01 26 13 - Requests for Interpretation.pdf

PDF 228 KB Posted

Attached to
WCTA Meter Replacement Project
Solicitation number
US.257570
Issued by
Lancaster County, Pennsylvania

About this file

This file is a specification section detailing the Requests for Interpretation (RFI) procedures for the WCTA Meter Replacement Project in West Cocalico Township Authority, Pennsylvania. The document establishes the protocol for contractors to request clarification on contract documents and specifications related to the replacement of approximately 790 water meters with new Automated Meter Infrastructure (AMI) meters across the township. RFIs must be submitted using the designated RFI Form (Document 00 63 13) through the Project Documentation Website or correspondence, with forms completely filled out and legible, submitted in consecutive numerical order, and each attachment page bearing the RFI number. RFIs originated by subcontractors or material suppliers must be submitted through and approved by the primary contractor before submission to the engineer; those sent directly to the engineer will be returned unanswered. For coordination issues, contractors must submit scaled drawings or sketches with suggested solutions; RFIs lacking this requirement will be returned unanswered.

RFIs cannot be used to request approval of submittals, substitutions, changes with known additional costs, or different work methods. Improper or frivolous RFIs—those not properly prepared or requesting information already available in the contract documents—will be processed at the engineer's standard hourly rate with costs deducted from contractor payments. The engineer will endeavor to respond to RFIs in a timely manner but does not guarantee response by contractor-requested dates if deemed too expeditious. The engineer may retain RFIs for discussion during scheduled project meetings for inclusion in meeting minutes. If a contractor believes an engineer's clarification results in additional cost or time, a Change Proposal must be submitted before proceeding with the work; answered RFIs do not constitute approval for extra work, and unanswered RFIs will be marked "Not Reviewed."

View the file

Other files

File Type Posted
01 64 00 - Owner Furnished Products.pdf PDF
00 73 73a Steel Products Procurement Certification.pdf PDF
00 01 01 LA Cover.pdf PDF
4-Bid Summary - EVP Edited .pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 63 63 - Change Order Form.pdf PDF
00 62 76 - App for Payment.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 73 46a - Wage Determination Schedule.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
00 73 46 - Wage Determination Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 35 13 - Special Project Requirements.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 10 00 - Project Summary.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
3-00 91 13 - Addenda No. 1.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 42 00 - References.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 32 26 - Construction Progress Reporting.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 26 13 – REQUESTS FOR INTERPRETATION

Herbert, Rowland & Grubic, Inc. 01 26 13 - 1 011364.0448

SECTION 01 26 13 – REQUESTS FOR INTERPRETATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Definitions.

2. Requests For Interpretation.

3. Engineer’s Response to RFIs.

B. Related Sections:

1. Document 00 60 00 – Project Forms.

2. Document 00 63 13 – RFI Form.

3. Section 01 26 00 – Contract Modification Procedures.

1.2 DEFINITIONS

A. Request For Information / Interpretation (RFI):

1. A properly prepared request for information / interpretation shall include a detailed written statement that indicates the specific Specification in need of clarification and the nature of the clarification requested:

a. Specifications shall be identified by Section number, page and paragraph.

2. Requests for Information: Request made by Contractor concerning items not indicated on drawings or contained in Contract Documents that is required to properly perform the work.

B. Improper and Frivolous RFIs:

1. RFIs that are not properly prepared, or

2. RFIs that request information that is clearly shown on the Contract Documents.

1.3 CONTRACTOR'S REQUESTS FOR INFORMATION

A. Format: Use form Document 00 63 13 – RFI Form:

1. Forms shall be completely filled in, and if prepared by hand, shall be fully legible after photocopying or scanning.

2. RFIs shall be submitted in numerical order with no breaks in the consecutive numbering.

3. Each page of attachments to RFIs shall bear the RFI number and shall be consecutively numbered in chronological order.

4. Submit RFI through Project Documentation Website or correspondence.

B. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract Documents will be deemed either "improper" or "frivolous".

1. Improper or Frivolous RFIs will be processed by the Engineer at the Engineer's standard hourly rate and Engineer will charge the Owner, and such costs will be

Herbert, Rowland & Grubic, Inc. 01 26 13 - 2 011364.0448 deducted from monies still due the Contractor. The Contractor will be notified by the Engineer prior to the processing of improper RFIs.

C. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Engineer shall be requested to make a clarification of the indeterminate item.

D. RFIs shall be originated by the Contractor:

1. RFIs from subcontractors or suppliers shall be submitted through, reviewed by, and approved by the Contractor prior to submittal to the Engineer.

2. RFIs from subcontractors or material suppliers sent directly to the Engineer shall not be accepted and will be returned unanswered.

E. In cases where RFIs are issued to request clarification of coordination issues, the Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale, and submit same with the RFI. RFIs which fail to include a suggested solution will be returned unanswered with a requirement that the Contractor submit a complete request.

