About this file

This is a technical specification document for soil preparation work developed by Herbert, Rowland & Grubic, Inc. in coordination with the Elizabethtown Area Water Authority for the Water Main Replacement Project Phase 4. The specification outlines comprehensive soil preparation requirements including subsoil preparation, soil testing, and topsoil placement. Work activities encompass plowing hard pan or heavy shale to a minimum depth of 6 inches, loosening and grading through harrowing, discing, or dragging, hand raking to remove stones over 2 inches in diameter and debris, preparation of subsoil to eliminate uneven areas and low spots while maintaining proper lines and levels, removal of foreign materials and contaminated soil, and scarification of subsoil to 3 inches depth where topsoil is to be placed. All work must comply with PennDOT and Elizabethtown Area Water Authority standards.

The specification requires soil testing to analyze nitrogen, phosphorus, potash, soluble salt content, organic matter content, and pH value, with recommendations provided for fertilizer and lime application rates based on test results. Testing may be waived if recent test certificates are available for imported topsoil. The document references related sections including trenching and backfilling for utilities, landscape grading, seeding, and sodding work. No specific pricing, budget allocation, set-asides, or incumbents are detailed within this technical specification document, as it functions solely as an execution and product requirements guide for the soil preparation phase of the broader water main replacement project.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

32 91 13 – SOIL PREPARATION

Herbert, Rowland & Grubic, Inc. 32 91 13 - 1 009280.0426

SECTION 32 91 13 – SOIL PREPARATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Preparation of subsoil.

2. Soil testing.

3. Placing topsoil.

B. Related Sections:

1. Section 31 23 33 – Trenching and Backfilling for Utilities.

2. Section 32 91 19 – Landscape Grading.

3. Section 32 92 19 – Seeding.

4. Section 32 92 23 – Sodding.

1.2 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

1.3 QUALITY ASSURANCE

A. Perform Work in accordance with PennDOT and Elizabethtown Area Water Authority standard.

PART 2 - PRODUCTS

2.1 SOIL MATERIALS

A. Topsoil: As specified in Section 32 91 19 – Landscape Grading.

2.2 SOURCE QUALITY CONTROL

A. Section 01 40 00 – Quality Requirements: Testing, inspection and analysis requirements.

B. Analyze to ascertain percentage of nitrogen, phosphorus, potash, soluble salt content, organic matter content, and pH value.

C. Provide recommendation for fertilizer and lime application rates for specified seed mix as result of testing.

32 91 13 – SOIL PREPARATION

Herbert, Rowland & Grubic, Inc. 32 91 13 - 2 009280.0426

D. Testing is not required when recent tests and certificates are available for imported topsoil. Submit these test results to testing laboratory. Indicate, by test results, information necessary to determine suitability.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 – Execution Requirements: Verification of existing conditions before starting work.

B. Verify prepared soil base is ready to receive the Work of this section.

3.2 PREPARATION OF SUBGRADE

A. "Hard pan" or heavy shale:

1. Plow to a minimum depth of 6".

2. Loosen and grade by harrowing, discing, or dragging.

3. Hand rake subgrade. Remove stones over 2" in diameter and other debris.

B. Loose loam, sandy loam, or light clay.

1. Loosen and grade by harrowing, discing, or dragging.

2. Hand rake subgrade. Remove rocks over 2" in diameter and other debris.

3.3 PREPARATION OF SUBSOIL

A. Prepare sub-soil to eliminate uneven areas and low spots. Maintain lines, levels, profiles and contours. Make changes in grade gradual. Blend slopes into level areas.

B. Remove foreign materials, weeds and undesirable plants and their roots. Remove contaminated sub-soil.

C. Scarify subsoil to depth of 3 inches where topsoil is to be placed. Repeat cultivation in areas where equipment, used for hauling and spreading topsoil, has compacted sub-soil.

3.4 PLACING TOPSOIL

A. Section 32 91 19 – Landscape Grading: Placing Topsoil

END OF SECTION 32 91 13