00 73 43 - Wage Rate Requirements.pdf

PDF 709 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a Wage Rate Requirements specification document applicable to the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4) in Pennsylvania, which is subject to the Pennsylvania Prevailing Wage Act (Act No. 442 of 1961, as amended). The document outlines mandatory compliance requirements for all contractors and subcontractors performing work on this public works project, including the relocation of approximately 13,860 feet of water main, replacement of fifteen fire hydrants, and transfer of approximately 180 existing water services. The project's bid deadline is Thursday, August 6, 2026, at 10:00 AM local time, with bids received online through https://pennbid.bonfirehub.com/. The specification establishes that all workmen must be paid prevailing wage rates as determined by the Pennsylvania Secretary of Labor and Industry, with no specific contract term renewal options identified in the wage requirements document.

Contractors and subcontractors are required to maintain accurate payroll records for two years, post prevailing wage rates prominently at the job site, and file weekly certified payroll statements under oath documenting compliance with wage standards. The document mandates that workers be paid not less than the minimum wage rates including employee benefits established by the Secretary of Labor and Industry, with workers retaining civil rights of action for any underpayment with a six-month statute of limitations. Contractors must file statements at project completion detailing any unpaid wages and make employees available for interviews by the Owner or Secretary regarding wage compliance. The specification references related documents including the General Conditions (Section 00 72 00) and the Wage Determination Schedule (Section 00 73 46), and requires use of the Pennsylvania Department of Labor and Industry "Weekly Payroll Certification for Public Works Projects" Form LLC-25 (rev 10/03) for compliance documentation.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 73 43 – WAGE RATE REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 00 73 43 - 1 009280.0426

SECTION 00 73 43 – WAGE RATE REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Duties and requirements of Contractor under Pennsylvania Prevailing Wage Act.

1.2 RELATED SECTIONS

A. Document 00 72 00 – General Conditions

B. Document 00 73 46– Wage Determination Schedule

1.3 DUTIES AND REQUIREMENTS

A. Contained with Section 00 72 00 are references to Laws and Regulations. The Pennsylvania Prevailing Wage Act (Act No. 442 - Session of 1961, as amended) shall apply to this Project. Contractor is responsible for compliance with the law, including the following specific requirements:

1. All workmen employed by this Project shall be paid not less than the minimum wage rates, including employee benefits, which have been determined by the Secretary of Labor and Industry.

2. Each Contractor and Subcontractor shall keep an accurate record showing the name, craft and the actual hourly rate of wage paid to each workman employed by him in connection with this public Work. This record shall be preserved for two years from date of Project. This record shall be open to the inspection of the Owner, or representative thereof, and to the Secretary of Labor and Industry.

3. Contractor and Subcontractors shall post for the entire period of construction the general prevailing minimum wages for each craft and classification involved, as determined by the Secretary of Labor and Industry, and in a prominent and easily accessible place at the Site of the Work. At a minimum, the posted notice of wage rates must contain the following information:

a. Name of Project.

b. Name of public body for which it is being constructed.

c. The crafts and classifications of workmen listed in the Secretary's general prevailing minimum wage rate determination for the particular Project.

d. The general prevailing minimum wage rates determined for each craft and classification and the effective date of any changes.

e. A statement advising workmen that if they have been paid less than the general prevailing minimum wage rate for their job classification or that the Contractor and/or Subcontractor are not complying with the Act or these Regulations in any manner whatsoever, they may file a protest with the Secretary of Labor and Industry. Any workmen paid less than the rate specified shall have a civil right of action for the difference between the wage paid and the wages stipulated, which right of action must be

00 73 43 – WAGE RATE REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 00 73 43 - 2 009280.0426 exercised within six months from the occurrence of the event creating such right.

4. At the completion of the Work and as a prerequisite for acceptance by the Owner, each Contractor and Subcontractor shall file statements with the Owner of the names and amounts of unpaid wages.

5. Each Contractor and each Subcontractor shall file a statement each week under oath and in form satisfactory to the Secretary certifying that all workmen have been paid wages in strict conformity with the provisions, if any wages remain unpaid, to set forth the amount of wages due and owing to each workman respectively.

6. Contractor and Subcontractors shall make employees available for interviews by the Owner or representative thereof or to the Secretary on a reasonable basis.

Interviews shall be limited to the employee's name, address, dates worked on the Project, hourly rate, job classification, duties, tools and equipment utilized and comments regarding compliance with the labor standards.

B. Attached to this Section are the forms to be used for weekly payroll certifications:

1. Pennsylvania Department of Labor and Industry “WEEKLY PAYROLL

CERTIFICATION FOR PUBLIC WORKS PROJECTS” Form LLC-25, rev 10/03.

END OF SECTION 00 73 43

File details come from the government source that posted it. Updated .