01 32 16 - Construction Progress Schedule - SMALL.pdf
PDF 244 KB Posted
- Attached to
- WCTA Meter Replacement Project
- Solicitation number
- US.257570
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a Construction Progress Schedule specification document for the WCTA Meter Replacement Project in Pennsylvania, prepared by Herbert, Rowland & Grubic, Inc. The specification establishes administrative and procedural requirements for the General Contractor's preparation, submittal, and maintenance of project schedules, including format, content, revisions, and distribution protocols. The contractor must submit a preliminary Gantt chart schedule within seven days of contract award covering all work items from project start to completion. The schedule must utilize Microsoft Project software in the latest version and be formatted as a horizontal bar chart with separate bars for each major work element, identifying the first work day of each week. The contractor is fully responsible for determining and including foreseeable weather delay days in the schedule based on normal anticipated weather conditions for the project location. Schedules must be revised monthly and whenever actual schedule performance for significant items varies more than seven days from the proposed schedule, with revised schedules submitted for each Application for Payment.
The specification requires the contractor to document the complete construction sequence by activity with beginning and completion dates, identify work phases and logically grouped activities, show accumulated completion percentages as of the first day of each month, and provide separate schedules for submittal dates including shop drawings, product data, samples, and owner-furnished products. The contractor must indicate the critical path with original baseline, delivery dates for owner-furnished products, and provide narrative reports defining problem areas, anticipated delays, schedule impacts, and corrective actions. Electronic copies must be distributed to the engineer, owner, other contractors, subcontractors, suppliers, and concerned parties. The specification includes no pricing terms, set-asides, or funding information, as it is purely a scheduling and documentation requirement specification rather than a contract award or pricing document.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 32 16 – CONSTRUCTION PROGRESS SCHEDULE
Herbert, Rowland & Grubic, Inc. 01 32 16-1 011364.0448
SECTION 01 32 16 – CONSTRUCTION PROGRESS SCHEDULE
PART 1 – GENERAL
1.1. SECTION INCLUDES
A. This Section includes administrative and procedural requirements for the preparation, submittal, and maintenance of the progress schedule, reporting progress of the Work, and Contract Time adjustments, including the following:
1. Format.
2. Content.
3. Revisions to schedules.
4. Submittals.
5. Distribution.
B. Refer to the General Conditions and the Agreement for definitions and specific dates of Contract Time.
C. The above listed Project schedules shall be used for evaluating all issues related to time for this Contract. The Project schedules shall be updated in accordance with the requirements of this Section to reflect the actual progress of the Work and the Contractor’s current plan for the timely completion of the Work. The Project schedules shall be used by the Owner and Contractor for the following purposes as well as any other purpose where the issue of time is relevant:
1. To communicate to the Owner the Contractor’s current plan for carrying out the
Work;
2. To identify work paths that is critical to the timely completion of the Work;
3. To identify upcoming activities on the Critical Path(s);
4. To evaluate the best course of action for mitigating the impact of unforeseen events;
5. As the basis for analyzing the time impact of changes in the Work;
6. As a reference in determining the cost associated with increases or decreases in the Work;
7. To identify when submittals will be submitted;
8. To prioritize the review of submittals;
9. To document the actual progress of the Work;
10. To evaluate resource requirements of the Contractor and the Owner;
11. To integrate the Work with the operational requirements of the Owner’s facilities;
12. To facilitate efforts to complete the Work in a timely manner.
13. To document the history of the Work.
1.2. RELATED SECTIONS
A. Section 01 10 00 – Project Summary.
B. Section 01 22 00 – Unit Prices.
Herbert, Rowland & Grubic, Inc. 01 32 16-2 011364.0448
C. Section 01 33 00 – Submittal Procedures.
D. Section 01 40 00 – Quality Requirements.
1.3. DEFINITIONS
A. Construction Schedule: A method of planning and scheduling a construction project utilizing a horizontal bar chart with a separate bar for each major portion of the Work or operation to make the schedule an effective tool for planning and monitoring the progress of the work.
B. Critical Path: The longest continuous chain of activities through the network at a given data date for the Schedule to a Contract Milestone or Contract Completion. Where the path to a specific Milestone has become negative, the Critical Path shall be the longest continuous chain of activities with the greatest amount of negative float.
C. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path.
2. Predecessor activity is an activity that must be completed before a given activity can be started.
D. Event: An event is the starting or ending point of an activity.
E. Milestone: A key or critical point in time for reference or measurement.
1.4. QUALITY ASSURANCE
A. Scheduling Software:
1. The Contractor shall use the latest version of Microsoft Project as the scheduling software system for use on this Project.
