31 23 16.26 - Rock Removal.pdf

PDF 466 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a technical specification document for rock removal procedures related to the West Pump Station Replacement Project in Pennsylvania, managed by Northwestern Chester County Municipal Authority. The specification outlines the removal of identified and discovered rock during excavation operations, including site rock and trench rock materials that exceed defined volume thresholds or cannot be removed with standard excavation equipment without drilling or blasting. The work involves mechanical excavation methods, cutting rock at excavation bottoms to form level bearing surfaces, removing shaled layers to ensure sound foundations, and completing utility trench excavation to six inches below invert elevation and 24 inches wider than pipe diameter. All excavated materials must be removed from the site, and unauthorized rock removal must be corrected in accordance with backfilling and compacting requirements. The specification requires documentation of existing building conditions near rock removal locations through survey reports and photographs prior to work commencement, with scheduling designed to avoid disruption to occupied nearby buildings. Visual inspection of foundation bearing surfaces by the Engineer and inspection agency is mandated before subsequent work installation.

The specification references industry standards including NFPA 495 Explosive Materials Code and cross-references related construction sections covering rough grading, excavation, trenching, and fill materials. Submittal procedures are required per Section 01 33 00, and field quality control provisions are established under Section 01 40 00. The specification does not contain pricing information, set-asides, incumbent details, or contract term specifics, as it functions as a technical execution standard within the broader West Pump Station Replacement Project bid package that includes three separate contracts for general construction, electrical construction, and mechanical construction, with lump sum bidding required.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 23 16.26 – ROCK REMOVAL

Herbert, Rowland & Grubic, Inc. 31 23 16.26 - 1 000483.0450

SECTION 31 23 16.26 – ROCK REMOVAL

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Removing identified and discovered rock during excavation.

B. Related Sections:

1. Section 31 22 13 – Rough Grading.

2. Section 31 23 16 – Excavation: Building excavation.

3. Section 31 23 16.13 – Trenching: Trenching and backfilling for utilities.

4. Section 31 23 23 – Fill: Backfill materials.

1.2 REFERENCES

A. National Fire Protection Association:

1. NFPA 495 - Explosive Materials Code.

1.3 DEFINITIONS

A. Site Rock: Solid mineral material with volume in excess of 1/3 cu yd or solid material that cannot be removed with ¾ cu yd capacity excavator without drilling or blasting.

B. Trench Rock: Solid mineral material with volume in excess of 1/6 cu yd or solid material that cannot be removed with ¾ cu yd capacity excavator without drilling or blasting.

1.4 SUBMITTALS

A. Section 01 33 00 – Submittal Procedures: Submittal procedures.

B. Survey Report: Submit survey report on conditions of buildings near locations of rock removal.

1.5 PROJECT CONDITIONS

A. Conduct survey and document conditions of buildings near locations of rock removal, prior to rock removal and photograph existing conditions identifying existing irregularities.

1.6 SCHEDULING

A. Section 01 31 13 – Project Coordination: Coordination and project conditions.

B. Schedule Work to avoid disruption to occupied buildings nearby.

31 23 16.26 – ROCK REMOVAL

Herbert, Rowland & Grubic, Inc. 31 23 16.26 - 2 000483.0450

PART 2 - PRODUCTS

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 31 13 – Project Coordination: Coordination and project conditions.

B. Verify site conditions and note subsurface irregularities affecting Work of this section.

3.2 PREPARATION

A. Identify required lines, levels, contours, and datum.

3.3 ROCK REMOVAL BY MECHANICAL METHOD

A. Excavate and remove rock by mechanical method.

B. Cut away rock at bottom of excavation to form level bearing.

C. Remove shaled layers to provide sound and un-shattered base for foundations.

D. In utility trenches, excavate to 6 inches below invert elevation of pipe and 24 inches wider than pipe diameter.

E. Remove excavated materials from site.

F. Correct unauthorized rock removal in accordance with backfilling and compacting requirements of Section 31 23 23, as directed by Engineer.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 – Quality Requirements: Field inspecting, testing, adjusting, and balancing.

B. Request visual inspection of foundation bearing surfaces by Engineer and inspection agency before installing subsequent work.

END OF SECTION 31 23 16.26