This is an electrical demolition plan sheet (EB201) for the California Department of Corrections and Rehabilitation (CDCR) at California State Prison, Los Angeles County located in Lancaster, CA. The document is part of a roof replacement project for Facility A 270 Housing Unit Building 334, specifically detailing the electrical demolition plan for the roof and partial second level. The project is being managed by M. Neil Engineering and is scheduled for implementation in August 2023, with working drawings dated 08/29/2023 and 09/13/2023.

The electrical demolition plan provides detailed instructions for removing and replacing existing electrical infrastructure, including conduits, junction boxes, and electrical circuits associated with HVAC and electrical equipment on the rooftop. Key specifications include placing existing electrical circuits in a "safe-off" condition, removing portions of existing conduits and wiring, replacing junction boxes and flex conduits, and maintaining circuit continuity. The plan includes specific notes about preserving fire alarm devices, replacing non-GFCI receptacles, and ensuring that new electrical installations match existing wiring sizes, quantities, and types. The document has received approval from the Office of the State Fire Marshal on 10/10/23 with the approval number 23-0002.

View the file

Other files

File Type Posted
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_14.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_30.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_36.pdf PDF
I-001104_-_21-040_-_002_-_Roof_Penetrations.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_10.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_37.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_9.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_13.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_32.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_48.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_26.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_21.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_51.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_6.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_31.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_25.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_38.pdf PDF
21-039_LAC_Replace_Roofs_Volume_1.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_34.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_40.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_7.pdf PDF
21-039_LAC_Replace_Roofs_Volume_2.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_23.pdf PDF
12_-_FPCM-LAC-I001104-M035-RS.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_47.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_42.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_33.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_12.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_16.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_3.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_20.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_18.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_46.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_39.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_35.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_22.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_5.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_24.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_28.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_43.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_15.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_50.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_4.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_19.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_49.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_8.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_29.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_17.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_41.pdf PDF
21-040-LAC_Replace-Roofs-Phase1_Final-Drawings_45.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3 1 1.8 2 6 4 5 7 8 9 1110

B.4

A

B

D

C

J

E

F

G

H

K

K.8

L

M

1 111.8 2 3 4 5 6 7 8 9 105.7 7.3

A

B

B.7

D

E.7

G.3

J

K.7

L

M

(E) 3/4" CONDUIT UP

THROUGH ROOF

(E)

(R)

(E) (3) 3/4" CONDUITS

IN PITCH POCKET

(E) 1-1/2" CONDUIT UP

THROUGH ROOF

(E) (3) 3/4" CONDUITS

IN PITCH POCKET

(E) (2) 3/4" CONDUITS

IN PITCH POCKET

J

(E) 3/4" CONDUIT UP

THROUGH ROOF TO

J-BOX

(R)

(E) 1-1/2" CONDUIT UP

THROUGH ROOF

(E) MAIN CIRCUIT

BREAKER

DISCONNECT

J

(R)

(E) CONTROL

PANELS

(E) MAIN CIRCUIT

BREAKER

DISCONNECT

(E) 1-1/2" CONDUIT UP

THROUGH ROOF

(E) (4) 3/4" CONDUITS

UP THROUGH ROOF

(E) 3/4" CONDUIT UP

THROUGH ROOF TO

J-BOX

J

(E) 3/4" CONDUIT UP

THROUGH ROOF TO

J-BOX

(R)

(E) 1-1/2" CONDUIT UP

THROUGH ROOF

(E) (4) 3/4" CONDUITS

UP THROUGH ROOF

(E) CONTROL

PANELS

(E) MAIN CIRCUIT

BREAKER

DISCONNECT

(E) BEACON 7

(E) 1/2" CONDUIT ON

TOP OF PARAPET

J

(E) 3/4" CONDUIT UP

THROUGH ROOF

(E) 3/4" CONDUIT DOWN

SIDE OF BUILDING

(E) 3/4" CONDUIT

(E) (1) 3/4" CONDUIT

AND (E) 1/2" CONDUIT

J

(E) GUARD SHACK

(E) 3/4" CONDUIT ON

PARAPET WALL

(E) 3/4" CONDUIT UP

THROUGH ROOF

(E) 3/4" CONDUIT ON

TOP OF PARAPET

(E)

