01 33 00 - Submittal Procedures.pdf

PDF 508 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

Summary

This is a Submittal Procedures specification document from Herbert, Rowland & Grubic, Inc. (HRG), the engineer for the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4). The document establishes comprehensive requirements for contractors to submit construction-related documentation including product data, shop drawings, samples, test reports, certificates, and erection drawings for engineer review and approval. Submittals must be sequentially numbered, clearly identified with project, contract, and specification section information, and bear the contractor's certification stamp indicating compliance with contract documents. All submittals shall be submitted electronically via email as PDF files to Alexander Bar at abar@hrg-inc.com with specific subject line formatting including contractor name, contract number, submittal type, and identification number. For approved or approved-as-corrected submittals, contractors must mail three hard copies to HRG within five business days at 501 Allendale Road, Suite 203, King of Prussia, PA 19406.

The engineer will review submittals and return them with one of five actions: "APPROVED," "APPROVED AS CORRECTED," "REVISE AND RESUBMIT," "NOT APPROVED," or "NO ACTION TAKEN." Contractors must not begin fabrication or work on items requiring submittal approval until receiving approved documentation. Electronic CAD files of project drawings are available at a cost of $25 per file plus a $60 administrative fee, paid in advance by certified check or money order. The document prohibits "mass submittals" (six or more items in one day or twenty or more items in one week); violations will result in extended review timelines at engineer discretion. Starting with the second resubmission, the owner may charge contractors for engineer review time and expenses at standard rates, offset against contractor payment.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 33 00 – SUBMITTAL PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 33 00 - 1 009280.0426

SECTION 01 33 00 – SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Definitions.

B. Submittal procedures.

C. Construction progress schedules.

D. Proposed product & Subcontractor lists.

E. Product data.

F. Use of electronic CAD files of Project Drawings.

G. Shop Drawings.

H. Samples.

I. Other submittals.

J. Design data.

K. Test reports.

L. Certificates.

M. Erection Drawings.

N. Contractor review.

O. Engineer review.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action.

B. Informational Submittals: Written and graphic information and physical Samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements.

1.3 SUBMITTAL PROCEDURES

A. Transmit each submittal with Engineer-accepted form.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 2 009280.0426

B. Sequentially number transmittal forms. Mark revised submittals with original number and sequential alphabetic suffix.

C. Identify: Project, Contractor, Subcontractor and supplier, pertinent Drawing and detail number, and Specification Section number appropriate to submittal.

1. Specification: Specification Number, Article Number (include the Paragraph

Letter if more than one item is included in the Article section) dash submittal number. Example: 03 30 00, 2.02-01 (1st submittal)

2. Plan Sheet: Plan and Sheet Number dash submittal number.

3. Mark revised resubmittals with original number and sequential alphabetic suffix.

D. Apply Contractor's stamp, signed or initialed, certifying that review, approval, verification of products required, field dimensions, adjacent construction Work, and coordination of information is according to requirements of the Work and Contract Documents.

Submittals not containing an executed certification stamp shall be returned.

E. Schedule submittals to expedite Project and submit electronic submittals via email as PDF electronic files. Coordinate submission of related items.

1. Email submittals shall have the Contract Name, Contract Number, “Shop

Drawing”, and Submittal Identification Number in the subject line.

2. Engineer will review Submittal as received. PDF Submittal will be returned to Contractor with comment(s) and Action using the same method as submitted.

3. APPROVED or APPROVED AS CORRECTED Submittals – Contractor shall submit 3 paper copies & mail to the Engineer within five (5) days Attn: Alexander Bar, P.E.

4. PDF electronic files: Where documents are scanned, all text shall be clearly readable and no information blurred/pixilated. Any non-readable text, blurred/pixilated information on a submittal will cause it to be rejected.

F. For each submittal for review, allow reasonable time for Engineer.

G. Identify variations in Contract Documents and product or system limitations that may be detrimental to successful performance of completed Work.

