About this file
This is a Project Summary document for the West Cocalico Township Authority (WCTA) Meter Replacement Project, a water utility infrastructure initiative in Pennsylvania. The project involves the replacement of approximately 790 water meters with new Automatic Meter Infrastructure (AMI) meters across West Cocalico Township. Bids for the construction work will be received online via PennBid until Thursday, November 5, 2026 at 10:00 AM local time, at which point submitted bids will be opened publicly. Prospective bidders are required to register with the PennBid website to access official bidding documents, addenda, and project updates. All inquiries regarding the meaning or intent of bidding documents must be submitted through PennBid in accordance with the Instructions to Bidders; telephone inquiries are not acceptable.
Bid security in the form of a Certified Check or Bid Bond must accompany each bid submission in an amount not less than 10% of the bid price. All official notifications, addenda, and bidding documents will be provided exclusively through the designated PennBid website, and neither the Owner nor Engineer will assume responsibility for bidding documents obtained from alternative sources. For complete requirements regarding bid submittal procedures, bidder qualifications, and contract award criteria, prospective bidders must consult the Instructions to Bidders included in the full bidding documents package available on the PennBid platform.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 10 00 – PROJECT SUMMARY
Herbert, Rowland & Grubic, Inc. 01 10 00-1 011364.0448
SECTION 01 10 00 – PROJECT SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Access to site.
4. Hazardous environmental condition.
5. Coordination with occupants.
6. Work restrictions.
7. Intent of Contract Documents.
1.2 PROJECT INFORMATION
A. Project Identification: WCTA Meter Replacement Project.
1. Project Location: West Cocalico Township.
B. Owner: West Cocalico Township Authority.
1. Owner's Representative:
a. Carolyn Hildabrand, Township Manager.
C. Engineer: Herbert, Rowland & Grubic, Inc., 1848 Charter Lane, Suite 214, Lancaster, PA 17601.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Project generally includes, but is not limited to, the installation of roughly 790 water meters with new AMI transmitters across the West Cocalico Township Authority service area.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 ACCESS TO SITE
A. Contractor is responsible for obtaining Homeowner permissions for entering each site.
B. Use of Site: Do not disturb portions of Project site beyond areas in which the Work is indicated:
1. Limits: Confine construction operations areas where work is being completed.
2. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
Herbert, Rowland & Grubic, Inc. 01 10 00-2 011364.0448
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.
Repair damage caused by construction operations.
D. Cleaning:
1. Continuously keep rights-of-way, storage areas, streets, roads, highways and adjacent properties free from accumulations of waste materials, excess excavation, rubbish and windblown debris resulting from construction operations.
2. Broom or water clean paved surfaces and remove surplus materials, tools, construction equipment and machinery as each work area is completed.
E. Protection:
1. Contractor shall make every effort to protect and avoid damage within the work area. Prior to the commencement of construction, the Contractor, Owner, and Engineer's representatives will meet to identify special needs and desires.
2. Contractor shall make every effort to protect and avoid damage to trees or shrubbery within the work area that are not designated for removal. Prior to the commencement of construction, the Contractor, Owner, and Engineer's representatives will meet to identify special needs and desires. The Contractor can anticipate that certain trees will be tagged for preservation.
3. The Contractor shall adequately close and/or protect all excavations, equipment, and materials stored within the site of the project.
4. It shall be the responsibility of the Contractor not to interfere with or create any hazards to traffic. No equipment or material will be stored or permitted to stand where traffic must be maintained. It shall be the responsibility of the Contractor to control dust on all roads, drives, walkways, and parking areas on which traffic is being maintained.
5. The Contractor shall take special care and attention and be responsible for the protection of all existing equipment located throughout the Project area. The Contractor shall immediately notify both the Owner, Engineer, and any authority having jurisdiction should a spill or other incident occur that may cause damage to adjacent structure, infrastructure, natural resource, etc.
F. Public Relations:
1. Contractor's attention is directed to the fact that, in the eyes of the general public, his conduct and attitude will be closely associated with that of the Owner.
Accordingly, where operations of the Contractor require personal contact with the public, the Contractor and all his employees shall conduct themselves in a courteous and respectful manner. Any violation of this section shall be considered sufficient cause for the Owner to order discharge of the employee involved, and he shall not be employed again on the work without written permission from the Owner.
Herbert, Rowland & Grubic, Inc. 01 10 00-3 011364.0448
2. Contractor shall use all means necessary to control dust on and near the work, including off-site borrow and stockpile areas if such dust is caused by the Contractor's operations. Thoroughly moisten all surfaces as required to prevent dust from being a nuisance to the public, neighbors, and concurrent performance of other work on the site.
3. In carrying out the work, the Contractor shall interfere as little as possible with traffic. The Contractor shall provide and maintain ingress and egress for all residents along the construction route.
4. Contractor shall be responsible for notifying all local emergency services, school districts, and other public agencies with regard to control and maintenance of traffic in the work area.
5. The Contractor shall obey and follow all posted speed limits.
1.5 HAZARDOUS ENVIRONMENTAL CONDITION
A. The Contractor shall complete any mitigation in accordance with all local, state and federal laws and regulations.
1.6 COORDINATION WITH OCCUPANTS
A. Homeowner Occupancy: Homeowner will occupy the premises during entire construction period. Cooperate with Homeowner during construction operations to minimize conflicts and facilitate installation. Perform the Work so as not to interfere with Homeowner's operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.
1.7 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Engineer and Owner not less than 2 days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
Herbert, Rowland & Grubic, Inc. 01 10 00-4 011364.0448
1.8 INTENT OF CONTRACT DOCUMENTS
A. The intent and meaning of the Contract Documents is that the Contractor, under the terms of the Contract, will take such action as necessary and/or required to provide labor, supervision, plant, materials, supplies, equipment, power, transportation, facilities, etc., whether temporary or permanent, which are indicated or may be reasonably inferred from each Drawing and each section of these Specifications, all of which are collectively necessary and/or required for the execution of the Work.
B. The information shown on the Contract Drawings or referenced herein relative to the depiction of existing facilities is shown for information purposes only. No representatives or warranties are given or implied relative to the accuracy thereof. The data is presented or described only to indicate the general and approximate extent of existing facilities. The Contractor shall consider these facilities in the preparation of his bid and include any contingent costs in those items for which payment will be made. No separate payment will be made for adjustments or modifications in the work due to inaccuracies in the nature or assumption of existing facilities, except as may be determined or warranted by the Owner/Engineer. Payment for changes in the work, if found necessary or prudent, shall be reimbursed only through procedure outlined in the General Conditions.
C. The Contractor will note that the Contract Drawings are general in detail and scope with respect to the extent of demolition, cutting, patching, removal of existing facilities, etc.
and that all such Work will be provided by the Contractor, whether specifically indicated on the Contract Drawings or not, which is necessary for the completion of the Work or for the proper operation and appearance of the finished installation, in accordance with the intent of the Contract Documents for this Project.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.
END OF SECTION