2. Standards: Comply with procedures contained in AGC's "Construction Planning
& Scheduling."
1.5. PRELIMINARY SCHEDULE
A. Preliminary Gantt schedule is to be prepared by the General Contractor and submitted to the Engineer within seven (7) days of award of contract. This schedule is to cover all items of Work from the start of the project up to the completion of the project. This schedule must be revised when the actual schedule of significant items varies more than one week from the proposed schedule.
1.6. CONSTRUCTION SCHEDULE FORMAT
A. Format: Utilize a horizontal bar chart (Gantt) with a separate bar for each major portion of the Work or operation, identifying first work day of each week.
B. Program: Use Microsoft Project, latest version.
Herbert, Rowland & Grubic, Inc. 01 32 16-3 011364.0448
C. Sequence of Listings: Utilize the Table of Contents of this Project Manual and the chronological order of the start of each item of work.
D. Scale and Spacing: Provide space for notations and revisions.
E. Sheet Size: To be coordinated with Construction Administrator.
F. Foreseeable Bad Weather Days Allowance: The Contractor shall include a separate identifiable activity on the Critical Path labeled "Foreseeable Bad Weather Days."
1. The Contractor shall be fully responsible for determining the number of weather delay days to be included in the Schedule. This determination shall be based on the normal anticipated weather for the project location and the nature of the project work. The Schedule shall be based on the Contractor’s determined weather delay allowance, but must meet the minimum shown in the General Conditions or Supplementary Conditions.
2. The Contractor shall insert an activity in the Schedule to reflect weather day occurrences when weather days are experienced. Identify this activity as a foreseeable weather delay.
3. The Contractor shall reduce duration of Foreseeable Bad Weather Days Allowance activity as weather delays are experienced and inserted into the schedule. Remaining days in Foreseeable Bad Weather Day Allowance at completion of project is considered float. Weather delay, when justified, are considered allowable, non-compensable.
1.7. CONTENT
A. Show complete sequence of construction by activity, with dates beginning and completion of each element of construction.
B. Identify work of separate phases and other logically grouped activities.
C. Show accumulated percentages of completion of each item, and total percentage of Work completed, as of the first day of each month.
D. Provide separate schedule of submittal dates for shop drawings, product data, and samples, Owner/Agency furnished products and any products identified as under Allowances, and dates reviewed submittals will be required from Engineer. Indicate decision dates for selection of finishes.
E. Indicate delivery dates for Owner/Agency furnished products.
F. Indicate critical path with original baseline indicated.
1.8. SUBMITTALS AND REVISIONS TO SCHEDULES
A. An initial bar graph schedule is to be prepared by the General Contractor and submitted.
B. Indicate progress of each activity to date of submittal, and projected completion date of each activity.
Herbert, Rowland & Grubic, Inc. 01 32 16-4 011364.0448
C. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes.
D. Provide narrative report to define problem areas, anticipated delays, and impact on Schedule. Report corrective action taken, or proposed, and its effect.
E. Schedules must be revised monthly and when the actual schedule of significant items varies more than seven (7) days from the proposed schedule.
F. Submit revised Construction Schedules for each Application for Payment.
G. Submit an electronic copy of the Construction Schedule.
1.9. DISTRIBUTION
A. Distribute copies of the computer-generated schedules to Engineer, Owner, other Contractors, Subcontractors, suppliers, and other concerned parties.
B. Instruct recipients to promptly report, in writing, problem anticipated by projections indicated in schedules.
PART 2 - PRODUCTS - Not Used.
PART 3 – EXECUTION – Not Used.
