01 26 00 - Contract Modifications.pdf

PDF 474 KB Posted

Attached to
Water Main Replacement Project Phase 4 Contract No. WR-4
Solicitation number
Not on record
Issued by
Lancaster County, Pennsylvania

About this file

This document is a specification section for contract modification procedures issued by Herbert, Rowland & Grubic, Inc., applicable to the Elizabethtown Area Water Authority's water infrastructure projects. The section establishes standardized procedures for managing changes to contract work, including provisions for requests for interpretation (RFI), minor changes through field orders, proposal requests initiated by either the owner or contractor, and change order execution. The contract modification framework requires contractors to identify an authorized representative for receiving change documents, carefully review contract documents before commencing work, and promptly report any discrepancies to the engineer. For owner-initiated changes, the engineer issues proposal requests requiring contractors to submit detailed estimates within specified timeframes that include material quantities and costs, applicable taxes, delivery charges, equipment rental, labor costs, and updated construction schedules reflecting the change's impact. Contractor-proposed changes must include comprehensive documentation of the reason for the change and its effects on contract price and time. Change orders are executed upon owner approval of proposal requests, with options for stipulated price or unit price arrangements depending on contract circumstances.

The modification procedures also establish provisions for work change directives issued by the engineer and signed by the owner, which authorize contractors to proceed with work modifications pending subsequent change order execution. Contractors must maintain detailed time and material records for all directive work to substantiate costs and facilitate change evaluation. All revisions to the schedule of values, payment applications, progress schedules, and record documents must be promptly updated to reflect authorized changes as separate line items with corresponding adjustments to contract price and time. The specification does not address pricing terms, set-asides, incumbents, or funding sources, as it functions as a procedural framework applicable across multiple Elizabethtown Area Water Authority projects, including the Water Main Replacement Project Phase 4 Contract No. WR-4.

View the file

Other files

File Type Posted
03 30 00 - Cast-in-Place Concrete.pdf PDF
01 78 39 - Tap Card - Project Record Documents.pdf PDF
32 12 16 - Asphalt Paving.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 26 13 - Request for Interpretation.pdf PDF
32 11 23 - Aggregate Base Courses.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
02 31 00 Subsurface Utility Engineering.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 63 36 - Field Order Form.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 46 - Wage Rate Determination.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 10 00 - Project Summary.pdf PDF
03 20 00 - Concrete Reinforcing.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
00 31 46 - Permits_01 - Phase 4 HOP Application - Sealed.pdf PDF
01 42 00 - References.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
31 23 19 - Dewatering.pdf PDF
02 82 33 Removal and Disposal of ACM.pdf PDF
32 91 13 - Soil Preparation.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
00 52 00 - Owner_Contractor Agreement.pdf PDF
33 14 19 - Valves And Hydrants For Water Utility Service.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
31 23 16.26 - Rock Removal.pdf PDF
01 32 36 - Video Monitoring and Documentation.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 45 36 EEO Certificate.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
01 31 13 - Project Coordination.pdf PDF
Show 40 more

Latest 50 of 91 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 26 00 – CONTRACT MODIFICATION PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 26 00 - 1 009280.0426

SECTION 01 26 00 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Change procedures.

B. Related Sections

1. Document 00 60 00 – Project Forms

2. Document 00 63 13 – RFI Form

3. Document 00 63 49 – Work Change Directive Form

4. Document 00 63 63 – Change Order Form

5. Section 01 26 13 – Request for Interpretation

1.2 CHANGE PROCEDURES

A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.

B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.

C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications.

1. Refer to Section 01 26 13 – Request for Interpretation.

2. Engineer may respond with a direct answer on the Request for Interpretation form, Field Order, or Proposal Request.

1.3 MINOR CHANGES IN THE WORK

A. Engineer will advise of minor changes in the Work not involving adjustment to Contract Price or Contract Time by issuing supplemental instructions on Field Order.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Engineer may issue Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and Specifications.

Herbert, Rowland & Grubic, Inc. 01 26 00 - 2 009280.0426

1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.

2. Contractor will prepare and submit estimate within time specified in the Proposal Request after receipt of Proposal Request

a. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and equipment directly attributable to the change.

d. Include an updated Construction Schedule that indicates the effect of the change.

B. Contractor may propose changes by submitting a Change Proposal to Engineer, describing proposed change and its full effect on the Work. Include a statement describing reason for the change and the effect on Contract Price and Contract Time with full documentation.

1. Notice: Comply with General Conditions where latent or changed conditions require modifications to the Contract.

2. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and equipment directly attributable to the change.

5. Include an updated Construction Schedule that indicates the effect of the change.

C. Document requested substitutions according to paragraph 7.06 in the General Conditions.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for execution by Owner and Contractor.

1. Change Order Forms: Document 00 63 63 – Change Order Form.

B. Stipulated Price Change Order: Based on Proposal Request and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer.

C. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, execute Work under Work Directive Change.

Herbert, Rowland & Grubic, Inc. 01 26 00 - 3 009280.0426

D. Correlation of Contractor Submittals:

1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Price.

2. Promptly revise Progress Schedules to reflect change in Contract Time, adjust times for other items of Work affected by the change, and resubmit.

3. Promptly enter changes in Record Documents.

1.6 WORK CHANGE DIRECTIVE

A. Engineer may issue directive, on Work Change Directive signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work and designate method of determining any change in Contract Price or Contract Time. Promptly execute change.

B. Maintain detailed records of Work done on time and material basis. Provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 26 00