H. Allow 4”x4” space on submittals for Contractor and Engineer review stamps.

I. When revised for resubmission, identify changes made since previous submission.

J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report inability to comply with requirements.

K. Submittals not requested will not be recognized nor processed.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 3 009280.0426

L. Incomplete Submittals: Engineer will not review. Complete submittals for each item are required. Delays resulting from incomplete submittals are not the responsibility of Engineer.

1.4 CONSTRUCTION PROGRESS SCHEDULES

A. Comply with Section 01 32 16 – Construction Progress Schedule

1.5 PROPOSED PRODUCT LIST

A. Within 15 days after date of Notice to Proceed, submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.

B. For products specified only by reference standards, indicate manufacturer, trade name, model or catalog designation, and reference standards.

1.6 PRODUCT DATA

A. Product Data: Action Submittal: Submit to Engineer for review for assessing conformance with information given and design concept expressed in Contract Documents.

B. Submit number of copies Contractor requires, plus three copies Engineer will retain.

C. Mark each copy to identify applicable products, models, options, and other data.

Supplement manufacturers' standard data to provide information specific to this Project.

D. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

E. After review, produce copies and distribute according to 01 33 00 – Submittal Procedures Article and for record documents described in Section 01 73 00 – Execution Requirements.

1.7 ELECTRONIC CAD FILES OF PROJECT DRAWINGS

A. Electronic CAD Files of Project Drawings: May only be used to expedite production of Shop Drawings for the Project. Use for other Projects or purposes is not allowed.

B. Electronic CAD Files of Project Drawings: Distributed only under the following conditions:

1. Use of files is solely at receiver's risk. Engineer does not warrant accuracy of files.

Receiving files in electronic form does not relieve receiver of responsibilities for measurements, dimensions, and quantities set forth in Contract Documents. In the event of ambiguity, discrepancy, or conflict between information on electronic media and that in Contract Documents, notify Engineer of discrepancy and use information in hard-copy Drawings and Specifications.

2. CAD files do not necessarily represent the latest Contract Documents, existing conditions, and as-built conditions. Receiver is responsible for determining and

Herbert, Rowland & Grubic, Inc. 01 33 00 - 4 009280.0426 complying with these conditions and for incorporating addenda and modifications.

3. User is responsible for removing information not normally provided on Shop Drawings and removing references to Contract Documents. Shop Drawings submitted with information associated with other trades or with references to Contract Documents will not be reviewed and will be immediately returned.

4. Receiver shall not hold Engineer responsible for data or file clean-up required to make files usable, nor for error or malfunction in translation, interpretation, or use of this electronic information.

5. Receiver shall understand that even though Engineer has computer virus scanning software to detect presence of computer viruses, there is no guarantee that computer viruses are not present in files or in electronic media.

6. Receiver shall not hold Engineer responsible for such viruses or their consequences, and shall hold Engineer harmless against costs, losses, or damage caused by presence of computer virus in files or media.

C. Costs: $25 per file, plus an administrative fee of $60 per request paid in advance by certified check or money order payable to Engineer.

1.8 SHOP DRAWINGS

A. Shop Drawings: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.

B. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

C. When required by individual Specification Sections, provide Shop Drawings signed and sealed by a professional Engineer responsible for designing components shown on Shop Drawings.

1. Include signed and sealed calculations to support design.

2. Submit Shop Drawings and calculations in form suitable for submission to and approval by authorities having jurisdiction.

3. Make revisions and provide additional information when required by authorities having jurisdiction.

D. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information:

1. Dimensions.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 5 009280.0426

2. Identification of products.

3. Fabrication and installation drawings.

4. Roughing-in and setting diagrams.

5. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

6. Shopwork manufacturing instructions.

7. Templates and patterns.

8. Schedules.

9. Compliance with specified standards.

10. Notation of coordination requirements.

11. Notation of dimensions established by field measurement.

12. Relationship to adjoining construction clearly indicated.

13. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

E. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches.

