01 77 00 - Closeout Procedures.pdf

PDF 476 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This is a closeout procedures specification document prepared by Herbert, Rowland & Grubic, Inc. for construction project management, applicable to the Elizabethtown Area Water Authority's Water Main Replacement Project Phase 4 (Contract No. WR-4). The document establishes comprehensive procedures for project closeout, including prerequisites for substantial completion, final completion inspections, and final cleaning requirements. The closeout process requires contractors to submit maintenance manuals, project record documents, digital construction photographs, certificates of release from authorities having jurisdiction, certificates of insurance for continuing coverage, and initial punch lists documenting incomplete or nonconforming work items with anticipated completion dates. Contractors must also complete facility startup, testing, adjusting, and balancing of systems; obtain necessary occupancy certificates and releases from utility companies; deliver tools and spare parts to the Owner; perform lock changeover; remove temporary facilities; and execute final cleaning. The Engineer conducts substantial completion inspections upon contractor request, and if deficiencies are identified, the contractor must remedy them and resubmit for reinspection, repeating this process until work passes inspection.

For final completion, contractors must submit a final punch list confirming all items are completed, a final payment request with supporting documentation and insurance certificates, specified warranties and maintenance agreements, an accounting statement of final contract changes, affidavits of payment of debts and release of liens, and surety consent to final payment. The Engineer performs a final completion inspection, and any incomplete or defective work must be remedied with reinspections at the contractor's cost for reimbursement to the Owner. Final cleaning requirements include sanitizing equipment and fixtures with appropriate cleaning materials, removing debris from roofs and drainage systems, sweeping paved areas, raking landscaped surfaces, and removing all waste, surplus materials, and construction facilities from the site.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 77 00 – CLOSEOUT PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 77 00 - 1 009280.0426

SECTION 01 77 00 – CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Closeout procedures.

B. Testing, adjusting, and balancing.

C. Final cleaning.

1.2 SUBMITTALS

A. Product Data: For cleaning agents.

B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.

C. Closeout Submittals:

1. Certificates of Release: From authorities having jurisdiction.

2. Certificate of Insurance: For continuing coverage.

3. Submittals as required by various specification sections.

1.3 CLOSEOUT PROCEDURES

A. Prerequisites to Substantial Completion: Complete following items before requesting Certification of Substantial Completion, either for entire Work or for portions of Work:

1. Submit maintenance manuals, Project record documents, digital images of construction photographs, and other similar final record data in compliance with this Section.

2. Complete facility startup, testing, adjusting, balancing of systems and equipment, demonstrations, and instructions to Owner's operating and maintenance personnel as specified in compliance with this Section.

3. Conduct inspection to establish basis for request that Work is substantially complete. Create comprehensive list (initial punch list) indicating items to be completed or corrected, value of incomplete or nonconforming Work, reason for being incomplete, and date of anticipated completion for each item. Include copy of list with request for Certificate of Substantial Completion.

4. Obtain and submit releases enabling Owner's full, unrestricted use of Project and access to services and utilities. Include certificate of occupancy, operating certificates, and similar releases from authorities having jurisdiction and utility companies.

Herbert, Rowland & Grubic, Inc. 01 77 00 - 2 009280.0426

5. Deliver tools, spare parts, extra stocks of material, and similar physical items to Owner.

6. Make final change-over of locks, eliminating construction master-key system, and transmit keys directly to Owner. Advise Owner's personnel of change-over in security provisions.

7. Discontinue or change over and remove temporary facilities and services from Project Site, along with construction tools, mockups, and similar elements.

8. Perform final cleaning according to this Section.

B. Substantial Completion Inspection:

1. When Contractor considers Work to be substantially complete, submit to Engineer:

a. Written certificate that Work, or designated portion, is substantially complete.

b. List of items to be completed or corrected (initial punch list).

2. Upon receipt of request for Substantial Completion, Owner and Engineer will make inspection to determine whether Work or designated portion is substantially complete.

3. Should Engineer determine that Work is not substantially complete:

a. Engineer will promptly notify Contractor in writing, stating reasons for its opinion.

b. Contractor shall remedy deficiencies in Work and send second written request for Substantial Completion to Engineer.

c. Engineer will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes

Engineer's inspection.

4. When Engineer finds that Work is substantially complete, Engineer will:

a. Prepare Certificate of Substantial Completion on EJCDC C-625 - Certificate of Substantial Completion, accompanied by Contractor's list of items to be completed or corrected as verified and amended by Engineer and Owner (final punch list).

b. Submit preliminary Certificate to Owner for review.

c. Submit final Certificate to Owner and Contractor for their written acceptance of responsibilities assigned to them in Certificate.

5. After Work is substantially complete, Contractor shall:

a. Allow Owner occupancy of Project under provisions stated in Certificate of Substantial Completion.

b. Complete Work listed for completion or correction within time period stipulated.

Herbert, Rowland & Grubic, Inc. 01 77 00 - 3 009280.0426

C. Prerequisites for Final Completion: Complete following items before requesting final acceptance and final payment.

1. When Contractor considers Work to be complete, submit written certification that:

a. Contract Documents have been reviewed.

b. Work has been examined for compliance with Contract Documents.

c. Work has been completed according to Contract Documents.

d. Work is completed and ready for final inspection.

2. Submittals: Submit following:

a. Final punch list indicating all items have been completed or corrected.

b. Final payment request with final releases and supporting documentation not previously submitted and accepted. Include certificates of insurance for products and completed operations where required.

c. Specified warranties, workmanship/maintenance bonds, maintenance agreements, and other similar documents.

d. Accounting statement for final changes to Contract Sum.

e. Contractor's affidavit of payment of debts and claims on form in Section

00 65 19.16.

f. Contractor affidavit of release of liens on form in Section 00 65 19.16.

g. Consent of surety to final payment on form in Section 00 65 19.19.

3. Perform final cleaning for Contractor-soiled areas according to this Section.

D. Final Completion Inspection:

1. After receipt of request for final inspection, Engineer will make inspection to determine whether Work or designated portion is complete.

2. Should Engineer or Owner consider Work to be incomplete or defective:

a. Engineer will promptly notify Contractor in writing, listing incomplete or defective Work.

b. Contractor shall remedy stated deficiencies and send second written request to Engineer that Work is complete.

c. Engineer and Owner will re-inspect Work.

d. Redo and Inspection of Deficient Work: Repeated until Work passes

Engineer's and Owner's inspection. Contractor shall reimburse Owner for the costs of Engineer for re-inspections due to incomplete work.

PART 2 - PRODUCTS – Not Used

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. Execute final cleaning prior to final Project assessment.

B. Clean equipment and fixtures to sanitary condition with appropriate cleaning materials.

Herbert, Rowland & Grubic, Inc. 01 77 00 - 4 009280.0426

C. Clean debris from roofs, gutters, downspouts, and drainage systems.

D. Clean Site; sweep paved areas, rake clean landscaped surfaces.

E. Remove waste and surplus materials, rubbish, and construction facilities from Site.

END OF SECTION 01 77 00