About this file

This is a construction specification document for Section 01 74 19 - Construction Waste Management and Disposal, prepared by Herbert, Rowland & Grubic, Inc., applicable to the Water Main Replacement Project Phase 4 (Contract No. WR-4) being procured by the Elizabethtown Area Water Authority in Pennsylvania. The specification establishes requirements for the contractor to manage, salvage, recycle, and dispose of nonhazardous demolition and construction waste generated during the project. The contractor must implement an approved waste management plan that includes proper handling, containerization, storage, signage, transportation, worker training, and compliance with all applicable hauling and disposal regulations. Salvaged items designated for owner use must be cleaned, crated, labeled with contents and removal information, and stored securely until delivery to the owner's designated storage area. Recyclable waste materials must be separated by type at the project site to the maximum extent practicable, maintained free of contaminants, stockpiled separately without intermixing, and transported to licensed recycling or processing facilities. All remaining waste materials must be legally disposed of in licensed landfills or incinerators acceptable to authorities having jurisdiction, with removal and transportation conducted to prevent spillage on adjacent areas. Burning of waste materials is prohibited.

The specification indicates that revenues, savings, rebates, tax credits, and other incentives received from recycling waste materials accrue to the contractor. The contractor bears responsibility for maintaining detailed records of all waste disposition, including manifests, weight tickets, receipts, and invoices from recycling facilities, landfills, and incinerators, which must be submitted as required by the project's submittal procedures outlined in Section 01 33 00. The contractor must conduct all waste management operations in compliance with Section 01 50 00 - Temporary Facilities and Controls to minimize interference with adjacent roads, streets, and occupied facilities while controlling dust, dirt, and noise. No specific budget allocation for waste management is provided in this specification section.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

Herbert, Rowland & Grubic, Inc. 01 74 19 - 1 009280.0426

SECTION 01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Salvaging nonhazardous demolition waste

2. Disposing of nonhazardous demolition and construction waste.

1.2 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures contains requirements for submittals.

B. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.

C. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.

1.3 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with hauling and disposal regulations of Authorities having Jurisdiction.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION

3.1 PLAN IMPLEMENTATION

A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.

1. Comply with operation, termination, and removal requirements in Section 01 50

00 – Temporary Facilities and Controls.

B. Training: Train workers, Subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at the Project Site.

C. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Comply with Section 01 50 00 – Temporary Facilities and Controls for controlling dust and dirt, environmental protection, and noise control.

Herbert, Rowland & Grubic, Inc. 01 74 19 - 2 009280.0426

3.2 SALVAGING DEMOLITION WASTE

A. Salvaged Items for Sale: Not permitted on Project Site.

B. Salvaged Items for Owner’s use: Salvage Items for Owner’s use and handle as follows:

1. Clean Salvaged Items

2. Pack or crate items after cleaning. Identify contents of containers with label indicating elements, date of removal, quantity, and location where removed.

3. Store items in a secure area until delivery to Owner.

4. Transport items to Owner's storage area designated by Owner.

5. Protect items from damage during transport and storage.

C. Equipment: Drain tanks, piping, and fixtures. Seal Openings with caps or plugs. Protect

Equipment from exposure to weather.

3.3 RECYCLYING DEMOLITION WASTE, GENERAL

A. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Contractor.

B. Preparation of Waste: Prepare and maintain recyclable waste materials according to recycling or reuse facility requirements. Maintain materials free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process.

C. Procedures: Separate recyclable waste from other waste materials, trash, and debris.

Separate recyclable waste by type at Project Site to the maximum extent practical according to approved construction waste management plan.

1. Provide appropriately marked containers or bins for controlling recyclable waste until removed from Project Site. Include list of acceptable and unacceptable materials at each container and bin.

a. Inspect containers and bins for contamination and remove contaminated materials if found.

2. Stockpile processed materials on-site without intermixing with other materials.

3. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

4. Stockpile materials away from construction area. Do not store within drip line of remaining trees.

5. Store components off the ground and protect from the weather.

Herbert, Rowland & Grubic, Inc. 01 74 19 - 3 009280.0426

6. Remove recyclable waste from Owner's property and transport to recycling receiver or processor.

3.4 DISPOSAL OF WASTE

A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project Site and legally dispose of them in a landfill or incinerator acceptable to Authorities having Jurisdiction.

1. Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn waste materials.

C. Disposal: Remove waste materials from Owner's property and legally dispose of them.

END OF SECTION 01 74 19