This is an Agreement between Owner and Contractor for Construction Contract (Stipulated Price) executed between West Cocalico Township Authority and a contractor for the WCTA Meter Replacement Project. The work involves the replacement of approximately 790 water meters with new AMI (Advanced Metering Infrastructure) meters across West Cocalico Township. The contract establishes a substantial completion deadline of 200 days after the contract commencement date, with final completion and readiness for payment required within 230 days. Bids were received online via PennBid until Thursday, November 5, 2026 at 10:00 AM local time. Bid security is required in the form of a Certified Check or Bid Bond in an amount not less than 10 percent. Herbert, Rowland & Grubic, Inc. serves as the Engineer and Owner's representative for the project.

The contract price is based on the contractor's bid submitted with the agreement, subject to adjustment under the contract terms. Progress payments are made monthly on approximately the second Tuesday of each month at 90 percent of the value of work completed, with 10 percent retainage; retainage may be reduced to 5 percent once 50 percent or more of work is completed and performance remains satisfactory. Upon substantial completion, payment increases to 100 percent less 150 percent of the Engineer's estimate of remaining work on the punch list. Final payment is made upon completion and acceptance of work. The contractor shall pay liquidated damages of $500 per day for each day beyond the 200-day substantial completion deadline and $500 per day for each day beyond the 230-day final completion deadline. The contractor must provide performance and payment bonds and comply with Pennsylvania's Workers' Compensation Act of 1915. The agreement is governed by the exclusive jurisdiction of the Court of Common Pleas of Lancaster County, Pennsylvania.

View the file

Other files

File Type Posted
01 64 00 - Owner Furnished Products.pdf PDF
00 73 73a Steel Products Procurement Certification.pdf PDF
00 01 01 LA Cover.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
4-Bid Summary - EVP Edited .pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 63 63 - Change Order Form.pdf PDF
00 62 76 - App for Payment.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
00 73 46a - Wage Determination Schedule.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
00 73 46 - Wage Determination Schedule.pdf PDF
01 61 00 - Product Requirements.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 73 43 - Wage Rate Requirements.pdf PDF
00 45 36 EEO Certificate.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 35 13 - Special Project Requirements.pdf PDF
01 32 33 - Photographic Documentation.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
00 01 10 - Table of Contents.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 10 00 - Project Summary.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
3-00 91 13 - Addenda No. 1.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
01 42 00 - References.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 60 00 - Project Forms.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 63 13 - RFI Form.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
01 26 00 - Contract Modifications.pdf PDF
00 43 13 - Bid Bond PENAL SUM Form.pdf PDF
01 32 26 - Construction Progress Reporting.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Herbert, Rowland & Grubic, Inc. 00 52 00 - 1 011364.0448

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

AGREEMENT BETWEEN OWNER AND CONTRACTOR

FOR CONSTRUCTION CONTRACT (STIPULATED PRICE)

This Agreement is by and between West Cocalico Township Authority (“Owner”) and __________________________________________________ (“Contractor”).

Terms used in this Agreement have the meanings stated in the General Conditions and the Supplementary Conditions.

Owner and Contractor hereby agree as follows:

ARTICLE 1—WORK

1.1 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: The replacement of approximately 790 water meters with new AMI meters across West Cocalico Township.

ARTICLE 2—THE PROJECT

2.1 The Project, of which the Work under the Contract Documents is a part, is generally described as follows: WCTA Meter Replacement Project

ARTICLE 3—ENGINEER

3.1 The Owner has retained Herbert, Rowland, & Grubic, Inc. (“Engineer”) to act as Owner’s representative, assume all duties and responsibilities of Engineer, and have the rights and authority assigned to Engineer in the Contract.

3.2 The part of the Project that pertains to the Work has been designed by Engineer.

ARTICLE 4—CONTRACT TIMES

4.1 Time is of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

4.2 Contract Times: Days

A. The Work will be substantially complete within 200 days after the date when the Contract Times commence to run as provided in Paragraph 4.01 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions within 230 days after the date when the Contract Times commence to run.

4.3 Liquidated Damages

A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial and other losses if the Work is not completed and Milestones, if any, not achieved within the Contract Times, as duly modified. The parties also recognize the delays, expense, and difficulties involved in proving, in a legal or arbitration proceeding, the actual loss suffered by Owner if the Work is not completed on time.

