This is a specification document for Subsurface Utility Engineering (SUE) services prepared by Herbert, Rowland & Grubic, Inc. for the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4). The contractor must furnish all labor, materials, equipment, and services necessary to perform comprehensive utility investigations on approximately 13,860 feet of water main relocation involving 4-inch, 6-inch, and 8-inch ductile iron pipe replacement with new 12-inch DIP, the replacement of approximately fifteen fire hydrants, and the transfer of approximately 180 existing water services. Work scope includes Quality Level B designation of existing water facilities using geophysical methods, field marking of designated utilities, utility mapping and documentation, survey and preparation of updated utility base mapping, Quality Level A vacuum excavation when directed by the Engineer, and preparation of utility investigation reports. All utility investigation activities must be completed and accepted by the Engineer prior to commencement of construction operations. Online bids are due Thursday, August 6, 2026 at 10:00 AM local time, with public bid opening immediately following. Bidding documents are available through https://pennbid.bonfirehub.com/.
All utility investigations shall be performed in accordance with ASCE/UESI 38-22, Investigating and Documenting Existing Utilities, and the APWA Uniform Color Code for Utility Identification. Utility investigation personnel must demonstrate experience performing ASCE 38 utility investigations, and designation technicians must be experienced in geophysical utility locating methods. Survey activities shall be performed under the responsible charge of a Professional Land Surveyor licensed in the Commonwealth of Pennsylvania. Required deliverables include updated AutoCAD utility base mapping compatible with contract documents, PDF utility plans, utility investigation reports, utility quality-level maps, field markup sketches, Quality Level A test-hole logs if performed, and photographs of Quality Level A investigations. The specification permits use of electromagnetic locators, pipe and cable locating equipment, Ground Penetrating Radar, GPS equipment, total stations, and vacuum or hydro-vac excavation equipment. Contractors must document utility segments that cannot be designated with reasonable confidence and identify potential causes such as non-conductive pipe materials, utility congestion, depth limitations, surface obstructions, and equipment limitations. No construction operations, excavation, trenching, water main installation, or directional drilling may commence until Quality Level B investigations are completed, findings are mapped, required deliverables are submitted, any Engineer-directed Quality Level A investigations are completed, and the Engineer accepts the updated utility base map.
View the file
Other files
Show 40 more
Latest 50 of 91 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
02 31 00 – SUBSURFACE UTILITY ENGINEERING
Herbert, Rowland & Grubic, Inc. 02 82 33 - 1 009280.0426
SECTION 02 31 00 – SUBSURFACE UTILITY ENGINEERING
PART 1 – GENERAL
1.01 SUMMARY
A. Furnish all labor, materials, equipment, and services necessary to perform Subsurface
Utility Engineering (SUE) services within the limits of construction.
B. Work includes:
1. Quality Level B designation of existing water facilities.
2. Field marking of designated water facilities.
3. Utility mapping and documentation.
4. Survey and preparation of updated utility base mapping.
5. Quality Level A vacuum excavation when directed by the Engineer.
6. Preparation of utility investigation reports and deliverables.
7. All utility investigations shall be performed in accordance with ASCE/UESI 38-22, Investigating and Documenting Existing Utilities.
8. All utility investigation activities and deliverables shall be completed and accepted by the Engineer prior to the commencement of construction operations.
1.02 REFERENCES
A. ASCE/UESI 38-22 – Investigating and Documenting Existing Utilities.
B. APWA Uniform Color Code for Utility Identification.
C. Pennsylvania One Call System Requirements.
1.03 DEFINITIONS
A. Quality Level B (QL-B)
1. Information obtained through interpretation of utility designating methods using surface geophysical techniques.
B. Quality Level A (QL-A)
1. Information obtained through direct exposure and precise measurement of utility facilities using vacuum excavation or other nondestructive methods.
C. Designation
1. The process of using geophysical methods to determine and mark the horizontal position of subsurface utilities.
D. Test Hole
1. A vacuum excavation performed to expose and verify the location of a utility.
1.04 SUBMITTALS
Herbert, Rowland & Grubic, Inc. 02 82 33 - 2 009280.0426
A. Submit the following:
1. Utility Investigation Work Plan.
2. Utility Investigation Report.
B. Updated AutoCAD Utility Base Mapping.
C. PDF Utility Plans.
D. Utility Quality Level Map.
E. Field Markup Sketches.
F. Quality Level A Test Hole Logs, if performed.
G. Photographs of Quality Level A investigations, if performed.
1.05 QUALIFICATIONS
A. Utility investigation personnel shall have demonstrated experience performing ASCE 38 utility investigations.
B. Utility designation technicians shall be experienced in geophysical utility locating methods.
C. Survey activities shall be performed under the responsible charge of a Professional Land Surveyor licensed in the Commonwealth of Pennsylvania.
1.06 PROJECT REQUIREMENTS
A. Perform Quality Level B investigation of all existing water facilities within the project limits
B. Facilities to be investigated shall include:
1. Water mains.
2. Water service laterals.
3. Fire hydrant branches.
4. Gate valves.
5. Butterfly valves.
6. Valve boxes.
7. Associated water system appurtenances.
C. Water service laterals shall be designated from the water main toward the served property to the maximum extent reasonably achievable using surface geophysical methods.
