01 32 33 - Photographic Documentation.pdf

PDF 216 KB Posted

Attached to
WCTA Meter Replacement Project
Solicitation number
US.257570
Issued by
Lancaster County, Pennsylvania

About this file

This document is a Photographic Documentation specification section prepared by Herbert, Rowland & Grubic, Inc. for the West Cocalico Township Authority (WCTA) Meter Replacement Project in Pennsylvania. The project involves the replacement of approximately 790 water meters with new Automatic Meter Infrastructure (AMI) meters across West Cocalico Township. Bidding for this construction project is conducted online via PennBid, with bids due on Thursday, November 5, 2026 at 10:00 AM local time. Bid security is required in the form of a Certified Check or Bid Bond in an amount not less than 10%. The specification requires that all photographic documentation be submitted according to procedures outlined in Section 01 33 00 (Submittal Procedures) and Section 01 77 00 (Closeout Procedures).

The photographic documentation requirements specify that all images must be captured using cameras with a minimum sensor resolution of 8 megapixels and submitted in JPG format with a minimum resolution of 3200 by 2400 pixels in unaltered original files, date and time stamped, organized in folders named by address. All photographs must be in focus with maximum depth of field and must include metadata identifying the meter installation address and the date the photograph was taken. Required documentation includes photographs of existing meter installations and surrounding conditions prior to work, any pre-existing plumbing deficiencies or damage, evidence of leaks or tampering, close-up identification of water service line materials, removed meters with final readings and serial numbers, newly installed meters with initial readings and serial numbers, and complete new meter assemblies showing upstream and downstream connections and shut-off valves. Copyright usage rights to all photographic documentation must be transferred to the Owner for unlimited use and reproduction.

View the file

Other files

File Type Posted
01 64 00 - Owner Furnished Products.pdf PDF
00 73 73a Steel Products Procurement Certification.pdf PDF
00 01 01 LA Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
4-Bid Summary - EVP Edited .pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 63 63 - Change Order Form.pdf PDF
00 62 76 - App for Payment.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 73 46a - Wage Determination Schedule.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
00 73 46 - Wage Determination Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 35 13 - Special Project Requirements.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 52 00 - Agmnt btw Own and Cntr for Const Con Stip Price.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 10 00 - Project Summary.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
3-00 91 13 - Addenda No. 1.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 42 00 - References.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 32 26 - Construction Progress Reporting.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 33 – PHOTOGRAPHIC DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 33 - 1 011364.0448

SECTION 01 32 33 – PHOTOGRAPHIC DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Meter replacement photographs.

B. Related Sections:

1. Section 01 33 00 – Submittal Procedures: Procedures for submitting photographic documentation.

2. Section 01 77 00 – Closeout Procedures: Procedures for submitting photographic documentation as project record documents at Project closeout.

1.2 SUBMITTALS

A. Digital Photographs:

1. Camera: Minimum sensor resolution of 8 megapixels.

2. Format: JPG with minimum 3200 by 2400 pixels, in unaltered original files, with same aspect ratio as the sensor, uncropped, date and time stamped, in folder named by address (street name and number).

3. Identification: Provide the following information with each image description in file metadata tag:

a. Address of meter installation.

b. Date photograph was taken.

1.3 USAGE RIGHTS

A. Transfer copyright usage rights to Owner for unlimited use and reproduction of photographic documentation.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION

3.1 GENERAL

A. Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.

3.2 METER REPLACEMENT PHOTOGRAPHS

A. Provide photographs of the following:

1. Existing meter installation and surrounding conditions prior to any work being performed.

01 32 33 – PHOTOGRAPHIC DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 33 - 2 011364.0448

2. Any pre-existing plumbing deficiencies, damage, corrosion, code concerns, or other conditions that may affect the meter replacement.

3. Any active leaks, evidence of prior leaks, unauthorized connections, meter bypasses, or signs of tampering within the property.

4. Close-up photographs identifying the incoming water service line material, including documentation of the method used to determine the material type.

5. Existing meter removed, clearly showing the final meter reading and serial number.

6. New meter installed, clearly showing the initial meter reading and serial number.

7. New meter installation, showing the complete assembly, including upstream and downstream connections and shut-off valves.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Meter replacement photographs.
B. Related Sections:
1. Section 01 33 00 – Submittal Procedures: Procedures for submitting photographic documentation.
2. Section 01 77 00 – Closeout Procedures: Procedures for submitting photographic documentation as project record documents at Project closeout.
1.2 SUBMITTALS
A. Digital Photographs:
1. Camera: Minimum sensor resolution of 8 megapixels.
2. Format: JPG with minimum 3200 by 2400 pixels, in unaltered original files, with same aspect ratio as the sensor, uncropped, date and time stamped, in folder named by address (street name and number).
3. Identification: Provide the following information with each image description in file metadata tag:
a. Address of meter installation.
b. Date photograph was taken.
1.3 USAGE RIGHTS
A. Transfer copyright usage rights to Owner for unlimited use and reproduction of photographic documentation.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION
3.1 GENERAL
A. Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.
3.2 METER REPLACEMENT PHOTOGRAPHS
A. Provide photographs of the following:
1. Existing meter installation and surrounding conditions prior to any work being performed.
2. Any pre-existing plumbing deficiencies, damage, corrosion, code concerns, or other conditions that may affect the meter replacement.
3. Any active leaks, evidence of prior leaks, unauthorized connections, meter bypasses, or signs of tampering within the property.
4. Close-up photographs identifying the incoming water service line material, including documentation of the method used to determine the material type.
5. Existing meter removed, clearly showing the final meter reading and serial number.
6. New meter installed, clearly showing the initial meter reading and serial number.
7. New meter installation, showing the complete assembly, including upstream and downstream connections and shut-off valves.