END OF SECTION
| PART 1 – GENERAL |
| A. This Section includes administrative and procedural requirements for the preparation, submittal, and maintenance of the progress schedule, reporting progress of the Work, and Contract Time adjustments, including the following: |
| 1. Format. |
| 2. Content. |
| 3. Revisions to schedules. |
| 4. Submittals. |
| 5. Distribution. |
| B. Refer to the General Conditions and the Agreement for definitions and specific dates of Contract Time. |
| C. The above listed Project schedules shall be used for evaluating all issues related to time for this Contract. The Project schedules shall be updated in accordance with the requirements of this Section to reflect the actual progress of the Work and ... |
| 1. To communicate to the Owner the Contractor’s current plan for carrying out the Work; |
| 2. To identify work paths that is critical to the timely completion of the Work; |
| 3. To identify upcoming activities on the Critical Path(s); |
| 4. To evaluate the best course of action for mitigating the impact of unforeseen events; |
| 5. As the basis for analyzing the time impact of changes in the Work; |
| 6. As a reference in determining the cost associated with increases or decreases in the Work; |
| 7. To identify when submittals will be submitted; |
| 8. To prioritize the review of submittals; |
| 9. To document the actual progress of the Work; |
| 10. To evaluate resource requirements of the Contractor and the Owner; |
| 11. To integrate the Work with the operational requirements of the Owner’s facilities; |
| 12. To facilitate efforts to complete the Work in a timely manner. |
| 13. To document the history of the Work. |
| A. Section 01 10 00 – Project Summary. |
| B. Section 01 22 00 – Unit Prices. |
| C. Section 01 33 00 – Submittal Procedures. |
| D. Section 01 40 00 – Quality Requirements. |
| A. Construction Schedule: A method of planning and scheduling a construction project utilizing a horizontal bar chart with a separate bar for each major portion of the Work or operation to make the schedule an effective tool for planning and monitorin... |
| B. Critical Path: The longest continuous chain of activities through the network at a given data date for the Schedule to a Contract Milestone or Contract Completion. Where the path to a specific Milestone has become negative, the Critical Path shall ... |
| C. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources. |
| 1. Critical activities are activities on the critical path. |
| 2. Predecessor activity is an activity that must be completed before a given activity can be started. |
| D. Event: An event is the starting or ending point of an activity. |
| E. Milestone: A key or critical point in time for reference or measurement. |
| A. Scheduling Software: |
| 1. The Contractor shall use the latest version of Microsoft Project as the scheduling software system for use on this Project. |
| 2. Standards: Comply with procedures contained in AGC's "Construction Planning & Scheduling." |
| A. Preliminary Gantt schedule is to be prepared by the General Contractor and submitted to the Engineer within seven (7) days of award of contract. This schedule is to cover all items of Work from the start of the project up to the completion of the p... |
| A. Format: Utilize a horizontal bar chart (Gantt) with a separate bar for each major portion of the Work or operation, identifying first work day of each week. |
| B. Program: Use Microsoft Project, latest version. |
| C. Sequence of Listings: Utilize the Table of Contents of this Project Manual and the chronological order of the start of each item of work. |
| D. Scale and Spacing: Provide space for notations and revisions. |
| E. Sheet Size: To be coordinated with Construction Administrator. |
| F. Foreseeable Bad Weather Days Allowance: The Contractor shall include a separate identifiable activity on the Critical Path labeled "Foreseeable Bad Weather Days." |
| 1. The Contractor shall be fully responsible for determining the number of weather delay days to be included in the Schedule. This determination shall be based on the normal anticipated weather for the project location and the nature of the project wo... |
| 2. The Contractor shall insert an activity in the Schedule to reflect weather day occurrences when weather days are experienced. Identify this activity as a foreseeable weather delay. |
| 3. The Contractor shall reduce duration of Foreseeable Bad Weather Days Allowance activity as weather delays are experienced and inserted into the schedule. Remaining days in Foreseeable Bad Weather Day Allowance at completion of project is considered... |
| A. Show complete sequence of construction by activity, with dates beginning and completion of each element of construction. |
| B. Identify work of separate phases and other logically grouped activities. |
| C. Show accumulated percentages of completion of each item, and total percentage of Work completed, as of the first day of each month. |
| D. Provide separate schedule of submittal dates for shop drawings, product data, and samples, Owner/Agency furnished products and any products identified as under Allowances, and dates reviewed submittals will be required from Engineer. Indicate decis... |
| E. Indicate delivery dates for Owner/Agency furnished products. |
| F. Indicate critical path with original baseline indicated. |
| A. An initial bar graph schedule is to be prepared by the General Contractor and submitted. |
| B. Indicate progress of each activity to date of submittal, and projected completion date of each activity. |
| C. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes. |
| D. Provide narrative report to define problem areas, anticipated delays, and impact on Schedule. Report corrective action taken, or proposed, and its effect. |
| E. Schedules must be revised monthly and when the actual schedule of significant items varies more than seven (7) days from the proposed schedule. |
| F. Submit revised Construction Schedules for each Application for Payment. |
| G. Submit an electronic copy of the Construction Schedule. |
| A. Distribute copies of the computer-generated schedules to Engineer, Owner, other Contractors, Subcontractors, suppliers, and other concerned parties. |
| B. Instruct recipients to promptly report, in writing, problem anticipated by projections indicated in schedules. |