01 50 00 - Temporary Facilities and Controls.pdf
PDF 477 KB Posted
- Solicitation number
- Not on record
- Issued by
- Lancaster County, Pennsylvania
About this file
This document is a Temporary Facilities and Controls specification section (01 50 00) prepared by Herbert, Rowland & Grubic, Inc. for the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4). The specification outlines the contractor's responsibilities for establishing and maintaining temporary infrastructure during construction, including temporary utilities (electricity, water service, and sanitary facilities), construction facilities (field offices, vehicular access, and waste removal), and temporary controls (erosion and sediment management). The project involves relocation of approximately 13,860 feet of 4-inch, 6-inch, and 8-inch ductile iron pipe water main with replacement using new 12-inch DIP, replacement of approximately fifteen fire hydrants, and transfer of approximately 180 existing water services. Bids were to be received online until Thursday, August 6, 2026, at 10:00 AM local time, with public opening and reading of bids immediately following. All bidding documents are available through the designated website at https://pennbid.bonfirehub.com/.
The specification requires contractors to provide temporary facilities at their own expense, including field offices, storage sheds, access roads, sanitary facilities, electrical distribution systems, telephone and internet service, fire protection equipment, and erosion control measures. The Owner will furnish water for the initial hydrostatic test and disinfection procedures, with contractors responsible for costs of any required retesting. Contractors must maintain the site in a clean and orderly condition, remove all temporary utilities, equipment, and facilities before final payment, and restore any existing or permanent facilities to their original condition. The specification references ASTM International standards for fire testing and sound transmission and requires compliance with all applicable laws and regulations regarding material storage and waste management.
View the file
Other files
Show 40 more
Latest 50 of 91 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 50 00 – TEMPORARY FACILITIES AND CONTROLS
Herbert, Rowland & Grubic, Inc. 01 50 00 - 1 009280.0426
SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Temporary facilities under Construction Management Agreement.
B. Temporary Utilities:
1. Temporary electricity.
2. Temporary water service.
3. Temporary sanitary facilities.
C. Construction Facilities:
1. Field offices and sheds.
2. Vehicular access.
3. Progress cleaning and waste removal.
4. Fire-prevention facilities.
D. Temporary Controls:
1. Erosion and sediment control.
E. Removal of utilities, facilities, and controls.
1.2 REFERENCES
A. ASTM International:
1. ASTM E 84 - Standard Test Method for Surface Burning Characteristics of Building Materials.
2. ASTM E 90 - Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements.
3. ASTM E 119 - Standard Test Methods for Fire Tests of Building Construction and Materials.
1.3 CONTRACTOR USE OF PREMISES
A. Contractor’s use of the site shall at all times be coordinated with the Owner so as to
Herbert, Rowland & Grubic, Inc. 01 50 00 - 2 009280.0426 ensure continuous operation.
B. Contractors shall not be provided space in any of the existing buildings, except as required, to accomplish the Work of the Contracts.
C. Contractor shall take all precautions to minimize dust, dirt, and debris while working in the areas indicated on the Contract Drawings. Provide polyethylene curtains or other barriers over opening between new work and existing work areas as required. Clean and remove debris daily before leaving work site.
1.4 TEMPORARY FACILITIES
A. Temporary Provisions Provided by Contractor:
1. Temporary barriers, barricades, covered walkways, fencing, exterior closures, and interior closures.
2. Temporary field offices.
3. Cleaning during construction.
4. Access roads and approaches.
5. Temporary sanitary facilities.
6. Temporary heating and ventilating after enclosure.
7. Temporary electrical service and distribution system for power and lighting.
8. Temporary telephone and internet service.
B. Each Contractor: Coordinate provisions with Engineer or Owner and provide the following items as necessary for execution of the Work including associated costs:
1. Construction aids.
2. Temporary fire protection, dust control, erosion and sediment control, water control, noise control, and other necessary temporary controls.
3. Temporary barriers, barricades, and similar devices as necessary for safety and protection of construction personnel and public.
4. On Owner’s approval, may provide temporary field office including electrical service and temporary telephone.
5. Temporary tree and plant protection.
6. Temporary heating before building enclosure.
Herbert, Rowland & Grubic, Inc. 01 50 00 - 3 009280.0426
7. Electrical service required in addition to temporary service and distribution provided by herein.
8. Temporary provisions for protection of installed Work.
1.5 TEMPORARY WATER SERVICE
A. Water shall be furnished by the Owner for the first hydrostatic test and disinfection procedure in each section. If pipeline must be retested and disinfected, the contractor shall pay for additional water at a cost rate determined by the owner.
1.6 TEMPORARY SANITARY FACILITIES
A. Each Contractor shall provide and maintain required facilities and enclosures. Existing facility use is not permitted. Provide facilities at time of Project mobilization.
1.7 FIELD OFFICES AND SHEDS
A. Field Office: Prefabricated Mobile Units with lockable entrances, operable windows, and serviceable finishes; heated and air conditioned; on foundation adequate for normal loading with steps and landings at entrance doors.
B. Storage Areas and Sheds: Size to storage requirements for products of individual Sections, allowing for access and orderly provision for maintenance and inspection of products to suit requirements in Section 01 61 00 – Product Requirements.
C. Storage of materials shall comply with all applicable Laws and Regulations.
1.8 VEHICULAR ACCESS
A. Provide unimpeded access for emergency vehicles. Maintain 20-foot-wide driveways with turning space between and around combustible materials.
B. Provide and maintain access to fire hydrants and control valves free of obstructions.
C. Provide means of removing mud from vehicle wheels before entering streets.
1.9 PROGRESS CLEANING AND WASTE REMOVAL
A. Maintain areas free of waste materials, debris, and rubbish. Maintain Site in clean and orderly condition.
B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, before enclosing spaces.
C. Broom and vacuum clean interior areas before starting surface finishing, and continue cleaning to eliminate dust.
D. Collect and remove waste materials, debris, and rubbish from Site periodically and
Herbert, Rowland & Grubic, Inc. 01 50 00 - 4 009280.0426 dispose of off-Site. Comply with Section 01 74 19 – Construction Waste Management and Disposal.
E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
1.10 FIRE-PREVENTION FACILITIES
A. Portable Fire Extinguishers: NFPA 10; 10-pound capacity, 4A-60B: C UL rating.
1. Provide minimum of one fire extinguisher in every construction trailer and storage shed.
1.11 EROSION AND SEDIMENT CONTROL
A. Plan and execute construction by methods to control surface drainage from cuts and fills from borrow and waste disposal areas. Prevent erosion and sedimentation.
B. Minimize surface area of bare soil exposed at one time.
C. Provide temporary measures including berms, dikes, drains, and other devices to prevent water flow.
D. Construct fill and waste areas by selective placement to avoid erosive surface silts and clays.
E. Periodically inspect earthwork to detect evidence of erosion and sedimentation. Promptly apply corrective measures.
F. Comply with sediment and erosion control plan indicated on Drawings.
1.12 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS
A. Remove temporary utilities, equipment, facilities, and materials before Final Application for Payment inspection.
B. Clean and repair damage caused by installation or use of temporary Work.
C. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.
PART 2 - PRODUCTS - Not Used
PART 3 - EXECUTION - Not Used
END OF SECTION 01 50 00