33 05 05.31 - Hydrostatic Testing.pdf

PDF 471 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a technical specification document for hydrostatic testing procedures as part of the West Pump Station Replacement Project being undertaken by the Northwestern Chester County Municipal Authority in Pennsylvania. The specification establishes requirements for hydrostatic testing of pressure piping systems, including ductile iron and PVC piping, that will be installed during the project. The testing must be performed by an applicator with a minimum of three years' documented experience in hydrostatic testing work. Prior to testing initiation, contractors must submit testing procedures, equipment lists, testing sequence schedules, water disposal provisions, pressure gage calibration certificates, and applicant qualifications to the project authority.

The hydrostatic testing protocol requires pressurizing each piping section to 1.5 times the working pressure for a minimum two-hour duration, with pressure maintained within plus or minus 5.0 psi of the test pressure throughout. The specification references AWWA C600 and ASTM F 2164 standards and establishes a maximum allowable leakage formula using pipe length, diameter, and test pressure variables. All visible leaks must be corrected regardless of quantity, and any leakage exceeding calculated allowable limits requires locating the source, making corrections, and retesting until acceptable parameters are achieved. The specification mandates that trenches be backfilled and pressure piping thrust restraints be installed prior to testing commencement.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.31 – HYDROSTATIC TESTING

Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 1 000483.0450

SECTION 33 05 05.31 – HYDROSTATIC TESTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Hydrostatic testing of pressure piping.

B. Related Requirements:

1. Section 33 31 23 – Sanitary Sewerage Force Main Piping: Pipe materials and accessories normally encountered with municipal sanitary sewage force mains.

1.2 REFERENCE STANDARDS

A. American Water Works Association:

1. AWWA C600 - Installation of Ductile-Iron Water Mains and Their Appurtenances.

B. American Standard Testing Methods

1. ASTM F 2164 - Standard Practice for Field Leak Testing of Polyethylene (PE) and

Crosslinked Polyethylene (PEX) Pressure Piping Systems Using Hydrostatic Pressure.

1.3 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Submit following items prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Provisions for disposal of flushing and test water.

5. Certification of test gage calibration.

C. Test and Evaluation Reports: Indicate results of piping tests.

D. Qualifications Statement:

1. Submit qualifications for applicator.

1.4 QUALIFICATIONS

A. Applicator: Company specializing in performing Work of this Section with minimum three years' documented experience.

PART 2 - PRODUCTS

2.1 HYDROSTATIC TESTING

A. Equipment:

1. Pressure pump.

Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 2 000483.0450

2. Pressure hose.

3. Water meter.

4. Test connections.

5. Pressure relief valve.

6. Pressure Gage: Calibrated to 0.1 psi.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 – Execution and Closeout Requirements: Requirements for installation examination.

B. Verify that piping is ready for testing.

C. Verify that trenches are backfilled.

D. Verify that pressure piping thrust restraints have been installed.

3.2 FIELD QUALITY CONTROL

A. Section 01 40 00 – Quality Requirements: Requirements for inspecting and testing.

B. Testing of Pressure Ductile Iron or PVC Piping:

1. Test system according to AWWA C600 and following:

a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage.

b. Conduct hydrostatic testing for at least two hours.

c. Slowly fill with water portion of piping to be tested, expelling air from piping at high points.

d. Install corporation cocks at high points.

e. Close air vents and corporation cocks after air is expelled.

f. Raise pressure to specified test pressure.

g. Observe joints, fittings, and valves undergoing testing.

h. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage.

i. Retest.

j. Correct visible deficiencies and continue testing at same test pressure for additional two hours to determine leakage rate.

k. Maintain pressure within plus or minus 5.0 psi of test pressure.

l. Leakage is defined as quantity of water supplied to piping necessary to maintain test pressure during period of testing.

m. Compute maximum allowable leakage using following formula:

1) L = [SD x sqrt(P)]/C.

2) L = testing allowance, gph.

3) S = length of pipe tested, feet.

4) D = nominal diameter of pipe, inches.

5) P = average test pressure during hydrostatic testing, psig.

Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 3 000483.0450

6) C = 148,000.

7) If pipe undergoing testing contains sections of various diameters, calculate allowable leakage from sum of computed leakage for each pipe size.

2. If testing of piping indicates leakage greater than that allowed, locate source of leakage, make corrections, and retest until leakage is within acceptable limits.

3. Correct visible leaks regardless of quantity of leakage.

END OF SECTION 33 05 05.31