This is a permit requirements specification document prepared by Herbert, Rowland & Grubic, Inc. for the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4) in West Donegal Township, Pennsylvania. The document establishes permit compliance requirements for the contractor executing the water main replacement work, which includes the relocation of approximately 13,860 feet of 4-inch, 6-inch, and 8-inch ductile iron pipe (DIP) water main with replacement using new 12-inch DIP, replacement of approximately fifteen fire hydrants, and transfer of approximately 180 existing water services. Bids for this project were received online until Thursday, August 6, 2026, at 10:00 AM local time, with public bid opening immediately following. The contract is structured as a single Prime Contract for General Construction, with all bidding documents available through the designated PennBid website at https://pennbid.bonfirehub.com/.

The specification document outlines that the contractor bears full responsibility for obtaining a street opening permit from West Donegal Township prior to commencing work. The contractor must submit copies of all inspection reports, certifications, correspondence, and compliance documentation to the owner's records as evidence of permit compliance and adherence to applicable standards and regulations. This requirement ensures that all street-related work activities comply with local township regulations and that proper authorization is obtained before any street opening or disturbance occurs as part of the water main replacement operations.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 41 26 – PERMIT REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 01 41 26 - 1 009280.0426

SECTION 01 41 26 – PERMIT REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Street Opening Permit

1.2 SUBMITTALS

A. Permits and Certificates: For Owner's records, submit copies of inspection reports, certifications, correspondence, records, and similar documents, established for compliance with standards and regulations required by permits for the project.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION

3.1 STREET OPENING PERMIT

A. The Contractor shall be responsible for obtaining a street opening permit from West Donegal Township.

END OF SECTION 01 41 26