33 14 17 - Site Water Service Utility Laterals.pdf

PDF 489 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

File Summary: Site Water Service Utility Laterals Specification

This specification document establishes the technical requirements for the installation of site water service utility laterals for the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4). The project encompasses the transfer of approximately 180 existing water services from existing 4-inch, 6-inch, and 8-inch ductile iron pipe (DIP) water mains to a new 12-inch DIP water main, covering approximately 13,860 feet of relocation work. The specification details the materials, products, and installation procedures for 2-inch water service connections, including copper tubing (Type K, annealed), corporation stop assemblies, curb stop assemblies with cast iron boxes and covers, trenching, bedding, and backfill requirements. Key installation requirements include proper spacing of corporation stops at least 12 inches apart, location of curb stops no more than 18 inches behind the curb face, use of continuous pipe runs with no joint connections from curb box to corporation fitting, minimum 4 feet of ground cover for frost protection, and mandatory inspection of service lines prior to backfilling. All piping must be pressure tested according to hydrostatic testing standards, flushed, and disinfected before acceptance. Bids are due online by Thursday, August 6, 2026, at 10:00 AM local time through https://pennbid.bonfirehub.com/, with public bid opening immediately following.

The specification requires compliance with multiple industry standards including ASTM B88 for copper tubing, ASTM B62 for bronze castings, ASME B16.18 for solder joint fittings, and AWWA C800 for underground service line valves and fittings. Acceptable manufacturers for corporation stops include Mueller 110 and Ford F1000-3Q models, while curb stop assemblies must be Mueller 110 or Ford B44-333Q models, with all products requiring engineer approval. Curb boxes and covers must be supplied by Opelika B & T, Tyler Union, or approved equivalents, featuring cast iron construction with tar or asphaltic coating and pentagonal plugs. The specification explicitly prohibits lead-containing fittings in contact with water and requires dielectric couplings for all copper-to-non-copper connections. Lines larger than 2 inches require chlorine tablets to be placed in the pipe prior to installation. All service lines must remain uncovered until pressure testing is completed and approved by the Engineer before backfilling. No specific budget range, set-asides, or incumbent contractors are identified in the specification document.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 14 17 – SITE WATER SERVICE UTILITY LATERALS

Herbert, Rowland & Grubic, Inc. 33 14 17 - 1 009280.0426

SECTION 33 14 17 – SITE WATER SERVICE UTILITY LATERALS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Pipe and fittings for 2-inch water service connections to buildings.

2. Corporation stop assemblies.

3. Curb stop assemblies.

4. Trenching, bedding, and cover.

B. Related Requirements:

1. Section 33 13 00 – Disinfection of Water Utility Distribution: Flushing and disinfecting of water system.

1.2 REFERENCE STANDARDS

A. American Society of Mechanical Engineers:

1. ASME B16.18 - Cast Copper Alloy Solder Joint Pressure Fittings.

B. ASTM International:

1. ASTM B62 - Standard Specification for Composition Bronze or Ounce Metal

Castings.

2. ASTM B88 - Standard Specification for Seamless Copper Water Tube.

C. American Water Works Association:

1. AWWA C800 - Underground Service Line Valves and Fittings.

1.3 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Product Data: Submit manufacturer information regarding pipe materials, pipe fittings, corporation stop assemblies, curb stop assemblies, service saddles, and accessories.

1.4 CLOSEOUT SUBMITTALS

A. Section 01 77 00 – Closeout Procedures: Requirements for submittals.

B. Project Record Documents: Record actual locations of piping mains, curb stops, connections, thrust restraints, and elevations.

C. Identify and describe unexpected variations to subsoil conditions or discovery of uncharted utilities.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Section 01 61 00 – Product Requirements: Requirements for transporting, handling, Herbert, Rowland & Grubic, Inc. 33 14 17 - 2 009280.0426 storing, and protecting products.