F. Submit electronic submittals via email as PDF electronic files.

1. The submittal requires the formatted shop drawing transmittal letter to be included as the cover sheet of the submittal on the Contractor’s letterhead. All shop drawing and certification submissions are required to be on the form.

a. All shop drawings submitted to HRG for review shall bear the contractor’s certification that he has reviewed, check and approved the shop drawings, all dimensions and that they are in conformance with the Contract Documents. Uncertified shop drawings will be returned to the Contractor for certification prior to review by HRG.

2. Scan the complete reviewed and approved shop drawing submittal as one PDF scan.

a. The scan attachment should be named per submittal

3. The submittal should be emailed to HRG, Alexander Bar, abar@hrg-inc.com

a. Subject Line of Email shall include the following:

1) Contractor Name Water Main Replacement Project Phase 4

2) Contract #WR-4

Herbert, Rowland & Grubic, Inc. 01 33 00 - 6 009280.0426

3) Shop Drawing

4) Submittal Identification Number

4. The Engineer will review submittal as reviewed, comment and indicate action.

a. Engineer will e-mail back (PDF) reviewed submittal to the Contractor.

b. Once the submittal is Approved or Approved as Corrected the Contractor shall mail 3 hard copies of the complete Shop Drawing within 5 days to

1) HRG, 501 Allendale Road, Suite 203 King of Prussia, PA 19406

Attention: Alexander Bar

1.9 SAMPLES

A. Samples: Action Submittal: Submit to Engineer for assessing conformance with information given and design concept expressed in Contract Documents.

B. Samples for Selection as Specified in Product Sections:

1. Submit to Engineer for aesthetic, color, and finish selection.

2. Submit Samples of finishes, textures, and patterns for Engineer selection.

C. Submit Samples to illustrate functional and aesthetic characteristics of products, with integral parts and attachment devices. Coordinate Sample submittals for interfacing work.

D. Include identification on each Sample, with full Project information.

E. Submit number of Samples specified in individual Specification Sections; Engineer will retain one Sample.

F. Reviewed Samples that may be used in the Work are indicated in individual Specification Sections.

G. Samples will not be used for testing purposes unless specifically stated in Specification Section.

H. After review, produce copies and distribute according to 01 33 00 – Submittal Procedures Article and for record documents described in Section 01 73 00 – Execution Requirements and Section 01 77 00 – Closeout Procedures.

1.10 OTHER SUBMITTALS

A. Closeout Submittals: Comply with Section 01 77 00 – Closeout Procedures.

B. Informational Submittal: Submit data for Engineer's knowledge as Contract administrator or for Owner.

C. Submit information for assessing conformance with information given and design concept expressed in Contract Documents.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 7 009280.0426

1.11 TEST REPORTS

A. Informational Submittal: Submit reports for Engineer's knowledge as Contract administrator or for Owner.

B. Submit test reports for information for assessing conformance with information given and design concept expressed in Contract Documents.

1.12 CERTIFICATES

A. Informational Submittal: Submit certification by manufacturer, installation/application Subcontractor, or Contractor to Engineer, in quantities specified for Product Data.

B. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

C. Certificates may be recent or previous test results on material or product but must be acceptable to Engineer.

1.13 MANUFACTURER'S INSTRUCTIONS

A. Informational Submittal: Submit manufacturer's installation instructions for Engineer's knowledge as Contract administrator or for Owner.

B. Submit printed instructions for delivery, storage, assembly, installation, startup, adjusting, and finishing, to Engineer in quantities specified for Product Data.

C. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

1.14 MANUFACTURER'S FIELD REPORTS

A. Informational Submittal: Submit reports for Engineer's knowledge as Contract administrator or for Owner.

B. Submit reports for information for assessing conformance with information given and design concept expressed in Contract Documents.

1.15 ERECTION DRAWINGS

A. Informational Submittal: Submit Drawings for Engineer's knowledge as Contract administrator or for Owner.

B. Submit Drawings for information assessing conformance with information given and design concept expressed in Contract Documents.