(E) (3) 3/4" CONDUITS

UP THROUGH ROOF

TO DUCT DETECTORS

AND CONTROLS

(E) CONDUIT

DOWN WALL

(E) 1" CONDUIT UP

THROUGH PLATFORM

(E) (3) 3/4" CONDUITS

UP THROUGH ROOF

TO DUCT DETECTORS

AND CONTROLS

(E) (3) 3/4" CONDUITS

UP THROUGH ROOF

TO DUCT DETECTORS

AND CONTROLS

(E) CONTROL

PANELS

(E) (4) 3/4" CONDUITS

UP THROUGH ROOF

11 8 9 10

G.3

J

K.7

L

M

SLO

PE

SLO

PE

7 7.3

J (E)

J

J

(E) CONDUIT ON

WALL TO REMAIN

NUMBERED NOTES

GENERAL NOTES

1. PLACE ALL EXISTING ELECTRICAL CIRCUITS FEEDING EXISTING HVAC AND ELECTRICAL EQUIPMENT ON

ROOFTOP IN A "SAFE-OFF" CONDITION, PRIOR TO CONSTRUCTION. NO NEW LOADS ADDED TO

CIRCUITS.

2. REMOVE PORTIONS OF EXISTING CONDUITS AND WIRING NECESSARY TO RE-ROOF EXISTING

BUILDING.

3. DO NOT DAMAGE DURING CONSTRUCTION AND REUSE ALL EXISTING CIRCUITS, PROVIDE NEW HVAC DISCONNECTS, PROVIDE NEW WEATHERPROOF GFCI SERVICE RECEPTACLES TO REPLACE EXISTING

RECEPTACLES FOR REMODEL.

4. REMOVE EXISTING JUNCTION BOXES AND FLEX CONDUITS BACK TO ROOF PENETRATION POINT, AND DO NOT REUSE. REPLACE ALL ABOVE ROOF CONDUITS WITH NEW - WIRING SIZE, QUANTITY AND TYPE SHALL MATCH EXISTING. SPLICE IN POWER WIRING IS NOT ACCEPTABLE. NEW CONTROL WIRING TO HVAC EQUIPMENT MAY ONLY BE INSTALLED FOR THE RUN FROM THE EQUIPMENT CONTROL PANEL TO

THE NEAREST EXISTING TERMINATION POINT OR SPLICE LOCATION. INSTALL NEW EMT WITH

COMPRESSION FITTINGS AND LIQUID-TIGHT METAL CONDUIT TERMINATION AT THE MECHANICAL

EQUIPMENT .

5. DO NOT DAMAGE HVAC DUCTS WITH DUCT DETECTORS. MAINTAIN FIRE ALARM DEVICE AND CIRCUIT

DURING CONSTRUCTION.

6. DO NOT DAMAGE WP SERVICE RECEPTACLE BACK BOXES. REMOVE ANCHORING, AS NEEDED, TO

ALLOW MOVEMENT DURING ROOFING REPAIR. MAINTAIN CIRCUIT CONTINUITY AND RECEPTACLE

FUNCTIONALITY AFTER CONSTRUCTION.

7. REPLACE JUNCTION BOXES. REPLACEMENT BOX TO MATCH EXISTING TYPE AND SIZE.

EXISTING MECHANICAL UNIT TO BE DISCONNECTED FOR ROOF REPAIR. COORDINATE WITH

MECHANICAL. REINSTALL USING NEW ELECTRICAL CONDUIT, CONDUCTORS AND DEVICES.

CONDUIT SIZE, WIRING SIZE, QUANTITY AND TYPE SHALL MATCH EXISTING. SEE REMODEL PLAN

"1/EB301".

EXISTING NON-GFCI RECEPTACLE TO BE REPLACED. SEE REMODEL PLAN "1/EB301".