Herbert, Rowland & Grubic, Inc. 00 52 00 - 2 011364.0448

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty):

1. Substantial Completion: Contractor shall pay Owner $500 for each day that expires after the time (as duly adjusted pursuant to the Contract) specified above for Substantial Completion, until the Work is substantially complete.

2. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times (as duly adjusted pursuant to the Contract) for completion and readiness for final payment, Contractor shall pay Owner $500 for each day that expires after such time until the Work is completed and ready for final payment.

3. Liquidated damages for failing to timely attain Milestones (if any), Substantial Completion, and final completion are not additive, and will not be imposed concurrently.

B. If Owner recovers liquidated damages for a delay in completion by Contractor, then such liquidated damages are Owner’s sole and exclusive remedy for such delay, and Owner is precluded from recovering any other damages, whether actual, direct, excess, or consequential, for such delay, except for special damages (if any) specified in this Agreement.

ARTICLE 5—CONTRACT PRICE

5.1 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents, the amounts that follow, subject to adjustment under the Contract:

A. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.

For all Unit Price Work, an amount equal to the sum of the extended prices (established for each separately identified item of Unit Price Work by multiplying the unit price times the actual quantity of that item).

The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer.

ARTICLE 6—PAYMENT PROCEDURES

6.1 Submittal and Processing of Payments

A. Contractor shall submit Applications for Payment in accordance with Article 15 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.

6.2 Progress Payments; Retainage

A. Owner shall make progress payments on the basis of Contractor’s Applications for Payment on or about the second Tuesday of each month during performance of the Work as provided in Paragraph 6.2.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

Herbert, Rowland & Grubic, Inc. 00 52 00 - 3 011364.0448

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Owner may withhold, including but not limited to liquidated damages, in accordance with the Contract.

a. 90 percent of the value of the Work completed (with the balance being retainage).

1) If 50 percent or more of the Work has been completed, as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, the retainage may be reduced from 10 percent to 5 percent; and

b. 90 percent of cost of materials and equipment not incorporated in the Work (with the balance being retainage).

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts set off by Owner pursuant to Paragraph 15.01.E of the General Conditions, and less 150 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the punch list of items to be completed or corrected prior to final payment.

6.3 Final Payment

A. Upon final completion and acceptance of the Work, Owner shall pay the remainder of the Contract Price in accordance with Paragraph 15.06 of the General Conditions.

6.4 Consent of Surety

A. Owner will not make final payment, or return or release retainage at Substantial Completion or any other time, unless Contractor submits written consent of the surety to such payment, return, or release.

6.5 Interest

A. No allowance for interest shall be made with respect to progress payments prior to Substantial Completion. The final payment due the Contractor from the Owner after the Engineer has certified Substantial Completion of the Work shall bear interest at a rate of ten percent per annum, such interest to begin to accrue from the date such payment shall become due and payable to Contractor; provided, however, that where the Owner has issued bonds to finance the project to which the Work relates, interest shall be payable to the Contractor at the rate of interest of the bond issue or at the rate of ten percent per annum, whichever is less.

ARTICLE 7—CONTRACT DOCUMENTS

7.1 Contents

A. The Contract Documents consist of all of the following:

1. This Agreement.

2. Bonds:

a. Performance bond (together with power of attorney).

Herbert, Rowland & Grubic, Inc. 00 52 00 - 4 011364.0448

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

b. Payment bond (together with power of attorney).

3. General Conditions.

4. Supplementary Conditions.

5. Specifications as listed in the table of contents of the project manual (copy of list attached).

6. Addenda (numbers _____ to _____, inclusive).

7. Exhibits to this Agreement (enumerated as follows):

a. Contractor’s Bid (pages _____ to _____, inclusive).

8. The following which may be delivered or issued on or after the Effective Date of the Contract and are not attached hereto:

a. Notice to Proceed.

b. Work Change Directives.

c. Change Orders.

d. Field Orders.

B. The Contract Documents listed in Paragraph 7.1.A are attached to this Agreement (except as expressly noted otherwise above).