C. Data indicating inappropriate or unacceptable Work may be subject to action by Engineer or Owner.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 8 009280.0426

1.16 CONTRACTOR REVIEW

A. Review for compliance with Contract Documents and approve submittals before transmitting to Engineer.

B. Contractor: Responsible for:

1. Determination and verification of materials including manufacturer's catalog numbers.

2. Determination and verification of field measurements and field construction criteria.

3. Checking and coordinating information in submittal with requirements of Work and of Contract Documents.

4. Determination of accuracy and completeness of dimensions and quantities.

5. Confirmation and coordination of dimensions and field conditions at Site.

6. Construction means, techniques, sequences, and procedures.

7. Safety precautions.

8. Coordination and performance of Work of all trades.

C. Stamp, sign or initial, and date each submittal to certify compliance with requirements of Contract Documents.

D. Do not fabricate products or begin Work for which submittals are required until approved submittals have been received from Engineer.

E. Before submitting each Shop Drawing or Sample, Contractor shall have:

1. Reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents;

2. Determined and verified all field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto;

3. Determined and verified the suitability of all materials offered with respect to the indicated application, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of the Work;

Herbert, Rowland & Grubic, Inc. 01 33 00 - 9 009280.0426

4. Determined and verified all information relative to Contractor's responsibilities for means, methods, techniques, sequences, and procedures of construction, and safety precautions and programs incident thereto.

1.17 ENGINEER REVIEW

A. Do not make "mass submittals" to Engineer. "Mass submittals" are defined as six or more submittals or items in one day or 20 or more submittals or items in one week. If "mass submittals" are received, Engineer's review time will be extended as necessary to perform proper review. Engineer will review "mass submittals" based on priority determined by Engineer after consultation with Owner and Contractor.

B. Informational submittals and other similar data are for Engineer's information, do not require Engineer's responsive action, and will not be reviewed or returned with comments.

C. Submittals made by Contractor that are not required by Contract Documents may be returned without action.

D. Submittal approval does not authorize changes to Contract requirements unless accompanied by Change Order, Field Order, or Work Change Directive.

E. Engineer's Action: Where action and return is required, Engineer will provide timely review of each submittal in accordance with the accepted Schedule of Submittals.

1. Submittals returned with "APPROVED" action indicates that the information submitted was found to be in conformance with the design concept and in compliance with the requirements of the Contract Documents. Contractor may proceed with performance of the work covered by the submittal.

2. Submittals returned with "APPROVED AS CORRECTED" action indicates that the information submitted was found to be in conformance with the design concept and in compliance with the requirements of the Contract Documents, provided the noted clarifications or corrections are completed. Submission of a corrected submittal indicating the changes noted by Engineer is required as part of the Project Record Documents. Contractor may proceed with performance of the work covered by the corrected submittal.

3. Submittals returned with "REVISE AND RESUBMIT" action indicate that: (1) information submitted is at least partially not in conformance with the design concept, (2) information submitted is at least partially not in compliance with the requirements of the Contract Documents, (3) submittal is incomplete and does not include all items required by the individual specification Sections, or (4) certifications or computations required by the individual specification Sections have not been included in the submittal. Submittal will be returned to Contractor noting the reasons for noncompliance. Contractor shall not proceed with the performance of the work covered by submittal until corrected information is submitted and approved.

Herbert, Rowland & Grubic, Inc. 01 33 00 - 10 009280.0426

4. Submittals returned with "NOT APPROVED" action indicates that the Engineer interprets the information submitted to be not in conformance with the design concept or not in compliance with the Contract Documents. Performance of the work shall not proceed until submittal is revised, resubmitted and approved.

5. Submittals returned with “NO ACTION TAKEN” indicates that the Engineer interprets the information to be for informational purposes only and does not require other action by the Engineer.

F. Owner may offset payment due to Contractor to cover additional costs beyond the first resubmission review. Starting with the second resubmission, Contractor may be charged, by Owner, for the time and expenses of Engineer at Engineer's standard rates. Such charge shall be offset from Contractor's payment.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 33 00