EXISTING RSC LOCATED ON ROOF TO BE REMOVED TO ALLOW FOR RE-ROOFING. EXISTING

CONDUIT TO BE REPLACED WITH NEW AFTER NEW ROOF IS INSTALLED. MAINTAIN CONTINUITY OF EXISTING CIRCUITING RUNNING IN THE THE CONDUIT. FIELD VERIFY QUANTITIES AND SIZES.

EXISTING RSC LOCATED ON TOP OF PARAPET TO BE REMOVED TO ALLOW FOR RE-ROOFING.

EXISTING CONDUIT TO BE REPLACED WITH NEW AFTER NEW ROOF IS INSTALLED. MAINTAIN

CONTINUITY OF EXISTING CIRCUITING RUNNING IN THE THE CONDUIT. FIELD VERIFY QUANTITIES

AND SIZES.

EXISTING RSC LOCATED ON PARAPET WALL TO BE REMOVED TO ALLOW FOR RE-ROOFING.

EXISTING CONDUIT TO BE REPLACED WITH NEW AFTER NEW ROOF IS INSTALLED. MAINTAIN

CONTINUITY OF EXISTING CIRCUITING RUNNING IN THE THE CONDUIT. FIELD VERIFY QUANTITIES

AND SIZES.

EXISTING WALL MOUNTED LIGHT FIXTURE TO BE REMOVED

EXISTING BEACON MOUNTED HIGH ON WALL TO REMAIN. PROTECT EXISTING BEACON AND

ASSOCIATED MOUNTING EQUIPMENT DURING CONSTRUCTION. IF EQUIPMENT MUST BE

TEMPORARILY RELOCATED FOR NEW ROOF INSTALLATION, THEN REINSTALL AFTER ROOF

INSTALLATION. MAINTAIN ALL EXISTING CONNECTIONS.

SHEET NUMBER

S

TA

TE

O

F C A

LI

FO

R N

IA

D E P A R

TM

E N T

O F

C O

R R E C

TI

O

N S A

N D

R E H

A B

IL

IT

A

TI

O N

FA

C

IL

IT

Y P

LA

N N

IN

G , C

O N S

TR

U C

TI

O

N A

N D

M A N A G

E M

E N

T D

IV

IS

IO

N

DE

SI

G N

SE

RV

IC

ES

A

ND

S

TA

ND

AR

DS

B

RA

NC

H

DE

SI

G

N

SE

RV

IC

ES

S

EC

TI

O N

APPROVAL

L A C

V1

C A L

IF

O R

N

IA

S T A T E P

R

IS

O N L O

S A

N G

E L E S C

O U N T Y

T H

S T R

E E T , W

E S T

LA

N C

A S T E R

, C A

.1

Electrical Engineers Lighting Designers

100 Howe Ave., Suite 235N

Sacramento, CA 95825-8217

PROJECT #:

www.mneilsengineering.com

Tel: (916) 923-4400

PROJECT MGR: Stuart LinGsa\

21318.21

08/29/2023

R E P L A C E R

O O

F S

P H

A S E

A U G

U S T

W O

R K

IN

G D

R A W

IN

G

S

EB201

F A

C

IL

IT

Y A

H

O U

S

IN

G U

N

IT

B U

IL

D

IN

G

R

O O

F P

L A

N

D E M

O L

IT

IO

N

E

L E C

T R

IC

A L

1/8"=1'-0"

ROOF PLAN - DEMOLITION - ELECTRICAL2

EB201

PARTIAL SECOND LEVEL AND

FACILITY A 270 HOUSING UNIT BUILDING 334

1/8"=1'-0"

FACILITY A 270 HOUSING UNIT BUILDING 334 ROOF PLAN - DEMOLITION - ELECTRICAL1

EB201

5'

1/8" = 1'-0"

0 25'10' 15' 20'

GRAPHIC SCALE

N

N

09/13/2023

V1

OFFICE OF THE STATE FIRE MARSHAL

shall be available on the project site at all times.

10/10/23

APPROVED FIRE AND PANIC ONLY

Approval of this plan does not authorize or approve any omission or deviation from applicable regulations. Final approval is subject to field inspection. One set of approved plans