C. There are no Contract Documents other than those listed above in this Article 7.

D. The Contract Documents may only be amended, modified, or supplemented as provided in the Contract.

ARTICLE 8—REPRESENTATIONS, CERTIFICATIONS, AND STIPULATIONS

8.1 Contractor’s Representations

A. In order to induce Owner to enter into this Contract, Contractor makes the following representations:

1. Contractor has examined and carefully studied the Contract Documents, including Addenda.

2. Contractor has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Contractor is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Contractor has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Contractor has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in

Herbert, Rowland & Grubic, Inc. 00 52 00 - 5 011364.0448

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (c) Contractor’s safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

8. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.

9. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. Contractor’s entry into this Contract constitutes an incontrovertible representation by Contractor that without exception all prices in the Agreement are premised upon performing and furnishing the Work required by the Contract Documents.

12. Contractor shall accept the provisions of the Workers’ Compensation Act of 1915, and any supplements or amendments thereof, and Contractor shall insure its liability thereunder or file with Owner a certificate of exemption from insurance issued by the Department of Labor and Industry of the Commonwealth of Pennsylvania.

13. Contractor shall assume all risk of damage or loss which may occur in the performance of the Work or any part thereof and with respect to any of the materials or other things done, furnished, and supplied by the Contractor, or used and employed in the Work and in the performance of this Agreement. Contractor shall assume all liability for, and shall indemnify and hold the Owner harmless from and against, all claims and expense resulting from accidents, negligence or other cause that may occur during the performance of the Work and this Agreement to any person or persons employed upon the Work or to any other person or persons who may be injured or to any property which may be damaged in any manner whatsoever by and during the performance of the Work, together with all costs (including attorneys’ fees costs of defense) incurred in connection with said claim or claims. The parties hereto agree that in any and all relevant respects the Contractor is to be considered as an independent contractor.

14. Contractor shall comply with Pennsylvania Act 187 of 1996 relating to the Pennsylvania One Call System.

Herbert, Rowland & Grubic, Inc. 00 52 00 - 6 011364.0448

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

8.2 Contractor’s Certifications

A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 8.2:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner,

(b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

8.3 Standard General Conditions

A. Owner stipulates that if the General Conditions that are made a part of this Contract are EJCDC® C-700, Standard General Conditions for the Construction Contract (2018), published by the Engineers Joint Contract Documents Committee, and if Owner is the party that has furnished said General Conditions, then Owner has plainly shown all modifications to the standard wording of such published document to the Contractor, through a process such as highlighting or “track changes” (redline/strikeout), or in the Supplementary Conditions.

8.4 Accounting Records

A. Contractor shall keep such full and detailed accounts of materials incorporated and labor and equipment utilized for the Work consistent with the requirements of Paragraph 13.01.E of the General Conditions and as may be necessary for proper financial management under this Agreement. Subject to prior written notice, Owner shall be afforded reasonable access during normal business hours to all Contractor’s records, books, correspondence, instructions, drawings, receipts, vouchers, memoranda, and similar data relating to the Cost of the Work and Contractor’s fee. Contractor shall preserve all such documents for a period of three years after the final payment by Owner.

8.5 The parties hereto consent to the exclusive jurisdiction of the Court of Common Pleas of Lancaster County, Pennsylvania, with respect to any dispute which may arise in connection with this Agreement or the enforcement thereof unless the parties mutually agree in writing to another form of dispute resolution.

8.6 This Agreement represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral.

Herbert, Rowland & Grubic, Inc. 00 52 00 - 7 011364.0448

EJCDC® C-520, Agreement between Owner and Contractor for Construction Contract (Stipulated Price). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement.

This Agreement will be effective on Date Signed by Owner (which is the Effective Date of the Contract).

Owner: Contractor:

(typed or printed name of organization) (typed or printed name of organization)

By: By:

(individual’s signature) (individual’s signature)

Date: Date:

(date signed) (date signed)

Name: Name:

(typed or printed) (typed or printed)

Title: Title:

(typed or printed) (typed or printed)

(If [Type of Entity] is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest: Attest:

(individual’s signature) (individual’s signature)

Title: Title:

(typed or printed) (typed or printed)

Address for giving notices: Address for giving notices:

Designated Representative: Designated Representative:

Name: Name:

(typed or printed) (typed or printed)

Title: Title:

(typed or printed) (typed or printed)

Address: Address:

Phone: Phone:

Email: Email:

(If [Type of Entity] is a corporation, attach evidence of authority to sign. If [Type of Entity] is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)

License No.:

(where applicable)

State: