32 91 13 - Soil Preparation.pdf
PDF 462 KB Posted
- Solicitation number
- Not on record
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a technical specification document for soil preparation work developed by Herbert, Rowland & Grubic, Inc. in coordination with the Elizabethtown Area Water Authority for the Water Main Replacement Project Phase 4. The specification outlines comprehensive soil preparation requirements including subsoil preparation, soil testing, and topsoil placement. Work activities encompass plowing hard pan or heavy shale to a minimum depth of 6 inches, loosening and grading through harrowing, discing, or dragging, hand raking to remove stones over 2 inches in diameter and debris, preparation of subsoil to eliminate uneven areas and low spots while maintaining proper lines and levels, removal of foreign materials and contaminated soil, and scarification of subsoil to 3 inches depth where topsoil is to be placed. All work must comply with PennDOT and Elizabethtown Area Water Authority standards.
The specification requires soil testing to analyze nitrogen, phosphorus, potash, soluble salt content, organic matter content, and pH value, with recommendations provided for fertilizer and lime application rates based on test results. Testing may be waived if recent test certificates are available for imported topsoil. The document references related sections including trenching and backfilling for utilities, landscape grading, seeding, and sodding work. No specific pricing, budget allocation, set-asides, or incumbents are detailed within this technical specification document, as it functions solely as an execution and product requirements guide for the soil preparation phase of the broader water main replacement project.
View the file
Other files
Show 40 more
Latest 50 of 91 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
32 91 13 – SOIL PREPARATION
Herbert, Rowland & Grubic, Inc. 32 91 13 - 1 009280.0426
SECTION 32 91 13 – SOIL PREPARATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Preparation of subsoil.
2. Soil testing.
3. Placing topsoil.
B. Related Sections:
1. Section 31 23 33 – Trenching and Backfilling for Utilities.
2. Section 32 91 19 – Landscape Grading.
3. Section 32 92 19 – Seeding.
4. Section 32 92 23 – Sodding.
1.2 SUBMITTALS
A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.
1.3 QUALITY ASSURANCE
A. Perform Work in accordance with PennDOT and Elizabethtown Area Water Authority standard.
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. Topsoil: As specified in Section 32 91 19 – Landscape Grading.
2.2 SOURCE QUALITY CONTROL
A. Section 01 40 00 – Quality Requirements: Testing, inspection and analysis requirements.
B. Analyze to ascertain percentage of nitrogen, phosphorus, potash, soluble salt content, organic matter content, and pH value.
C. Provide recommendation for fertilizer and lime application rates for specified seed mix as result of testing.
32 91 13 – SOIL PREPARATION
Herbert, Rowland & Grubic, Inc. 32 91 13 - 2 009280.0426
D. Testing is not required when recent tests and certificates are available for imported topsoil. Submit these test results to testing laboratory. Indicate, by test results, information necessary to determine suitability.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 – Execution Requirements: Verification of existing conditions before starting work.
B. Verify prepared soil base is ready to receive the Work of this section.
3.2 PREPARATION OF SUBGRADE
A. "Hard pan" or heavy shale:
1. Plow to a minimum depth of 6".
2. Loosen and grade by harrowing, discing, or dragging.
3. Hand rake subgrade. Remove stones over 2" in diameter and other debris.
B. Loose loam, sandy loam, or light clay.
1. Loosen and grade by harrowing, discing, or dragging.
2. Hand rake subgrade. Remove rocks over 2" in diameter and other debris.
3.3 PREPARATION OF SUBSOIL
A. Prepare sub-soil to eliminate uneven areas and low spots. Maintain lines, levels, profiles and contours. Make changes in grade gradual. Blend slopes into level areas.
B. Remove foreign materials, weeds and undesirable plants and their roots. Remove contaminated sub-soil.
C. Scarify subsoil to depth of 3 inches where topsoil is to be placed. Repeat cultivation in areas where equipment, used for hauling and spreading topsoil, has compacted sub-soil.
3.4 PLACING TOPSOIL
A. Section 32 91 19 – Landscape Grading: Placing Topsoil
END OF SECTION 32 91 13