This is a Table of Contents document for the Water Main Replacement Project Phase 4 bid set prepared by Herbert, Rowland & Grubic, Inc. for the Elizabethtown Area Water Authority in Pennsylvania. The project encompasses the relocation of approximately 13,860 feet of 4-inch, 6-inch, and 8-inch ductile iron pipe (DIP) water main with associated appurtenances, replacement of approximately 15 fire hydrants, and transfer of approximately 180 existing water services to new 12-inch DIP water main. Bids will be received online via PennBid until Thursday, August 6, 2026, at 10:00 AM local time, with public bid opening immediately following. The contract is designated as WR-4 and requires a single Prime Contract for general construction. All bidding documents, addenda, and official communications will be distributed exclusively through the designated online platform at https://pennbid.bonfirehub.com/, and prospective bidders must register as plan holders to receive official notifications.
The bid set consists of comprehensive documentation organized into multiple divisions covering procurement and contracting requirements, general specifications, existing conditions, concrete work, earthwork, exterior improvements, and utility work specifications. Required bid documents include a bid form, bid bond, non-collusion affidavit, EEO certificate, public works employment verification form, performance bond, payment bond, and various project forms. The contract documents incorporate general conditions, wage rate requirements, anti-pollution measures, and statutory requirements. No specific budget, set-asides, or incumbent contractor information is identified in the table of contents. The project requires furnishing all necessary materials, equipment, labor, and miscellaneous items as specified in the complete contract documents and project manual.
View the file
Other files
Show 40 more
Latest 50 of 91 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Herbert, Rowland & Grubic, Inc. 00 01 10 - 1 009280.0426
WATER MAIN REPLACEMENT PROJECT PHASE 4
ELIZABETHTOWN AREA WATER AUTHORITY
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS SECTION: PAGES
Procurement Requirements ADVERTISEMENT FOR BIDS ............................................................................................................... 00 11 13: 2 INSTRUCTIONS TO BIDDERS .............................................................................................................. 00 21 13: 11 PERMITS ............................................................................................................................................ 00 31 46: 1 BID FORM FOR CONSTRUCTION CONTRACT ..................................................................................... 00 41 16: 7 BID BOND .......................................................................................................................................... 00 43 13: 2 NON-COLLUSION AFFIDAVIT ............................................................................................................. 00 45 19: 1 EEO CERTICATE ................................................................................................................................. 00 45 36: 1 PUBLIC WORKS EMPLOYMENT VERIFICATION FORM ....................................................................... 00 45 46: 1
Contracting Requirements AGREEMENT BETWEEN OWNER and CONTRACTOR for CONSTRUCTION CONTRACT ..................... 00 52 00: 7 NOTICE TO PROCEED FORM.............................................................................................................. 00 55 00: 1 PROJECT FORMS ............................................................................................................................... 00 60 00: 1 PERFORMANCE BOND ...................................................................................................................... 00 61 13.13: 4 PAYMENT BOND ............................................................................................................................... 00 61 13.16: 4 CONTRACTOR’S APPLICATION FOR PAYMENT .................................................................................. 00 62 76: 6 REQUEST FOR INFORMATION FORM ................................................................................................ 00 63 13: 1 FIELD ORDER FORM .......................................................................................................................... 00 63 36: 1 WORK CHANGE DIRECTIVE FORM .................................................................................................... 00 63 49: 1 CHANGE ORDER FORM ..................................................................................................................... 00 63 63: 1 CERTIFICATE OF SUBSTANTIAL COMPLETION FORM ........................................................................ 00 65 16: 1 AFFIDAVIT OF RELEASE OF LIENS FORM ........................................................................................... 00 65 19.16: 1 CONSENT OF SURETY FOR FINAL PAYMENT FORM .......................................................................... 00 65 19.19: 1 NOTICE OF ACCEPTABILITY OF WORK ............................................................................................... 00 65 19.23: 1 GENERAL CONDITIONS ...................................................................................................................... 00 72 00: 95 WAGE RATE REQUIREMENTS ............................................................................................................ 00 73 43: 4 WAGE DETERMINATION SCHEDULE ................................................................................................. 00 73 46: 8 ANTI-POLLUTION MEASURES ............................................................................................................ 00 73 53: 1 STATUTORY REQUIREMENTS ............................................................................................................ 00 73 73: 6
Specifications
DIVISION 01 – GENERAL REQUIREMENTS PAGES
01 10 00 PROJECT SUMMARY
01 22 00 UNIT PRICES
01 26 00 CONTRACT MODIFICATIONS
01 26 13 REQUEST FOR INTERPRETATION
01 31 13 PROJECT COORDINATION
01 31 19 PROJECT MEETINGS
01 32 16 CONSTRUCTION PROGRESS SCHEDULE
01 32 26 CONSTRUCTION PROGRESS REPORTING
01 32 33 PHOTOGRAPHIC DOCUMENTATION
01 32 36 VIDEO MONITORING AND DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 41 26 PERMIT REQUIREMENTS
01 42 00 REFERENCES
01 57 28 TEMPORARY FACILITIES AND CONTROLS
01 61 00 PRODUCT REQUIREMENTS
01 73 00 EXECUTION REQUIREMENTS
TABLE OF CONTENTS
Herbert, Rowland & Grubic, Inc. 00 01 10 - 2 009280.0426
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 77 00 CLOSEOUT PROCEDURES
01 78 36 WARRANTIES
01 78 39 PROJECT RECORD DOCUMENTS
DIVISION 02 - EXISTING CONDITIONS PAGES
02 31 00 Subsurface Utility Engineering 02 82 33 Removal and Disposal of Asbestos Containing Material
DIVISION 03 – CONCRETE PAGES
03 10 00 Concrete Forming And Accessories 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 35 00 Concrete Finishing 03 39 00 Concrete Curing 03 60 00 Grouting
DIVISION 31 – EARTHWORK PAGES
31 05 19.13 Geotextiles for Earthwork
31 23 16.26 Rock Removal 31 23 19 Dewatering 31 23 23.33 Flowable Fill 31 23 33 Trenching and Backfilling for Utilities 31 25 00 Erosion and Sedimentation Controls
DIVISION 32 – EXTERIOR IMPROVEMENTS PAGES
32 11 23 Aggregate Base Courses 32 12 16 Asphalt Paving 32 13 13 Concrete Paving 32 17 23 Pavement Markings 32 91 13 Soil Preparation 32 91 19 Landscape Grading 32 92 19 Seeding 32 92 23 Sodding
DIVISION 33 – UTILITIES PAGES
33 01 10 Operation and Maintenance of Water Utilities 33 05 05.31 Hydrostatic Testing 33 05 53 Identification for Utilities Piping and Equipment 33 13 00 Disinfection of Water Utility Distribution 33 14 13 Public Water Utility Distribution Piping 33 14 17 Site Water Service Utility Laterals
33 14 19 Valves and Hydrants for Water Utility Service
File details come from the government source that posted it. Updated .