01 78 36 - Warranties.pdf

PDF 473 KB Posted

Attached to
West Pump Station Replacement Project
Solicitation number
Not on record
Issued by
Chester County, Pennsylvania

About this file

This is a Warranties specification document (Section 01 78 36) for the West Pump Station Replacement Project being constructed by Northwestern Chester County Municipal Authority in Pennsylvania. The specification establishes comprehensive warranty requirements for all materials, equipment, and work incorporated into the project. Product warranties must be submitted within 10 days following the Date of Substantial Completion or Partial Utilization, formatted in three-ring binders with plastic covers on 8" x 11" pages, with two copies provided to the Owner. Warranties become valid upon issuance of the Certificate of Substantial Completion and shall be written in the Owner's name, running concurrent with other contractual warranties. For work items accepted after Substantial Completion, warranty documentation must be submitted within 10 days of each individual acceptance.

The specification requires that manufacturer disclaimers and limitations do not relieve the Contractor of its warranty obligations under the Contract Documents. Standard product warranties and special warranties must extend protection to the Owner and may not limit duties, obligations, rights, and remedies otherwise available under law. In the event of warranted work failure, the Contractor is responsible for all costs associated with replacement or rebuilding to acceptable condition, regardless of whether the Owner has benefited from prior use. Reinstated warranties following corrective work must be equal to the original warranty with equitable adjustment for depreciation. The Contractor must also remove and replace any collateral work damaged by the failure of warranted work or that requires removal to provide access for corrections.

View the file

Other files

File Type Posted
40 05 53 - Identification For Process Piping.pdf PDF
44 42 56 - Base Mounted Pumping System.pdf PDF
32 31 13 - chain link fences and gates.pdf PDF
32 05 13 - Soils For Exterior Improvements.pdf PDF
00 73 73 - Statutory Requirements.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
40 05 19 - Ductile Iron Process Pipe.pdf PDF
04 05 13 - Masonry Mortaring.pdf PDF
31 23 23.33 - Flowable Fill.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
07 31 13 - asphalt shingles.pdf PDF
00 65 16 - Certificate of Substantial Completion.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
26 27 16 - Electrical Panels & Enclosures.pdf PDF
01 31 19 - Project Meetings.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
01 32 16 - Construction Progress Schedule - SMALL.pdf PDF
00 63 49 - Work Change Directive Form.pdf PDF
40 66 16 - Firewall Hardware.pdf PDF
33 31 11 - Public Sanitary Sewerage Gravity Piping.pdf PDF
04 20 00 - Unit Masonry.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
07 71 23 - Manufactured Gutters and Downspouts.pdf PDF
32 91 19 - Landscape Grading.pdf PDF
41 22 23.19 - Monorail Electric Chain Hoists with Manual Geared Trolley.pdf PDF
00 41 16.b - Bid Frm for Const Contract 2018 - EC.pdf PDF
26 05 26 - Grounding.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
40 05 78.29 - Combination Air Valves For Wastewater Service.pdf PDF
01 40 00 - Quality Requirements.pdf PDF
00 65 19.19 - Consent of Surety to Final Payment.pdf PDF
00 45 46 Public Works Employment Verification Form.pdf PDF
40 05 61 - Gate Valves.pdf PDF
31 05 16 - aggregates for earthwork.pdf PDF
09 91 00 Painting.pdf PDF
08 13 13 - Standard Hollow Metal Doors.pdf PDF
00 61 13.13 - Performance Bond.pdf PDF
40 05 51 - Common Requirements For Process Valves..pdf PDF
00 73 43-1 - Certification Form llc-25 PA Dep L&I.pdf PDF
01 74 19 - Construction Waste Management and Disposal.pdf PDF
34 71 13 - Vehicle Barriers.pdf PDF
04 01 20 - Masonry Cleaning.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
00 21 13 - Instructions to Bidders.pdf PDF
00 61 13.16 - Payment Bond.pdf PDF
00 11 13 - Advertisement for Bids.pdf PDF
08 90 00 - LOUVERS AND VENTS.pdf PDF
40 05 63 - Ball Valves.pdf PDF
26 05 00 - Electrical General.pdf PDF
Show 40 more

Latest 50 of 171 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 36 – WARRANTIES

Herbert, Rowland & Grubic, Inc. 01 78 36 - 1 000483.0450

SECTION 01 78 36 – WARRANTIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Product warranty manuals.

2. Warranty requirements.

B. Related Sections

1. Section 01 77 00 – Closeout Procedures: general closeout procedures.

2. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 PRODUCT WARRANTIES

A. Warranties specified in individual Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents. Warranties shall be written in Owner’s name.

1. Standard Product Warranties are preprinted written warranties published by individual manufacturers for particular products and are specifically endorsed by the manufacturer to Owner.

2. Special Warranties are written warranties required by or incorporated into Contract Documents, either to extend time limits provided by standard warranties or to provide greater rights for Owner.

B. Submission requirements:

1. Submit documents to Owner and Engineer within 10 days following Date of

Substantial Completion or Partial Utilization. For item accepted after Date of Substantial Completion, submit documents within 10 days following each individual acceptance.

a. When special warranty is required to be executed by Contractor, or

Contractor and a subcontractor, supplier or manufacturer, prepare a written document that contains appropriate terms and identification, ready for execution by required parties. Submit a draft to Owner.

2. Submit information on 8½” x 11" pages, bound in three-ring binders with plastic covers. Prepare binder cover with title WARRANTIES AND BONDS, and title of Project and subject matter when multiple binders are needed.

a. Internally subdivide binder contents with permanent page dividers, logically organized with tabs clearly printed.

b. Quantity: Provide two copies of each volume to Owner.

1.3 WARRANTY REQUIREMENTS

A. Written warranties made to Owner are in addition to implied warranties and shall not limit duties, obligations, right and remedies otherwise available under Jaw, nor shall

01 78 36 – WARRANTIES

Herbert, Rowland & Grubic, Inc. 01 78 36 - 2 000483.0450 warranty periods be interpreted as limitations on time in which Owner can enforce such other duties, obligations, rights, or remedies.

B. Manufacturer's disclaimers and limitations on product warranties shall not relieve Contractor of warranty on Work that incorporates products, nor shall it relieve suppliers, manufacturers, and subcontractors required to countersign special warranties with Contractor.

C. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using appropriate form properly executed.

3. Refer to Sections for specific content requirements and particular requirements for submitting special warranties.

D. Warranties shall become valid and operative upon issuance of Certificate of Substantial Completion.

E. For items of Work delayed beyond Date of Substantial Completion, provide an updated schedule within 10 days after acceptance, listing date of acceptance as start of warranty.

F. Related Damages and Losses: When correcting warranted Work that has failed, remove and replace other Work that has been damaged as a result of such failure or that needs to be removed and replaced to provide access for correction of warranted Work.

G. Reinstatement of Warranty: In event of Work covered by warranty has failed, correct by replacement or rebuilding. Reinstate warranty by written endorsement. Reinstated warranty shall be equal to original warranty with an equitable adjustment for depreciation.

H. Replacement Cost:

1. Upon determining that Work covered by a warranty has failed replace or rebuild

Work to an acceptable condition in compliance with requirements of Contract Documents.

2. Contractor shall be responsible for cost of replacing or rebuilding defective Work regardless of whether Owner has benefited from use of Work through a portion of its anticipated useful service life.

PART 2 - PRODUCTS - Not Used

PART 3 - EXECUTION - Not Used

END OF SECTION 01 78 36