33 14 19 - Valves And Hydrants For Water Utility Service.pdf

PDF 483 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This technical specification document outlines the requirements for valves and hydrants for water utility service, prepared by Herbert, Rowland & Grubic, Inc., for the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4). The specification encompasses the procurement and installation of resilient-wedge gate valves with mechanical joint end connections rated at 200 psi for 12-inch diameter and smaller applications, valve boxes constructed of cast iron with tar or asphaltic coatings, and fire hydrants including both smart hydrants (Clow Valve Co., Model iHydrant) and standard hydrants (Mueller, Model Super Centurion 250). All valves and hydrants must comply with American Water Works Association standards (AWWA C500, C502, C509, and C550), include fusion bonded epoxy coatings for interior and exterior protection, and be certified for potable water contact according to NSF 61 and NSF 372. Fire hydrants must be dry-barrel, breakaway type units with compression valves, 6-inch inlet connections, and red polyurethane topcoating, equipped with one 4.5-inch pumper nozzle and two 2.5-inch hose nozzles. The project involves the replacement of approximately fifteen fire hydrants and the relocation of approximately 13,860 feet of water main with associated appurtenances, with a bid deadline of Thursday, August 6, 2026, at 10:00 AM local time through the PennBid online platform.

All materials must be delivered in manufacturer's original packaging with sealed ends to prevent foreign matter contamination, inspected upon receipt, and stored in clean, dry locations remote from construction operations. Valve boxes require alignment devices to prevent shifting during backfilling, and all installations must be performed in conjunction with pipe laying as specified in related sections covering trenching, backfilling, concrete work for thrust restraints, and disinfection procedures. Post-installation requirements include pressure testing with water mains per Section 33 05 05.31, flushing and drainage verification of fire hydrants after main-line pressure testing, and disinfection of the water piping system in accordance with Section 33 13 00. The specification mandates that manufacturer names, pressure ratings, and fabrication years be cast into valve bodies, and that project record documents accurately document actual locations of all installed valves and hydrants upon project completion.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 14 19 – VALVES AND HYDRANTS FOR WATER UTILITY SERVICE

Herbert, Rowland & Grubic, Inc. 33 14 19 - 1 009280.0426

SECTION 33 14 19 – VALVES AND HYDRANTS FOR WATER UTILITY SERVICE

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Valves.

2. Valve boxes.

3. Fire hydrants.

B. Related Requirements:

1. Section 03 30 00 – Cast-in-Place Concrete: Concrete for thrust restraints.

2. Section 31 23 33 – Trenching and Backfilling for Utilities.

3. Section 33 13 00 – Disinfection of Water Utility Distribution: Requirements for flushing and disinfecting.

4. Section 33 14 13 – Public Water Utility Distribution Piping: Pressure testing of valves and hydrants.

5. Section 33 14 17 – Site Water Service Utility Laterals: Piping, trenching, backfilling, and compaction requirements.

1.2 REFERENCE STANDARDS

A. American Water Works Association:

1. AWWA C500 - Metal-Seated Gate Valves for Water Supply Service.

2. AWWA C502 - Dry-Barrel Fire Hydrants.

3. AWWA C509 - Resilient-Seated Gate Valves for Water Supply Service.

4. AWWA C550 - Protective Interior Coatings for Valves and Hydrants.

B. National Fire Protection Association:

1. NFPA 291 - Recommended Practice for Fire Flow Testing and Marking of Hydrants.

C. NSF International:

1. NSF 61 - Drinking Water System Components - Health Effects.

2. NSF 372 - Drinking Water System Components - Lead Content.

1.3 COORDINATION

A. Section 01 10 00 – Project Summary: Requirements for coordination.

B. Coordinate Work of this Section with installation of water mains.

1.4 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Product Data: Submit manufacturer information regarding component materials, fittings, assembly and parts diagram, and accessories.

Herbert, Rowland & Grubic, Inc. 33 14 19 - 2 009280.0426

1.5 CLOSEOUT SUBMITTALS

A. Section 01 77 00 – Closeout Requirements: Requirements for submittals.

B. Project Record Documents: Record actual locations of valves and hydrants.

1.6 QUALITY ASSURANCE

A. Materials in Contact with Potable Water: Certified according to NSF 61 and NSF 372.

B. Cast manufacturer's name, pressure rating, and year of fabrication into valve body.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Section 01 61 00 – Product Requirements: Requirements for transporting, handling, storing, and protecting products.

B. Delivery:

1. Seal valve and hydrant ends to prevent entry of foreign matter.

2. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.

C. Store materials according to manufacturer instructions.

D. Protection:

1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.

2. Provide additional protection according to manufacturer instructions.

PART 2 - PRODUCTS

2.1 VALVES

A. Performance and Design Criteria:

1. Pressure Rating:

a. 12-inch Diameter and Smaller: 200 psi.