B. Inspection: Accept materials on Site in manufacturer's original packaging and inspect for damage.

C. Store materials according to manufacturer instructions.

D. Protection:

1. Protect materials from moisture and dust by storing in clean, dry location remote from construction operations areas.

2. Provide additional protection according to manufacturer instructions.

PART 2 - PRODUCTS

2.1 WATER PIPING AND FITTINGS

A. Copper Tubing (2” or less):

1. Comply with ASTM B88.

2. Type: K, annealed.

3. Joints: Compression connection.

B. Services larger than 2” shall be Ductile Iron in accordance with section 33 14 13 – Public Water Utility Distribution Piping.

C. Unions:

1. Comply with AWWA C800.

2. Material: Non-lead brass.

3. Connections: Compression style (pack joint, quick joint, or grip joint).

4. Dielectric coupling required for all copper to non-copper connections.

2.2 CORPORATION STOP ASSEMBLIES

A. Manufacturers:

1. Mueller 110 Compression Connection Outlet

2. Ford F1000-3Q Compression Connection Outlet

3. Or approved equal.

B. Corporation Stops:

1. Comply with ASTM B62.

2. Body: Bronze.

3. Inlet End: Threaded for tapping according to AWWA C800.

4. Outlet End: Suitable for service pipe specified.

C. Service Saddles:

1. Type: Double strap.

2. Designed to hold pressures in excess of pipe working pressure.

Herbert, Rowland & Grubic, Inc. 33 14 17 - 3 009280.0426

2.3 CURB STOP ASSEMBLIES

A. Manufacturers:

1. Mueller 110 Compression Connection Outlet

2. Ford B44-333Q Compression Connection Outlet

3. Or approved equal.

B. Curb Stops:

1. Body: Bronze.

2. Comply with ASTM B62.

3. Valve Type: Plug.

4. Inverted Key Stop

5. Sealing: Positive pressure.

C. Curb Boxes and Covers:

1. Manufacturer:

a. Opelika B & T.

b. Tyler Union.

c. Or approved equal.

2. Body: Cast iron.

3. Type: Extension.

4. Base: Arch pattern.

5. Coating: Tar or asphaltic compound; interior and exterior.

6. Lid:

a. Inscription: WATER.

b. 2 ½ new style flush fit covers with foot piece

c. Plug: Pentagonal.

2.4 MATERIALS

A. Bedding and Cover:

1. Bedding and cover: As specified in Section 31 23 33 – Trenching and Backfilling for Utilities.

2. Soil Backfill from above Pipe to Finish Grade: Suitable Backfill and Embankment Material as specified in Section 31 23 33 – Trenching and Backfilling for Utilities.

3. Subsoil: No rocks more than 6 inches in diameter, frozen earth, or foreign matter.

2.5 ACCESSORIES

A. Pipe Markers: As specified in Section 33 05 53 – Identification for Utilities Piping and Equipment.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 – Execution Requirements: Requirements for installation examination.

Herbert, Rowland & Grubic, Inc. 33 14 17 - 4 009280.0426

B. Verify that building service connections and municipal utility water main sizes, locations, and inverts are as indicated on Drawings.

3.2 PREPARATION

A. Section 01 73 00 – Execution Requirements: Requirements for installation preparation.

B. Cut pipe ends square, ream pipe and tube ends to full pipe diameter, and remove burrs.

C. Remove scale and dirt from inside and outside of piping before assembly.

D. Prepare pipe connections to equipment with flanges or unions.

3.3 INSTALLATION

A. Corporation Stop Assemblies:

1. Make connection for each different kind of water main, using suitable materials, equipment, and methods as approved by Architect/Engineer.

2. Provide service clamps for mains constructed of materials other than cast iron or ductile iron.

3. Location:

a. Screw corporation stops directly into tapped and threaded iron main at 10- and 2-o'clock positions along main's circumference.

b. Locate and stagger corporation stops at least 12 inches apart longitudinally.

