01 78 39 - Project Record Documents.pdf

PDF 217 KB Posted

Attached to
WCTA Meter Replacement Project
Solicitation number
US.257570
Issued by
Lancaster County, Pennsylvania

About this file

This file is a Project Record Documents specification section (01 78 39) prepared by Herbert, Rowland & Grubic, Inc. for the West Cocalico Township Authority (WCTA) Meter Replacement Project in Pennsylvania. The specification establishes requirements for maintaining comprehensive project record documentation throughout the construction phase of the WCTA's water meter replacement initiative, which involves replacing approximately 790 water meters with new Automated Meter Infrastructure (AMI) meters across West Cocalico Township. The contractor is required to maintain one complete set of record documents on-site, including specifications, addenda, change orders, reviewed shop drawings, product data, samples, and manufacturer's instructions. Record entries must be completed concurrently with construction progress on a weekly basis at minimum, with all information legibly marked and stored separately from construction documents to enable future reference by the Owner.

The specification requires detailed documentation of all products actually installed, including manufacturer names, model numbers, supplier information, product substitutions or alternates, and changes made through addenda or modifications. Additionally, the contractor must assemble miscellaneous records including a digital database of all installation data, property owner correspondence and coordination documentation as outlined in Section 01 35 13, and equipment photographs per Section 01 32 33. All record documents must be bound or filed and properly identified, with entries maintained as complete and accurate reference materials for the Owner's future use.

View the file

Other files

File Type Posted
01 64 00 - Owner Furnished Products.pdf PDF
00 73 73a Steel Products Procurement Certification.pdf PDF
00 01 01 LA Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
4-Bid Summary - EVP Edited .pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 63 63 - Change Order Form.pdf PDF
00 62 76 - App for Payment.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 73 46a - Wage Determination Schedule.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
00 73 46 - Wage Determination Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 35 13 - Special Project Requirements.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 10 00 - Project Summary.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
3-00 91 13 - Addenda No. 1.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 42 00 - References.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 32 26 - Construction Progress Reporting.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 39 – PROJECT RECORD DOCUMENTS

Herbert, Rowland & Grubic, Inc. 01 78 39 - 1 25-331-07

SECTION 01 78 39 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project record documents.

2. Miscellaneous Record Submittals

B. Related Sections:

1. Section 01 77 00 - Closeout Procedures: general closeout procedures.

2. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 PROJECT RECORD DOCUMENTS

A. Maintain on Site one set of the following record documents; record actual revisions to the Work:

1. Specifications.

2. Addenda.

3. Change Orders and other modifications to the Contract.

4. Reviewed Shop Drawings, product data, and Samples.

5. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

2. Suppliers name and contact.

3. Product substitutions or alternates used.

4. Changes made by Addenda and modifications.

1.3 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:

1. Digital database containing all installation data as outlined in Section 01 35 13 –

Special Project Requirements.

2. Property owners correspondence and coordination documentation as outline in

Section 01 35 13 - Special Project Requirements.

3. Equipment photographs as outlined in Section 01 32 33 – Photographic

Documentation.

01 78 39 – PROJECT RECORD DOCUMENTS

Herbert, Rowland & Grubic, Inc. 01 78 39 - 2 25-331-07

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project record documents.
2. Miscellaneous Record Submittals
B. Related Sections:
1. Section 01 77 00 - Closeout Procedures: general closeout procedures.
2. Individual Sections for specific requirements for Project Record Documents of the Work in those Sections.
1.2 PROJECT RECORD DOCUMENTS
A. Maintain on Site one set of the following record documents; record actual revisions to the Work:
1. Specifications.
2. Addenda.
3. Change Orders and other modifications to the Contract.
4. Reviewed Shop Drawings, product data, and Samples.
5. Manufacturer's instruction for assembly, installation, and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress, not less than weekly.
E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:
1. Manufacturer's name and product model and number.
2. Suppliers name and contact.
3. Product substitutions or alternates used.
4. Changes made by Addenda and modifications.
1.3 MISCELLANEOUS RECORD SUBMITTALS
A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:
1. Digital database containing all installation data as outlined in Section 01 35 13 – Special Project Requirements.
2. Property owners correspondence and coordination documentation as outline in Section 01 35 13 - Special Project Requirements.
3. Equipment photographs as outlined in Section 01 32 33 – Photographic Documentation.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.