01 32 36 - Video Monitoring and Documentation.pdf

PDF 473 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a technical specification document for video monitoring and documentation services prepared by Herbert, Rowland & Grubic, Inc., applicable to the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4) in Pennsylvania. The specification requires the contractor to provide comprehensive video documentation of the project site, including preconstruction recordings from multiple vantage points before work begins, and monthly periodic construction recordings coinciding with payment applications. All video recordings must be submitted in digital video disc format within seven days of recording, accompanied by detailed identification information, key site plans indicating vantage points with compass directions and elevations, and transcripts prepared on standard 8.5-by-11-inch paper bound in three-ring binders. The specification mandates a minimum recording time of 15 minutes for periodic construction videos and requires documentation of existing site conditions, building exteriors, adjacent properties, driveways, sidewalks, drainage patterns, utilities, and protection efforts by the contractor, with all recordings to be conducted during periods of good visibility and without precipitation or snow cover.

The specification establishes strict quality standards requiring maximum depth of field with all footage in sharp focus, with blurry or out-of-focus recordings subject to rejection. All media storage must be properly identified by number, date, location, and project name, with an index run sheet documenting each storage device's contents, referenced station numbers, line numbers, and time-date encoding. The contractor must transfer all copyright usage rights to the project owner for unlimited use and reproduction. The specification references Section 01 33 00 for submittal procedures and Section 01 77 00 for closeout procedures, indicating this documentation requirement is integrated into the broader project manual and contract specifications for the water main replacement work involving approximately 13,860 feet of water main relocation, fifteen fire hydrant replacements, and 180 service transfers.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 36 – VIDEO MONITORING AND DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 36 - 1 009280.0426

SECTION 01 32 36 – VIDEO MONITORING AND DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Preconstruction video recordings.

B. Related Sections:

1. Section 01 33 00 – Submittal Procedures: Procedures for submitting photographic documentation.

2. Section 01 77 00 – Closeout Procedures: Procedures for submitting photographic documentation as project record documents at Project closeout.

1.2 SUBMITTALS

A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each video recording. Indicate elevation or story of construction. Include same information as corresponding video documentation.

B. Video Recordings: Submit video recordings within seven days of recording.

1. Submit video recordings in digital video disc format acceptable to Engineer by posting to Project Web site.

2. Identification: With each submittal, provide the following information:

a. Name of Project.

b. Name and address of photographer.

c. Name of Engineer.

d. Name of Contractor.

e. Date video recording was recorded.

f. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

g. Weather conditions at time of recording.

3. Transcript: Prepared on 8-1/2-by-11-inch paper, punched and bound in heavy-duty, three-ring, vinyl-covered binders. Mark appropriate identification on front and spine of each binder. Include a cover sheet with same label information as corresponding video recording. Include name of Project and date of video recording on each page.

Herbert, Rowland & Grubic, Inc. 01 32 36 - 2 009280.0426

1.3 USAGE RIGHTS

A. Transfer copyright usage rights to Owner for unlimited use and reproduction of video documentation.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION

3.1 GENERAL

A. Take videos using the maximum range of depth of field, and that are in focus, to clearly show the Work. Videos with blurry or out-of-focus areas will not be accepted.

1. Maintain key plan with each set of construction photographs that identifies each location.

3.2 VIDEO TAPING PROCEDURE

A. All video to be done during periods of good visibility and not during periods of visible precipitation or while ground is covered by snow.

B. Control direction of travel, panning rates, and zoom in-out rates in a manner that produces clarity of subject during playback.

C. Include in outdoor video coverage driveways, sidewalks, curbs, ditches (to show drainage patterns), street (as full width as possible), landscaping, trees, shrubs, culverts, catch basins, retaining walls, headwalls, fences, visible utilities, and building exteriors within the zones of influence. Buildings should be identified both audibly and visibly when possible.

D. Properly identify all media storage by number, date, locations and project name. Begin each storage media with current date, project name and municipality.

E. Supply an index run sheet with a record of each media storage device contents and identify locations, station numbers, line numbers, etc., referenced to time and date encoded in video.

3.3 CONSTRUCTION VIDEO RECORDINGS

A. Preconstruction Video Recording: Before starting construction, record video recording of Project site and surrounding properties from sufficiently different vantage points to completely record the state of the site and existing building in and around the construction area. Coordinate with Owner Representative to ensure no sensitive areas outside of the limits of construction are videotaped.

1. Flag construction limits before recording construction video recordings.

2. Show existing conditions adjacent to Project site before starting the Work.

Herbert, Rowland & Grubic, Inc. 01 32 36 - 3 009280.0426

3. Show existing building on site to accurately record physical conditions at the start of construction.

4. Show protection efforts by Contractor.

B. Periodic Construction Video Recordings: Record video recording monthly with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last video recordings were recorded.

1. Video shall sufficiently show how construction is affecting the existing structure and site, and the efforts of the Contractor to protect existing site and structures.

2. Minimum recording time shall be 15 minutes.

END OF SECTION 01 32 36