2. End Connections: Mechanical joint.

3. Coatings:

a. Fusion bonded epoxy coating, comply with AWWA C550.

b. Application: Interior and exterior.

B. Resilient-Wedge Gate Valves:

1. Manufacturers:

a. American Flow Control.

b. Mueller.

c. Or approved equal.

2. Description:

a. Comply with AWWA C509 or C515.

b. Body: Ductile iron.

Herbert, Rowland & Grubic, Inc. 33 14 19 - 3 009280.0426

c. Seats: Resilient.

d. Stem:

1) Type: Non-rising.

2) Material: Bronze.

e. Operation:

1) Square operating nut.

2) Opening Direction: Counterclockwise.

2.2 VALVE BOXES

A. Manufacturers:

1. Tyler Utilities.

2. Bingham & Taylor.

3. Ford.

4. Or approved equal.

B. Description:

1. 12-inch Diameter Valves and Smaller:

a. Material: Cast iron.

b. Coating: Tar or asphaltic compound; interior and exterior.

c. Type: Two piece; screw.

2. Lid Inscription: WATER.

2.3 FIRE HYDRANTS

A. Smart Fire Hydrant

1. Manufacturer:

a. Clow Valve Co., Model- iHydrant.

b. Substitutions: not permitted

2. Dry-Barrel, Breakaway Type:

a. Comply with AWWA C502.

b. Body: Ductile iron.

c. Valve: Compression type.

d. Burial Depth: As indicated on Drawings.

e. Inlet Connection Size: 6 inches.

f. Valve Opening: 5-1/4 inches in diameter.

g. End Connections: Mechanical joint.

h. Interior Coating: Comply with AWWA C550.

i. Opening Direction: Counterclockwise.

3. Hose Connections:

a. One pumper (4-1/2”) with Storz nozzle, two hose (2-1/2”) nozzles.

b. Obtain thread type and size from local fire department.

c. Attach nozzle caps by separate chains.

4. Finishes:

a. Hydrant upper barrel shall be factory coated with epoxy primer and polyurethane topcoating.

b. Color: Red.

Herbert, Rowland & Grubic, Inc. 33 14 19 - 4 009280.0426

5. Smart Hydrants will be procured and provided by the Owner, for installation by the Contractor.

B. Fire Hydrant

1. Manufacturers:

a. Mueller, Model: Super Centurion 250

b. Substitutions: not permitted

2. Dry-Barrel, Breakaway Type:

a. Comply with AWWA C502.

b. Body: Cast iron.

c. Valve: Compression type.

d. Burial Depth: As indicated on Drawings.

e. Inlet Connection Size: 6 inches.

f. Valve Opening: 5-1/4 inches in diameter.

g. End Connections: Mechanical joint.

h. Bolts and Nuts: Bronze.

i. Interior Coating: Comply with AWWA C550.

j. Opening Direction: Counterclockwise.

3. Hose Connections:

a. One pumper (4-1/2”) with Storz nozzle, two hose (2-1/2”) nozzles.

b. Obtain thread type and size from local fire department.

c. Attach nozzle caps by separate chains.

4. Finishes:

a. Hydrant upper barrel shall be factory coated with epoxy primer and polyurethane topcoating

b. Color: Red.

2.4 ACCESSORIES

A. Valve Box Aligner: High-strength plastic device designed to automatically center valve box base and to prevent it from shifting off center during backfilling.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 – Execution Requirements: Requirements for installation examination.

B. Determine exact location and size of valves from Drawings.

C. Identify required lines, levels, contours, and datum locations.

D. Verify that elevations of existing facilities prior to excavation and installation of valves and hydrants are as indicated on Drawings.

3.2 PREPARATION

A. Section 01 73 00 – Execution Requirements: Requirements for installation preparation.

Herbert, Rowland & Grubic, Inc. 33 14 19 - 5 009280.0426

B. Locate, identify, and protect from damage utilities to remain.

C. Do not interrupt existing utilities without permission and without making arrangements to provide temporary utility services.

1. Notify Owner and Engineer not less than 48 hours in advance of proposed utility interruption.

2. Do not proceed without written permission from Owner and Engineer.

3.3 INSTALLATION

A. Perform trench excavation, backfilling, and compaction as specified in Section 31 23 33 – Trenching and Backfilling for Utilities.

B. Install valves and hydrants in conjunction with pipe laying.

C. Provide buried valves with valve boxes installed flush with finished grade.

D. Orientation:

1. Set valves and hydrants plumb.

E. After main-line pressure testing, flush fire hydrants and check for proper drainage.

F. Disinfection of Water Piping System: Flush and disinfect valves and hydrants with water mains as specified in Section 33 13 00 – Disinfection of Water Utility Distribution.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 – Quality Requirements: Requirements for inspecting and testing.

B. Testing: Pressure test valves and hydrants with water mains as specified in Section 33 05

05.31 – Hydrostatic Testing.

END OF SECTION 33 14 19