32 11 23 - Aggregate Base Courses.pdf

PDF 469 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a technical specification document for Aggregate Base Courses prepared by Herbert, Rowland & Grubic, Inc., applicable to the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4). The specification details the materials, quality standards, and installation procedures for aggregate subbase and aggregate base courses required for the project, which involves the relocation of approximately 13,860 feet of 4-inch, 6-inch, and 8-inch ductile iron pipe water main with replacement by new 12-inch DIP, replacement of approximately fifteen fire hydrants, and transfer of approximately 180 existing water services. The specification mandates the use of Type C or better No. 2A aggregate subbase in accordance with PennDOT Publication 408 Section 703.2, with AASHTO No. 1 coarse aggregate for repair work. All aggregate materials must originate from PennDOT-approved sources and be furnished from a single source throughout the work. Online bids are due Thursday, August 6, 2026, at 10:00 AM local time, with public bid opening immediately following, and work must be performed in accordance with PennDOT standards and West Donegal Township requirements.

The specification requires contractors to submit materials source names, manufacturer's certificates, and material slips certifying quantities utilized from producers in accordance with PennDOT specifications. Geotextile material (Class 4, Type B conforming to PennDOT Section 212.3) must be provided as an accessory material. Field quality control includes proof-rolling of subgrade with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding, with excavation and replacement of unsatisfactory soils as directed by the engineer. Compaction standards reference Section 31 23 23.33 - Flowable Fill, and all tolerances and quality requirements are governed by Section 01 40 00 - Quality Requirements. The project documentation is available through the PennBid website at https://pennbid.bonfirehub.com/, where prospective bidders must register as plan holders to access all official notifications, addenda, and bidding documents.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

32 11 23 – AGGREGATE BASE COURSES

Herbert, Rowland & Grubic, Inc. 32 11 23 - 1 009280.0426

SECTION 32 11 23 – AGGREGATE BASE COURSES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Aggregate subbase.

2. Aggregate base course.

B. Related Sections:

1. Section 31 23 33 – Trenching and Backfilling for Utilities.

2. Section 32 12 16 – Asphalt Paving.

3. Section 32 13 13 – Concrete Paving: Finish concrete surface course.

4. Section 32 91 19 – Landscape Grading: Topsoil fill at areas adjacent to aggregate base course.

1.2 REFERENCES

A. Pennsylvania Department of Transportation (PennDOT):

1. Publication 19 – Field and Laboratory Test Methods, latest edition.

2. Publication 408 - Specifications, latest edition, as amended.

B. Commonwealth of Pennsylvania, Pennsylvania Code, Title 67, Transportation, Department of Transportation:

1. Chapter 459, Occupancy of Highways by Utilities, as supplemented or revised.

2. Chapter 213, Work Zone Traffic Control (PennDOT Chapter 213).

C. American Association of State Highway and Transportation Officials:

1. AASHTO M288 - Standard Specification for Geotextile Specification for Highway Applications.

D. ASTM International:

1. ASTM D2922 - Standard Test Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth).

Herbert, Rowland & Grubic, Inc. 32 11 23 - 2 009280.0426

2. ASTM D2940 - Standard Specification for Graded Aggregate Material for Bases or Subbases for Highways or Airports.

3. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth).

1.3 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Materials Source: Submit name of aggregate materials suppliers.

C. Manufacturer's Certificate: Certify Products meet or exceed specified requirements.

D. Material Slips: Furnish certification of the amount of materials utilized from the producer in accordance with PennDOT specifications.

1.4 QUALITY ASSURANCE

A. Furnish each aggregate material from single source throughout the Work.

B. All aggregate must originate from a source approved by PennDOT meeting according to PennDOT standards.

C. Perform Work in accordance with PennDOT and West Donegal Township standard.

PART 2 - PRODUCTS

2.1 AGGREGATE MATERIALS

A. Aggregate Subbase: Type C or better, No. 2A, PennDOT Publication 408 Section 703.2.

B. Aggregate Subbase Repair: AASHTO No. 1, in accordance with PennDOT Publication 408, Section 703.2.

2.2 ACCESSORIES

A. Geotextile: Class 4, Type B, conforming to PennDOT Section 212.3.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 – Execution Requirements: Verification of existing conditions before starting work.

B. Verify compacted substrate is dry and ready to support paving and imposed loads.

Herbert, Rowland & Grubic, Inc. 32 11 23 - 3 009280.0426

C. Proof-roll subgrade below pavements with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding in accordance with PennDOT Pub. 408, Section

210.3. Do not proof-roll wet or saturated subgrades.

D. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as determined by Engineer, and replace with AASHTO No. 1 coarse aggregate lined with geotextile material or other means as directed by Engineer.

E. Verify substrate has been inspected, gradients and elevations are correct.

3.2 PREPARATION

A. Correct irregularities in substrate gradient and elevation by scarifying, reshaping, and re-compacting.

B. Do not place fill on soft, muddy, or frozen surfaces.

3.3 AGGREGATE PLACEMENT

A. Aggregate Subbase: Type C or better, No. 2A, Section 703.2, placement per PennDOT Publication 408 Section 350.

3.4 TOLERANCES

A. Section 01 40 00 – Quality Requirements: Tolerances.

3.5 FIELD QUALITY CONTROL

A. Section 01 40 00 – Quality Requirements: Field inspecting, testing, adjusting, and balancing.

3.6 COMPACTION

A. Refer to Section 31 23 23.33 – Flowable Fill.

3.7 SCHEDULE

A. Refer to Restoration Schedule seen in Section 32 12 16 – Asphalt Paving.

END OF SECTION 32 11 23