01 31 19 - Project Meetings.pdf

PDF 223 KB Posted

Attached to
WCTA Meter Replacement Project
Solicitation number
US.257570
Issued by
Lancaster County, Pennsylvania

About this file

This document is a Scope of Work section detailing project meeting requirements for the WCTA Meter Replacement Project in West Cocalico Township, Pennsylvania. The project involves the replacement of approximately 790 water meters with new Automated Meter Infrastructure (AMI) meters across West Cocalico Township Authority's service area. Bids for the construction project are to be submitted online via PennBid until Thursday, November 5, 2026 at 10:00 AM local time, with bid results to be posted publicly following opening. The project requires a preconstruction meeting to be scheduled by the Engineer after Notice of Award and prior to work commencement, with mandatory attendance by the Engineer, Owner, Resident Project Representative, appropriate governmental agency representatives, major Subcontractors, and the Contractor. Progress meetings are required to be scheduled and administered throughout the work at maximum monthly intervals with similar attendee requirements.

The preconstruction meeting agenda encompasses 22 topics including Engineer's status during construction, project communication procedures, contract times, permits and approvals, work schedules, shop drawings, substitutions, payment applications, prevailing wage and payroll certifications, insurances, Steel Products Procurement Act certifications, safety and OSHA requirements, and control of work. Progress meetings shall address work progress, maintenance of schedules, field observations and problems, submittal status, quality and work standards, and other business relating to the work. The Engineer is responsible for recording and distributing meeting minutes within seven days to all participants, the Owner, and affected parties. Bid security in the form of a Certified Check or Bid Bond is required in an amount not less than 10%. All questions regarding bidding documents must be submitted via PennBid; telephone inquiries are unacceptable.

View the file

Other files

File Type Posted
01 64 00 - Owner Furnished Products.pdf PDF
00 73 73a Steel Products Procurement Certification.pdf PDF
00 01 01 LA Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
4-Bid Summary - EVP Edited .pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 63 63 - Change Order Form.pdf PDF
00 62 76 - App for Payment.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 73 46a - Wage Determination Schedule.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
00 73 46 - Wage Determination Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 35 13 - Special Project Requirements.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 10 00 - Project Summary.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
3-00 91 13 - Addenda No. 1.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 42 00 - References.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 32 26 - Construction Progress Reporting.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 31 19 - PROJECT MEETINGS

Herbert, Rowland & Grubic, Inc. 01 31 19 - 1 011364.0448

SECTION 01 31 19 - PROJECT MEETINGS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Preconstruction meeting.

B. Progress meetings.

1.2 PRECONSTRUCTION MEETING

A. Engineer will schedule and preside over meeting after Notice of Award and prior to commencement of Work at the site.

B. Attendance Required: Engineer, Owner, Resident Project Representative, appropriate governmental agency representatives, major Subcontractors, and Contractor.

1. Contractor Representation: Person vested with the authority to make necessary decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules.

C. Agenda:

1. Engineer's Status During Construction.

2. Resident Project Representative (RPR).

3. Project Communication Procedures.

4. Contract Times.

5. Project Site: Access and Rights-of-Way.

6. Permits and Approvals.

7. Field Engineering.

8. Changes in the Work procedures.

9. Work Schedule.

10. Shop Drawings.

11. Substitutions.

12. Job Conference Schedule.

13. Payment Applications.

14. Temporary Utilities.

15. Emergency Phone Numbers.

16. Field Office Facilities.

17. Subcontractors.

18. Prevailing Wage and Payroll Certifications.

19. Insurances.

20. Steel Products Procurement Act Certifications.

21. Safety and OSHA.

22. Control of Work.

D. Engineer will record minutes and distribute copies to participants, with copies each to Contractor(s), Owner, and those affected by decisions made.

01 31 19 - PROJECT MEETINGS

Herbert, Rowland & Grubic, Inc. 01 31 19 - 2 011364.0448

1.3 PROGRESS MEETINGS

A. Engineer will schedule and administer meetings throughout progress of the Work at maximum monthly intervals.

B. Attendance Required: Contractors and job superintendent, major Subcontractors and suppliers, and Engineer, and Owner.

1. Contractors representative shall be vested with the authority to make any decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules

C. Minimum Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Planned progress during succeeding work period.

4. Maintenance of Progress Schedule.

5. Field observations, problems, and decisions.

6. Identification of problems impeding planned progress.

7. Review of submittal schedule and status of submittals.

8. Coordination of projected progress.

9. Maintenance of quality and work standards.

10. Other business relating to Work.

D. Engineer will record minutes and distribute copies to participants within seven days after meeting, with one copy each Engineer, Owner, and those affected by decisions made.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION – Not Used.

END OF SECTION

PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Preconstruction meeting.
B. Progress meetings.
1.2 PRECONSTRUCTION MEETING
A. Engineer will schedule and preside over meeting after Notice of Award and prior to commencement of Work at the site.
B. Attendance Required: Engineer, Owner, Resident Project Representative, appropriate governmental agency representatives, major Subcontractors, and Contractor.
1. Contractor Representation: Person vested with the authority to make necessary decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules.
C. Agenda:
1. Engineer's Status During Construction.
2. Resident Project Representative (RPR).
3. Project Communication Procedures.
4. Contract Times.
5. Project Site: Access and Rights-of-Way.
6. Permits and Approvals.
7. Field Engineering.
8. Changes in the Work procedures.
9. Work Schedule.
10. Shop Drawings.
11. Substitutions.
12. Job Conference Schedule.
13. Payment Applications.
14. Temporary Utilities.
15. Emergency Phone Numbers.
16. Field Office Facilities.
17. Subcontractors.
18. Prevailing Wage and Payroll Certifications.
19. Insurances.
20. Steel Products Procurement Act Certifications.
21. Safety and OSHA.
22. Control of Work.

D. Engineer will record minutes and distribute copies to participants, with copies each to Contractor(s), Owner, and those affected by decisions made.

1.3 PROGRESS MEETINGS
A. Engineer will schedule and administer meetings throughout progress of the Work at maximum monthly intervals.
B. Attendance Required: Contractors and job superintendent, major Subcontractors and suppliers, and Engineer, and Owner.
1. Contractors representative shall be vested with the authority to make any decisions on behalf of the Contractor, and such decisions shall commit the Contractor to the agreed procedures, sequence of operations and time schedules
C. Minimum Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Planned progress during succeeding work period.
4. Maintenance of Progress Schedule.
5. Field observations, problems, and decisions.
6. Identification of problems impeding planned progress.
7. Review of submittal schedule and status of submittals.
8. Coordination of projected progress.
9. Maintenance of quality and work standards.
10. Other business relating to Work.

D. Engineer will record minutes and distribute copies to participants within seven days after meeting, with one copy each Engineer, Owner, and those affected by decisions made.

PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION – Not Used.