00 65 16 - Certificate of Substantial Completion.pdf

PDF 253 KB Posted

Attached to
WCTA Meter Replacement Project
Solicitation number
US.257570
Issued by
Lancaster County, Pennsylvania

About this file

This is a Certificate of Substantial Completion form, modified from the EJCDC C-625 standard document, related to the West Cocalico Township Authority (WCTA) Meter Replacement Project in Pennsylvania. The certificate is used to formally document when work has been inspected and determined to be substantially complete by authorized representatives of the Owner, Contractor, and Engineer. The document establishes the Date of Substantial Completion, which marks the commencement of the contractual correction period and applicable warranties. The certificate notes that a punch list of items to be completed or corrected is attached and acknowledges that the failure to include items on the punch list does not relieve the Contractor of its obligation to complete all work in accordance with the Contract Documents. The form provides sections to document amendments to both Owner and Contractor responsibilities regarding security, operation, safety, maintenance, heat, utilities, insurance, and warranties upon the Owner's use or occupancy of the Work.

The Certificate of Substantial Completion does not constitute acceptance of work that does not comply with the Contract Documents, nor does it release the Contractor from its obligation to complete all work as specified. The form requires execution by the Engineer, with signature, name, and title required. This document serves as a critical checkpoint in the project delivery process for the WCTA Meter Replacement Project, which involves the replacement of approximately 790 water meters with new AMI meters across West Cocalico Township, with bids due November 5, 2026, at 10:00 AM local time via PennBid and bid security required at 10 percent of the bid amount.

View the file

Other files

File Type Posted
01 64 00 - Owner Furnished Products.pdf PDF
00 73 73a Steel Products Procurement Certification.pdf PDF
00 01 01 LA Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
4-Bid Summary - EVP Edited .pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 63 63 - Change Order Form.pdf PDF
00 62 76 - App for Payment.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 73 46a - Wage Determination Schedule.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
00 73 46 - Wage Determination Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 35 13 - Special Project Requirements.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 10 00 - Project Summary.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
3-00 91 13 - Addenda No. 1.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 42 00 - References.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 32 26 - Construction Progress Reporting.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Modified EJCDC® C-625, Certificate of Substantial Completion. Prepared and published 2018 by the Engineers Joint Contract Documents Committee.

Herbert, Rowland & Grubic, Inc. 00 65 16 - 1 011364.0448

CERTIFICATE OF SUBSTANTIAL COMPLETION

Owner: Owner's Contract No.:

Contractor: Contractor’s Project No.:

Engineer: Engineer's Project No.:

Project: Contract Name:

This ☐ Preliminary ☐ Final Certificate of Substantial Completion applies to:

All Work The following specified portions of the Work:

[Describe the portion of the work for which Certificate of Substantial Completion is issued]

Date of Substantial Completion: [Enter date, as determined by Engineer]

The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor, and Engineer, and found to be substantially complete. The Date of Substantial Completion of the Work or portion thereof designated above is hereby established, subject to the provisions of the Contract pertaining to Substantial Completion.

The date of Substantial Completion in the final Certificate of Substantial Completion marks the commencement of the contractual correction period and applicable warranties required by the Contract.

A punch list of items to be completed or corrected is attached to this Certificate. This list may not be all-inclusive, and the failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.

Amendments of contractual responsibilities recorded in this Certificate should be the product of mutual agreement of Owner and Contractor; see Paragraph 15.03.D of the General Conditions.

The responsibilities between Owner and Contractor for security, operation, safety, maintenance, heat, utilities, insurance, and warranties upon Owner's use or occupancy of the Work must be as provided in the Contract, except as amended as follows:

Amendments to Owner's responsibilities: None As follows

[List amendments to Owner’s Responsibilities]

Amendments to Contractor's responsibilities: None As follows:

[List amendments to Contractor’s Responsibilities]

The following documents are attached to and made a part of this Certificate: [punch list; others documents]

This Certificate does not constitute an acceptance of Work not in accordance with the Contract Documents, nor is it a release of Contractor's obligation to complete the Work in accordance with the Contract.

EXECUTED BY ENGINEER:

By:

(Authorized signature)

Name:

Title:

File details come from the government source that posted it. Updated .