D. Utility investigations shall be completed prior to the start of construction.
PART 2 – PRODUCTS
2.01 EQUIPMENT
A. Geophysical Designation Equipment
1. Electromagnetic utility locators.
Herbert, Rowland & Grubic, Inc. 02 82 33 - 3 009280.0426
2. Pipe and cable locating equipment.
3. Ground Penetrating Radar (GPR).
4. Transmitters and sondes.
5. Other approved utility locating equipment.
a) GPR may be used as a targeted investigation tool where beneficial to supplement other utility locating methods.
B. Survey Equipment
1. GPS equipment.
2. Total stations.
3. Data collectors.
C. Quality Level A Equipment
1. Vacuum excavation equipment.
2. Hydro-vac equipment.
3. Air-vac equipment.
2.02 MAPPING STANDARDS
A. Utility mapping shall be tied to project horizontal and vertical control.
B. Mapping shall be suitable for engineering design and construction planning purposes.
C. Mapping shall clearly distinguish:
1. Existing mapping information.
2. Field-designated utility alignments.
3. Quality Level A verified utility locations.
4. Areas of uncertainty.
D. All utility segments shown on the mapping shall be assigned and labeled with the applicable ASCE 38-22 Quality Level designation.
PART 3 – EXECUTION
3.01 GENERAL
A. Perform all utility investigations in accordance with ASCE/UESI 38-22.
B. Complete all required utility investigations prior to commencement of construction activities.
C. Construction operations shall not begin until the Engineer has reviewed and accepted the utility investigation deliverables.
3.02 QUALITY LEVEL B DESIGNATION
A. Designate the horizontal alignment of existing water facilities throughout the project limits.
B. Designation shall include:
1. Water mains.
2. Water service laterals.
3. Hydrant branches.
Herbert, Rowland & Grubic, Inc. 02 82 33 - 4 009280.0426
4. Valves.
5. Valve boxes.
6. Water system appurtenances.
C. Employ all reasonable geophysical methods necessary to accurately determine utility alignments.
D. Mark designated utilities in the field using paint, flags, or other highly visible marking methods.
E. Maintain markings until surveyed and documented.
3.03 SURVEY AND MAPPING
A. Survey all designated utility markings.
B. Mapping shall depict, where identifiable:
1. Utility alignment.
2. Changes in direction.
3. Tees.
4. Crosses.
5. Valves.
6. Hydrants.
7. Service laterals.
8. Associated appurtenances.
C. Incorporate all findings into the project base map.
D. Updated base mapping shall be submitted in AutoCAD format compatible with the Contract Documents.
E. PDF utility plans shall also be provided
3.04 UTILITY UNCERTAINTY DOCUMENTATION
A. The Contractor shall document utility segments that cannot be designated with reasonable confidence.
B. Areas of uncertainty shall be clearly depicted on the utility mapping.
C. Utility segments that cannot be confidently designated shall be identified and assigned the appropriate lesser Quality Level in accordance with ASCE 38-22.
D. The investigation report shall describe the reasons utility locations could not be reliably established.
E. Potential causes may include:
1. Non-conductive pipe materials.
2. Utility congestion.
3. Depth limitations.
4. Surface obstructions.
5. Soil conditions.
6. Equipment limitations.
Herbert, Rowland & Grubic, Inc. 02 82 33 - 5 009280.0426
3.05 QUALITY LEVEL A VACUUM EXCAVATION
A. Quality Level A investigations shall be performed only when directed by the Engineer.
B. The Engineer may direct vacuum excavation where:
1. Utility alignments are uncertain.
2. Utility crossings exist.
3. Potential conflicts are present.
4. Additional utility information is necessary to support construction planning.
C. Expose utilities using nondestructive vacuum excavation methods.
D. Record and document:
1. Horizontal location.
2. Vertical elevation.
3. Utility size.
4. Utility material.
5. Utility type.
6. Depth of cover.
E. Photograph exposed facilities.
F. Restore disturbed surfaces upon completion of investigations.
3.06 REPORTING
A. Provide a Utility Investigation Report including:
1. Summary of investigation activities.
2. Utility locating methods utilized.
3. Areas investigated.
4. Utility Quality Level assignments.
5. Utility uncertainty documentation.
6. Quality Level A findings, if performed.
7. Recommendations for additional investigation, if warranted.
3.07 DELIVERABLES
A. Provide:
1. Updated AutoCAD utility base map.
2. PDF utility plans.
3. Utility investigation report.
4. Utility quality-level map.
Herbert, Rowland & Grubic, Inc. 02 82 33 - 6 009280.0426
5. Field markup sketches.
6. Quality Level A test-hole logs, if performed.
7. Quality Level A photographs, if performed.
3.08 PRECONSTRUCTION ACCEPTANCE
A. Completion of utility investigation activities shall be a prerequisite to the commencement of construction.
B. No excavation, trenching, water main installation, directional drilling, or related construction activities shall begin until:
1. Quality Level B investigations have been completed.
2. Utility findings have been mapped.
3. Required deliverables have been submitted.
4. Any Engineer-directed Quality Level A investigations have been completed.
5. The Engineer has accepted the updated utility base map.
END OF SECTION 02 31 00