F. RFIs shall not be used for the following purposes:

1. To request approval of submittals.

2. To request approval of substitutions.

3. To request changes which are known to entail additional cost or credit.

4. To request different methods of performing work.

G. Contractor shall allow a reasonable time for review and response time for RFIs:

1. The Engineer will endeavor to respond in a timely fashion to RFIs.

2. RFI shall state requested date/time for response, however, this requested date/time for response is not a guarantee that the RFI will be answered by that date/time if that date/time is too expeditious.

1.4 ENGINEER'S RESPONSE TO RFIs

A. Engineer will respond to RFIs on one of the following forms:

1. Properly prepared RFIs:

a. Response directly upon Request for Information / Interpretation form.

b. Request for Proposal.

2. Improper or Frivolous RFIs:

a. Notification of Processing Fee(s).

b. Unanswered RFIs will be returned with a notation: Not Reviewed.

3. Answers to properly prepared RFIs will be directly upon the RFI form as deemed appropriate by the Engineer.

B. Engineer may opt to retain RFIs for discussion during regularly scheduled project meetings for inclusion of responses in meeting minutes.

C. In the event the Contractor believes that a clarification by the Engineer results in additional cost or time, Contractor shall submit a Change Proposal and not proceed with the Work indicated by the RFI until a Change Order (or Work Change Directive) is prepared

Herbert, Rowland & Grubic, Inc. 01 26 13 - 3 011364.0448 and approved. RFIs shall not justify a cost increase in the work or a change in the project schedule:

1. Answered RFIs shall not be construed as approval to perform extra work.

2. Unanswered RFIs will be returned with a stamp or notation: Not Reviewed.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Definitions.
2. Requests For Interpretation.
3. Engineer’s Response to RFIs.
B. Related Sections:
1. Document 00 60 00 – Project Forms.
2. Document 00 63 13 – RFI Form.
3. Section 01 26 00 – Contract Modification Procedures.
1.2 DEFINITIONS
A. Request For Information / Interpretation (RFI):
1. A properly prepared request for information / interpretation shall include a detailed written statement that indicates the specific Specification in need of clarification and the nature of the clarification requested:
a. Specifications shall be identified by Section number, page and paragraph.

2. Requests for Information: Request made by Contractor concerning items not indicated on drawings or contained in Contract Documents that is required to properly perform the work.

B. Improper and Frivolous RFIs:
1. RFIs that are not properly prepared, or
2. RFIs that request information that is clearly shown on the Contract Documents.
1.3 CONTRACTOR'S REQUESTS FOR INFORMATION
A. Format: Use form Document 00 63 13 – RFI Form:
1. Forms shall be completely filled in, and if prepared by hand, shall be fully legible after photocopying or scanning.
2. RFIs shall be submitted in numerical order with no breaks in the consecutive numbering.
3. Each page of attachments to RFIs shall bear the RFI number and shall be consecutively numbered in chronological order.
4. Submit RFI through Project Documentation Website or correspondence.
B. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract Documents will be deemed either "improper" or "frivolous".
1. Improper or Frivolous RFIs will be processed by the Engineer at the Engineer's standard hourly rate and Engineer will charge the Owner, and such costs will be deducted from monies still due the Contractor. The Contractor will be notified by the Eng...
C. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Engineer shall be requested to make a clarification of the indeterminate item.
D. RFIs shall be originated by the Contractor:
1. RFIs from subcontractors or suppliers shall be submitted through, reviewed by, and approved by the Contractor prior to submittal to the Engineer.
2. RFIs from subcontractors or material suppliers sent directly to the Engineer shall not be accepted and will be returned unanswered.
E. In cases where RFIs are issued to request clarification of coordination issues, the Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale, and submit same with the RFI. RFIs which fail to include a suggested ...
F. RFIs shall not be used for the following purposes:
1. To request approval of submittals.
2. To request approval of substitutions.
3. To request changes which are known to entail additional cost or credit.
4. To request different methods of performing work.
G. Contractor shall allow a reasonable time for review and response time for RFIs:
1. The Engineer will endeavor to respond in a timely fashion to RFIs.
2. RFI shall state requested date/time for response, however, this requested date/time for response is not a guarantee that the RFI will be answered by that date/time if that date/time is too expeditious.
1.4 ENGINEER'S RESPONSE TO RFIs
A. Engineer will respond to RFIs on one of the following forms:
1. Properly prepared RFIs:
a. Response directly upon Request for Information / Interpretation form.
b. Request for Proposal.
2. Improper or Frivolous RFIs:
a. Notification of Processing Fee(s).
b. Unanswered RFIs will be returned with a notation: Not Reviewed.

3. Answers to properly prepared RFIs will be directly upon the RFI form as deemed appropriate by the Engineer.

B. Engineer may opt to retain RFIs for discussion during regularly scheduled project meetings for inclusion of responses in meeting minutes.
C. In the event the Contractor believes that a clarification by the Engineer results in additional cost or time, Contractor shall submit a Change Proposal and not proceed with the Work indicated by the RFI until a Change Order (or Work Change Directiv...
1. Answered RFIs shall not be construed as approval to perform extra work.
2. Unanswered RFIs will be returned with a stamp or notation: Not Reviewed.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION - Not Used.

File details come from the government source that posted it. Updated .