4. Use seals or other devices such that no leaks are present in mains at points of tapping.

5. Do not backfill and cover service connections until installation has been approved by Engineer.

B. Bedding:

1. Excavate pipe trench as specified in Section 31 23 33 – Trenching and Backfilling for Utilities.

2. Backfill around sides and to top of pipe as specified in Section 31 23 33 –

Trenching and Backfilling for Utilities.

3. Maintain optimum moisture content of fill material to attain required compaction density.

C. Pipe and Fittings:

1. Maintain separation of water main from sewer piping according to state standards.

2. Group piping with other Site piping Work whenever practical.

3. Install pipe to allow for expansion and contraction without stressing pipe or joints.

4. Install access fittings to permit disinfection of water system.

5. Thrust Restraints: Form and place concrete for thrust restraints at each elbow or change of direction of pipe.

6. Establish elevations of buried piping with not less than 4 feet of cover.

Herbert, Rowland & Grubic, Inc. 33 14 17 - 5 009280.0426

7. Pipe Markers: As specified in Section 33 05 53 – Identification and Utilities Piping and Equipment.

8. Backfill trench as specified in Section 31 23 33 – Trenching and Backfilling for Utilities.

D. Curb Stop Assemblies:

1. Set curb stops on solid bearing compacted soil.

2. The curb step shall be located no more than 18" behind the curb face. Curb boxes are to be protected from vehicular traffic. If this is not possible, it shall be located by the Water Distribution Division.

a. The shut—off to a service line above 2" shall be located in the street within 3‘ of the main. If conflicts exist that the shut—off valve cannot be located within the required distance, then it shall be installed as close as possible.

3. Boxes:

a. Center and plumb curb boxes over curb stops.

b. Set box cover flush with finished grade.

E. Service Connections:

1. Install water service according to as indicated on Drawings.

2. One continuous length of pipe shall be used for all water services from the curb box to the corporation fitting. No joint connections shall be installed on the water service line. If an existing copper water service line requires to be extended to connect to the new water main, the full length of water service line shall be replaced from the curb stop to the corporation fitting.

3. No fittings in contact with water are to contain lead.

4. All service lines shall have a minimum of 4’ of ground cover to protect the pipe from freezing. The service line shall also be bedded in screening.

5. All service lines must be inspected prior to back filling. If a service line is back filled prior to inspection, it will be required to be excavated for inspection.

a. A service line shall be inspected for the proper fittings.

b. Proper type of pipe.

c. Verify that the correct connections were made.

d. Proper location of the curb box.

e. Proper bedding.

6. Lines greater than 2" shall have chlorine tablets placed in the pipe prior to installation.

7. Final inspection of a completed system, from the curb stop to the curb box, is required prior to acceptance.

8. Customer’s service line shall extend to the curb box.

9. If an existing water service line is broken, it can be repaired by using compression fittings meeting AWWA C800, that are manufactured for the specific pipe that is being repaired. In no case can the repaired water service line be back filled until the repaired water service line can be pressure tested. If the existing water service line is replaced with polyethylene plastic (ASTM 02239) and the home electrical system is grounded through the water pipe, the property owner will be

Herbert, Rowland & Grubic, Inc. 33 14 17 - 6 009280.0426 required to have grounding rods installed by a registered electrician, in accordance with the current electrical code.

F. Disinfection of Water Piping System: Flush and disinfect system as specified in Section 33 13 00 – Disinfection of Water Utility Distribution.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 – Quality Requirements: Requirements for inspecting and testing.

B. Testing:

1. Pressure test water distribution system according to section 33 05 05.31 –

Hydrostatic Testing.

2. After Inspection of the service line, all solid runs of pipe can be back filled to provide anchoring of the line. All connecting joints, fittings, valves, etc. must remain uncovered until the line is charged with water pressure. Then the joints shall be inspected for leaks. After the line has passed the pressure test, then it may be back filled with suitable material.

C. If tests indicate Work does not meet specified requirements, remove Work, replace, and retest.

END OF SECTION 33 14 17