00 65 19.16 - Affidavit of Release of Liens.pdf

PDF 545 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a Contractor's Affidavit of Release of Liens submitted by Herbert, Rowland & Grubic, Inc. to the Elizabethtown Area Water Authority for the Water Main Replacement Project Phase 4 (Contract No. WR-4). The affidavit certifies that all labor, materials, equipment, and outstanding claims arising from the contractor's performance have been paid and satisfied in full, with no remaining obligations or claims for which the owner might be liable. The document is executed under oath by an authorized representative of the contractor with personal knowledge of the facts stated and requires notarization.

This affidavit serves as a lien release document required as part of the project completion and payment process. It provides legal assurance to the Elizabethtown Area Water Authority that the contractor has resolved all financial obligations related to the project and that no mechanic's liens or other claims will be filed against the project. The affidavit references the Water Main Replacement Project Phase 4, which involves relocation of approximately 13,860 feet of DIP water main, replacement of fifteen fire hydrants, and transfer of approximately 180 existing water services to new 12-inch DIP water main infrastructure.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Herbert, Rowland & Grubic, Inc. 00 65 19.16 - 1 009280.0426

CONTRACTOR’S AFFIDAVIT OF RELEASE OF LIENS

To Owner: Elizabethtown Area Water Authority Owner's Contract No.: WR-4 From Contractor: Contract Name:

Project: Water Main Replacement Project Phase 4 Contract Date:

Commonwealth of:

County of:

The undersigned, being duly sworn according to law, deposes and certifies that the cost of all labor, material, and equipment and outstanding claims and indebtedness of whatever nature arising out of the performance in

County, have been paid and satisfied in full as of (County) (State) (Date) and that there are no outstanding obligations or claims of any kind for the payment of which the Owner on the above named project might be liable, or subject to, in any lawful proceeding or in equity.

The undersigned is authorized by Contractor to execute this document on Contractor’s behalf and has personal knowledge of the facts state herein.

This day of , 20

Contractor:

By:

(Authorized signature)

(printed name)

Title:

Subscribed and sworn to me this date:

Notary Public:

(signature)

(printed name)

Commission Expires: