ATTACHMENTS -
See attached document: S06 0004 Att Site Visits 1.2.3_Sign Ins_585-21-115.
See attached document: S06 0004 Att_Electric Heater product data.
-- END OF DOCUMENT --